Welcome to the community hub built on top of the Mumbai Urban Transport Project Wikipedia article. Here, you can discuss, collect, and organize anything related to Mumbai Urban Transport Project. The purpose of the hub is to connect people, foster deeper knowledge, and help improve the root Wikipedia article.
Add your contribution
Inside this hub
Mumbai Urban Transport Project

The Mumbai Urban Transport Project (MUTP), is a project formulated by the Mumbai Metropolitan Region Development Authority (MMRDA) to bring about improvement in the traffic and transport situation in the Mumbai metropolitan region with the assistance of the World Bank.

Background Information

[edit]

Phase I

[edit]

Phase I began in 2002 and was completed in 2011.[1] The total estimated cost of the MUTP Phase I was 4,526 crore (US$540 million). Most of the money was spent on railway projects, while less than a fourth was spent on road projects.

The following projects were proposed to be implemented under MUTP:[2]

The road projects included in MUTP were the Santa Cruz – Chembur Link Road (SCLR) and the Jogeshwari - Vikhroli Link Road (JVLR).[3]

Railway Minister Dinesh Trivedi announced in 2012 that Phase I was completed.[4]

Phase II

[edit]

The projects proposed under MUTP–II were:[5][2]

Project Sanctioned cost (crore) Revised cost (crore)
CST-Kurla, 5th and 6th track 659 923.78
Mumbai Central-Borivali, 6th track 522 1049.91
Thane–Diva, 5th and 6th track 133 287.62
Extension of Harbor Line to Goregaon 103 147.60
1500 V DC to 25000 V AC power conversion 293 739.91
EMU train procurement 2930 3041.13
Maintenance facilities for EMU trains 205 323.67
Stabling lines for EMUs 141 178.91
Technical assistance 62 62
Resettlement and rehabilitation of PAPs 124 124
Station improvement and trespassing control 128 128
Total 5300 7006.53

Phase III

[edit]

Phase III of the Mumbai Urban Transport Project was approved on 8 December 2011. It will cost 52,000 crore (US$6.2 billion). The feasibility study for the project cost 100 million (US$1.2 million).[6] The project includes a fast corridor from Chhatrapati Shivaji Terminus to Panvel with a connection to the proposed new Navi Mumbai International Airport, extending the Harbour Line to Borivali, and multiple additional tracks being laid on existing routes. The project is scheduled for completion in 2031.[6]

Phase 3A

[edit]

The Union Cabinet approved Phase 3A of the MUTP on 7 March 2019. It will cost 33,690 crore (US$4.0 billion) shared equally by the Union and State Governments, and is scheduled to be completed within 5 years. Projects approved under Phase 3A include:

  • Procurement of 191 air-conditioned rakes
  • Extension of the Harbour Line from Goregaon up to Borivali
  • Segregation of suburban and long-distance traffic at Kalyan Yard
  • Implementing a Communications Based Train Control System
  • Revamping 19 railway stations
  • Additional capacity of existing lines
    • 5th and 6th lines between Borivali and Virar
    • 4th line between Kalyan and Asangaon
    • 3rd and 4th lines between Kalyan and Badlapur.[7][8]

Phase 3B

[edit]

It is under Consideration by MRVC in the view of "Third Mumbai".

1) Panvel - Vasai new suburban corridor

2) Asangaon - Kasara 4th line

3) Badlapur - Karjat 3rd & 4th lines