Hubbry Logo
search
logo

Venues of the 2012 Summer Olympics and Paralympics

logo
Community Hub0 Subscribers
Write something...
Be the first to start a discussion here.
Be the first to start a discussion here.
See all
Venues of the 2012 Summer Olympics and Paralympics

The 2012 Summer Olympics and Paralympics venues were mostly located in the host city of London, though some other events required facilities located elsewhere. Venues outside London (and England) included Hampden Park in Glasgow, Scotland, and the Millennium Stadium in Cardiff, Wales. Between the successful bid and the Olympics and Paralympics themselves, several details and venues changed.

The 2012 Games used a mixture of newly built venues, existing facilities and temporary facilities, some of them in well known locations such as Hyde Park and Horse Guards Parade. Some of the facilities are being reused in their Olympic form, while others were constructed so that they could either be reduced in size or moved elsewhere in the UK. The plans were intended to contribute to the regeneration of Stratford in east London which is the site of the Olympic Park and of the neighbouring Lower Lea Valley.

The venues within Greater London were divided into three zones: the Olympic Zone, the River Zone and the Central Zone. In addition to these were venues that, by necessity, are outside the boundaries of Greater London.

The IOC has a number of major blue-chip sponsors for the Olympics, who are entitled to have their name exclusively associated with the event. As a consequence, any other company that provided sponsorship was not permitted to use its name or branding during the games, which includes as part of the name of any venue. Thus, three Olympic venues were temporarily renamed for the duration of the Games:

The Olympic Zone encompassed all of the facilities within the 500 acres (2 km2) Olympic Park in Stratford. This park was developed on existing waste and industrial land, and is seven minutes by Olympic Javelin train from central London. The park contained in the following below:

1: - As part of Lee Valley VeloPark
2: - Hockey facilities moved to Eton Manor

The original plan called for the construction of five new indoor arenas, four in the Olympic Park, and one in the River Zone (see below). In order to save money this was reduced to two. The existing venues at Earls Court and Wembley Arena were added to the plans, and various sports were shuffled around to make this possible.

The construction of the Olympic Park itself commenced in 2006, with Murphy Group awarded the contract to remove the powerlines which crossed the site and move these into a tunnel to be dug beneath the site. Civil engineering companies Morrisons and Nuttalls were appointed to undertake the demolition and land remediation works, under the project management of WS Atkins. The pace of this speeded up with the closure of the roads crossing the Olympic Park in June 2007. The construction phase of the Olympic Park was managed by CLM, a consortium comprising CH2M Hill, Laing O'Rourke and Mace. This consortium is officially titled Delivery Partner, ODA. The earliest construction of venues commenced in April 2008 with the start of the main build on the Olympic Stadium by McAlpine, with the nearby energy centre to be constructed by EDF Energy. Work on the Aquatics Centre began later the same year. During the construction phase the workforce on-site is expected to peak at 9,000 operatives. Accidents during construction of the venues resulted in no deaths - the only time this has happened in the history of Olympic construction.

See all
User Avatar
No comments yet.