The Hainan eastern ring high-speed railway is a high-speed railway on Hainan Island. It is operated by China Railway Guangzhou Group. Opened in December 2010, the railway links the capital Haikou at the northern end of the province, and goes alongside the eastern coastline to reach the resort city of Sanya in the southernmost region of the island. The railway share the end points with the Hainan western ring high-speed railway, which together creates a closed loop spanning 653 kms, as well as the world’s first circular high-speed railway, and allows passengers to travel around Hainan island (roughly same distance as circling Belgium) in about 3 hours.
The idea for the railway was first proposed in February 1958 by then Vice-Premier and Director of the National Planning Commission, Li Fuchun, during an inspection tour of Hainan. The original proposal was for a railway that would go completely around the island. It would incorporate several railway sections that had recently been, or were about to be, reconstructed in the southwestern part of the island (see Hainan western ring railway).
In February 1960, Premier Zhou Enlai visited Hainan and created a construction blueprint. In May 1963, Li Fuchun returned to inspect Hainan. His intention was for a ten-year plan to complete the railway. This was interrupted by the Cultural Revolution, and the plan was suspended.
In the summer of 1980, the State Council made the decision to speed up development and construction on Hainan Island.
The Guangdong–Hainan Train Ferry (part of the Guangdong–Hainan railway) was completed in December 2004, and the Hainan western ring railway along the western coast of the island from Haikou to Sanya was completed in 2005.
Preparation for the construction project in the eastern half of the island officially started in March 2006, with the National Development and Reform Commission officially approving the feasibility report on March 22, 2007. Construction began on September 29, 2007, and the railway went into service on December 30, 2010.
With a projected cost of over 22.22 billion RMB (approximately US$3.3 billion) shared between China's Ministry of Railways and the Hainan provincial government, this was Hainan's largest single investment project to date and employed a workforce of 50,000. Items of expenditure included 17.7 billion RMB on fixed assets and 1.5 billion RMB on trains.
The official opening and start of operations of the eastern ring railway took place on December 30, 2010 with a trial run. At the opening ceremony, Luo Baoming, governor of Hainan, stated that the railway will promote urbanization and greatly improve the island's transportation capacity.[citation needed]
Hub AI
Hainan eastern ring high-speed railway AI simulator
(@Hainan eastern ring high-speed railway_simulator)
Hainan eastern ring high-speed railway
The Hainan eastern ring high-speed railway is a high-speed railway on Hainan Island. It is operated by China Railway Guangzhou Group. Opened in December 2010, the railway links the capital Haikou at the northern end of the province, and goes alongside the eastern coastline to reach the resort city of Sanya in the southernmost region of the island. The railway share the end points with the Hainan western ring high-speed railway, which together creates a closed loop spanning 653 kms, as well as the world’s first circular high-speed railway, and allows passengers to travel around Hainan island (roughly same distance as circling Belgium) in about 3 hours.
The idea for the railway was first proposed in February 1958 by then Vice-Premier and Director of the National Planning Commission, Li Fuchun, during an inspection tour of Hainan. The original proposal was for a railway that would go completely around the island. It would incorporate several railway sections that had recently been, or were about to be, reconstructed in the southwestern part of the island (see Hainan western ring railway).
In February 1960, Premier Zhou Enlai visited Hainan and created a construction blueprint. In May 1963, Li Fuchun returned to inspect Hainan. His intention was for a ten-year plan to complete the railway. This was interrupted by the Cultural Revolution, and the plan was suspended.
In the summer of 1980, the State Council made the decision to speed up development and construction on Hainan Island.
The Guangdong–Hainan Train Ferry (part of the Guangdong–Hainan railway) was completed in December 2004, and the Hainan western ring railway along the western coast of the island from Haikou to Sanya was completed in 2005.
Preparation for the construction project in the eastern half of the island officially started in March 2006, with the National Development and Reform Commission officially approving the feasibility report on March 22, 2007. Construction began on September 29, 2007, and the railway went into service on December 30, 2010.
With a projected cost of over 22.22 billion RMB (approximately US$3.3 billion) shared between China's Ministry of Railways and the Hainan provincial government, this was Hainan's largest single investment project to date and employed a workforce of 50,000. Items of expenditure included 17.7 billion RMB on fixed assets and 1.5 billion RMB on trains.
The official opening and start of operations of the eastern ring railway took place on December 30, 2010 with a trial run. At the opening ceremony, Luo Baoming, governor of Hainan, stated that the railway will promote urbanization and greatly improve the island's transportation capacity.[citation needed]