Recent from talks
Knowledge base stats:
Talk channels stats:
Members stats:
Cherokee Nuclear Power Plant
The Cherokee Nuclear Power Plant is an incomplete energy project 10 miles (16 km) outside Gaffney, South Carolina, United States. In the early 1970s, Duke Power started constructing a three-reactor nuclear power plant at the site. However, the project stalled due to economic problems by the early 1980s, leading to the project's eventual abandonment. In 1987, the power plant was the site of an underwater film studio built by Hollywood director James Cameron, for the film The Abyss.
On December 13, 2007, Duke Energy filed an application with the U.S. Nuclear Regulatory Commission to construct a new $5–6 billion two-unit nuclear power plant at William States Lee III Nuclear Generating Station near the Cherokee Nuclear Power Plant site. In November 2008, the estimated cost to complete the project was raised to $11 billion (equivalent to $16.4 billion in 2025).
Duke originally planned three reactors on the property. One reactor was partially completed when work was halted in 1982, and plans were scrapped for the other two. Duke halted construction at the site in 1983 after spending $633 million (equivalent to $2.05 billion in 2025). An uncertain economy, stringent federal regulations on nuclear plants, and a decrease in electrical use caused Duke Power to abandon the site in the early 1980s.
The Nuclear Steam Supply System (NSSS) for each unit was planned to be a pressurized water reactor manufactured by Combustion Engineering, Inc. The reactor fuel was planned to be zircaloy clad uranium dioxide with a maximum enrichment of 3.6 wt. percent. The NSSS would have had a guaranteed main steam flow of 17,185,000 pounds (7,795,000 kg) /hr., a warranted output of 3817 MWt, and a design point of 4018 MWt. The turbine generators were planned to be manufactured by General Electric. Each was planned to have a gross rated electrical output of 1,345 MW and a gross valves-wide-open (VWO) electrical output of 1,387 MW.
By 1988, Earl Owensby, a Shelby, North Carolina, businessman, had converted the former energy complex into a movie studio.
In 1987, director James Cameron debated whether to actually film in the ocean or on a film set during the process of writing his screenplay for The Abyss. He ultimately chose to film in a man-made environment due to the need to control dangers, cost and filming environment.
Cameron decided to use Cherokee Nuclear Power plant facility to film the underwater sequences involving the submerged drilling rig.
The turbine pit, which was a large irregularly-shaped structure, was modified to hold 2.2 million US gallons (8,300 m3) of water. But when cinematographer Al Giddings visited the site he found the potential tank was still not quite large enough for the production's needs. Cameron then investigated the original containment vessel for the reactor chamber, a cylindrical structure 200 feet (61 m) across, 55 feet (17 m) deep. Following modifications, this vessel was converted into a vat able to hold 7.5 million US gallons (28,000 m3) of water. This containment vessel became "A" tank while the smaller turbine pit was the "B" tank.
Hub AI
Cherokee Nuclear Power Plant AI simulator
(@Cherokee Nuclear Power Plant_simulator)
Cherokee Nuclear Power Plant
The Cherokee Nuclear Power Plant is an incomplete energy project 10 miles (16 km) outside Gaffney, South Carolina, United States. In the early 1970s, Duke Power started constructing a three-reactor nuclear power plant at the site. However, the project stalled due to economic problems by the early 1980s, leading to the project's eventual abandonment. In 1987, the power plant was the site of an underwater film studio built by Hollywood director James Cameron, for the film The Abyss.
On December 13, 2007, Duke Energy filed an application with the U.S. Nuclear Regulatory Commission to construct a new $5–6 billion two-unit nuclear power plant at William States Lee III Nuclear Generating Station near the Cherokee Nuclear Power Plant site. In November 2008, the estimated cost to complete the project was raised to $11 billion (equivalent to $16.4 billion in 2025).
Duke originally planned three reactors on the property. One reactor was partially completed when work was halted in 1982, and plans were scrapped for the other two. Duke halted construction at the site in 1983 after spending $633 million (equivalent to $2.05 billion in 2025). An uncertain economy, stringent federal regulations on nuclear plants, and a decrease in electrical use caused Duke Power to abandon the site in the early 1980s.
The Nuclear Steam Supply System (NSSS) for each unit was planned to be a pressurized water reactor manufactured by Combustion Engineering, Inc. The reactor fuel was planned to be zircaloy clad uranium dioxide with a maximum enrichment of 3.6 wt. percent. The NSSS would have had a guaranteed main steam flow of 17,185,000 pounds (7,795,000 kg) /hr., a warranted output of 3817 MWt, and a design point of 4018 MWt. The turbine generators were planned to be manufactured by General Electric. Each was planned to have a gross rated electrical output of 1,345 MW and a gross valves-wide-open (VWO) electrical output of 1,387 MW.
By 1988, Earl Owensby, a Shelby, North Carolina, businessman, had converted the former energy complex into a movie studio.
In 1987, director James Cameron debated whether to actually film in the ocean or on a film set during the process of writing his screenplay for The Abyss. He ultimately chose to film in a man-made environment due to the need to control dangers, cost and filming environment.
Cameron decided to use Cherokee Nuclear Power plant facility to film the underwater sequences involving the submerged drilling rig.
The turbine pit, which was a large irregularly-shaped structure, was modified to hold 2.2 million US gallons (8,300 m3) of water. But when cinematographer Al Giddings visited the site he found the potential tank was still not quite large enough for the production's needs. Cameron then investigated the original containment vessel for the reactor chamber, a cylindrical structure 200 feet (61 m) across, 55 feet (17 m) deep. Following modifications, this vessel was converted into a vat able to hold 7.5 million US gallons (28,000 m3) of water. This containment vessel became "A" tank while the smaller turbine pit was the "B" tank.
