Gomal Zam Dam (Urdu: گومل زم ڈیم) is a multi-purpose gravity dam in South Waziristan District of Khyber Pakhtunkhwa, Pakistan. The dam impounds the Gomal River, a tributary of the Indus River, at Khjori Kach, where the Gomal River passes through a narrow ravine. The purpose of the dam is irrigation, flood control, and hydroelectric power generation. Construction of the dam began in August 2001 and was completed in April 2011. The powerhouse was completed in March 2013 and electricity production started in August 2013. The dam was officially inaugurated on 12 September 2013 by Minister for Water and Power Khawaja Muhammad Asif, along with US Ambassador Richard G. Olson and Khyber Pakhtunkhwa Governor Shaukatullah Khan.
Gomal Dam is a roller-compacted concrete (RCC) gravity dam with a height of 437 feet (133 m). It has a gross storage capacity of 1,140,000 acre-feet (1.41 km3) and the 60.5 km long main canal can irrigate about 163,000 acres (660 km2) of barren land in Tank district and Tehsil Kulachi of Dera Ismail Khan. It produces 17.4 MW of electricity.
The dam site at Khjori was first envisaged by four British officers of the Royal Corps of Engineers in 1898 and surveys were carried out. The Government of Pakistan approved the construction of the dam in August 1963 and preparatory work was commenced. However, it was stopped due to the outbreak of the 1965 Indo-Pak War and by subsequent budgetary constraints. However, in 2001, then President of Pakistan, General Pervez Musharraf ordered its construction. The groundbreaking ceremony was held on 14 August 2001.
In 2002, Pakistan's Water and Power Development Authority (WAPDA) hired a Chinese joint venture, CWHEC-HPE, to lead construction at a cost of about Rs. 4.388 billion. The venture joined China National Water Resources & Hydropower Engineering Corporation and Harbin Power Engineering Company. Work halted in October 2004 when two Chinese engineers were kidnapped by Tehrik-i-Taliban Pakistan militants. One was later rescued but the other was killed in the attempt. Work resumed in 2007 after Pakistan put its army's construction branch, the Frontier Works Organisation, in charge. It hired as sub-contractors China's state-owned Sinohydro Corporation to complete the dam, and Turkey's Tekser to finish irrigation works. The total cost of the resumed project was stated to be around Rs. 13 billion.
In July 2010, the United States Agency for International Development (USAID) announced it would provide funding for the dam. Further delay to the project was caused by the 2010 Pakistan floods.
In October 2010, the construction work on the dam was reported to be 92 percent complete. It was also stated to start operating from April 2011.
In January 2011, USAID signed an agreement with WAPDA to provide $40 million to help complete the under-construction Gomal Zam Dam & powerhouse. The first tranche of $20 million was released to WAPDA in February 2011. Another $20 million were provided to complete the main dam and the powerhouse.
Construction of the Dam was completed in April 2011 and filling of the reservoir was started in the same month. Eight more dam workers were kidnapped by Tehrik-i-Taliban Pakistan militants on 15 August 2012. Seven of the eight workers were released on 14 September 2013 after the Pakistani government paid a heavy ransom of Rs. 25 million to the ‘commander Latif’ group of Tehrik-i-Taliban Pakistan. The fate of the eighth kidnapped employee is unknown.
Hub AI
Gomal Zam Dam AI simulator
(@Gomal Zam Dam_simulator)
Gomal Zam Dam
Gomal Zam Dam (Urdu: گومل زم ڈیم) is a multi-purpose gravity dam in South Waziristan District of Khyber Pakhtunkhwa, Pakistan. The dam impounds the Gomal River, a tributary of the Indus River, at Khjori Kach, where the Gomal River passes through a narrow ravine. The purpose of the dam is irrigation, flood control, and hydroelectric power generation. Construction of the dam began in August 2001 and was completed in April 2011. The powerhouse was completed in March 2013 and electricity production started in August 2013. The dam was officially inaugurated on 12 September 2013 by Minister for Water and Power Khawaja Muhammad Asif, along with US Ambassador Richard G. Olson and Khyber Pakhtunkhwa Governor Shaukatullah Khan.
Gomal Dam is a roller-compacted concrete (RCC) gravity dam with a height of 437 feet (133 m). It has a gross storage capacity of 1,140,000 acre-feet (1.41 km3) and the 60.5 km long main canal can irrigate about 163,000 acres (660 km2) of barren land in Tank district and Tehsil Kulachi of Dera Ismail Khan. It produces 17.4 MW of electricity.
The dam site at Khjori was first envisaged by four British officers of the Royal Corps of Engineers in 1898 and surveys were carried out. The Government of Pakistan approved the construction of the dam in August 1963 and preparatory work was commenced. However, it was stopped due to the outbreak of the 1965 Indo-Pak War and by subsequent budgetary constraints. However, in 2001, then President of Pakistan, General Pervez Musharraf ordered its construction. The groundbreaking ceremony was held on 14 August 2001.
In 2002, Pakistan's Water and Power Development Authority (WAPDA) hired a Chinese joint venture, CWHEC-HPE, to lead construction at a cost of about Rs. 4.388 billion. The venture joined China National Water Resources & Hydropower Engineering Corporation and Harbin Power Engineering Company. Work halted in October 2004 when two Chinese engineers were kidnapped by Tehrik-i-Taliban Pakistan militants. One was later rescued but the other was killed in the attempt. Work resumed in 2007 after Pakistan put its army's construction branch, the Frontier Works Organisation, in charge. It hired as sub-contractors China's state-owned Sinohydro Corporation to complete the dam, and Turkey's Tekser to finish irrigation works. The total cost of the resumed project was stated to be around Rs. 13 billion.
In July 2010, the United States Agency for International Development (USAID) announced it would provide funding for the dam. Further delay to the project was caused by the 2010 Pakistan floods.
In October 2010, the construction work on the dam was reported to be 92 percent complete. It was also stated to start operating from April 2011.
In January 2011, USAID signed an agreement with WAPDA to provide $40 million to help complete the under-construction Gomal Zam Dam & powerhouse. The first tranche of $20 million was released to WAPDA in February 2011. Another $20 million were provided to complete the main dam and the powerhouse.
Construction of the Dam was completed in April 2011 and filling of the reservoir was started in the same month. Eight more dam workers were kidnapped by Tehrik-i-Taliban Pakistan militants on 15 August 2012. Seven of the eight workers were released on 14 September 2013 after the Pakistani government paid a heavy ransom of Rs. 25 million to the ‘commander Latif’ group of Tehrik-i-Taliban Pakistan. The fate of the eighth kidnapped employee is unknown.