Iterative and incremental development
Iterative and incremental development is any combination of both iterative design (or iterative method) and incremental build model for development.
Usage of the term began in software development, with a long-standing combination of the two terms iterative and incremental having been widely suggested for large development efforts. For example, the 1985 DOD-STD-2167 mentions (in section 4.1.2): "During software development, more than one iteration of the software development cycle may be in progress at the same time." and "This process may be described as an 'evolutionary acquisition' or 'incremental build' approach." In software, the relationship between iterations and increments is determined by the overall software development process.
The basic idea behind this method is to develop a system through repeated cycles (iterative) and in smaller portions at a time (incremental), allowing software developers to take advantage of what was learned during development of earlier parts or versions of the system. Learning comes from both the development and use of the system, where possible key steps in the process start with a simple implementation of a subset of the software requirements and iteratively enhance the evolving versions until the full system is implemented. At each iteration, design modifications are made and new functional capabilities are added.
The procedure itself consists of the initialization step, the iteration step, and the Project Control List. The initialization step creates a base version of the system. The goal for this initial implementation is to create a product to which the user can react. It should offer a sampling of the key aspects of the problem and provide a solution that is simple enough to understand and implement easily. To guide the iteration process, a project control list is created that contains a record of all tasks that need to be performed. It includes items such as new features to be implemented and areas of redesign of the existing solution. The control list is constantly being revised as a result of the analysis phase.
An iteration involves redesign and implementation, which is meant to be simple, straightforward, and modular, supporting redesign at that stage or as a future task added to the project control list.[clarification needed] The level of design detail is not dictated by the iterative approach. In a light-weight iterative project the code may represent the major source of documentation of the system; however, in a critical iterative project a formal Software Design Document may be used. The analysis of an iteration is based upon user feedback and the program analysis facilities available. It involves analysis of the structure, modularity, usability, reliability, efficiency, and achievement of goals. The project control list is modified in light of the analysis results.
Incremental development slices the system functionality into increments (portions). In each increment, a slice of functionality is delivered through cross-discipline work, from the requirements to the deployment. The Unified Process groups increments/iterations into phases: inception, elaboration, construction, and transition.
Each of the phases may be divided into 1 or more iterations, which are usually time-boxed rather than feature-boxed. Architects and analysts work one iteration ahead of developers and testers to keep their work-product backlog full.
Many examples of early usage are provided in Craig Larman and Victor Basili's article "Iterative and Incremental Development: A Brief History", with one of the earliest being NASA's 1960s Project Mercury.
Hub AI
Iterative and incremental development AI simulator
(@Iterative and incremental development_simulator)
Iterative and incremental development
Iterative and incremental development is any combination of both iterative design (or iterative method) and incremental build model for development.
Usage of the term began in software development, with a long-standing combination of the two terms iterative and incremental having been widely suggested for large development efforts. For example, the 1985 DOD-STD-2167 mentions (in section 4.1.2): "During software development, more than one iteration of the software development cycle may be in progress at the same time." and "This process may be described as an 'evolutionary acquisition' or 'incremental build' approach." In software, the relationship between iterations and increments is determined by the overall software development process.
The basic idea behind this method is to develop a system through repeated cycles (iterative) and in smaller portions at a time (incremental), allowing software developers to take advantage of what was learned during development of earlier parts or versions of the system. Learning comes from both the development and use of the system, where possible key steps in the process start with a simple implementation of a subset of the software requirements and iteratively enhance the evolving versions until the full system is implemented. At each iteration, design modifications are made and new functional capabilities are added.
The procedure itself consists of the initialization step, the iteration step, and the Project Control List. The initialization step creates a base version of the system. The goal for this initial implementation is to create a product to which the user can react. It should offer a sampling of the key aspects of the problem and provide a solution that is simple enough to understand and implement easily. To guide the iteration process, a project control list is created that contains a record of all tasks that need to be performed. It includes items such as new features to be implemented and areas of redesign of the existing solution. The control list is constantly being revised as a result of the analysis phase.
An iteration involves redesign and implementation, which is meant to be simple, straightforward, and modular, supporting redesign at that stage or as a future task added to the project control list.[clarification needed] The level of design detail is not dictated by the iterative approach. In a light-weight iterative project the code may represent the major source of documentation of the system; however, in a critical iterative project a formal Software Design Document may be used. The analysis of an iteration is based upon user feedback and the program analysis facilities available. It involves analysis of the structure, modularity, usability, reliability, efficiency, and achievement of goals. The project control list is modified in light of the analysis results.
Incremental development slices the system functionality into increments (portions). In each increment, a slice of functionality is delivered through cross-discipline work, from the requirements to the deployment. The Unified Process groups increments/iterations into phases: inception, elaboration, construction, and transition.
Each of the phases may be divided into 1 or more iterations, which are usually time-boxed rather than feature-boxed. Architects and analysts work one iteration ahead of developers and testers to keep their work-product backlog full.
Many examples of early usage are provided in Craig Larman and Victor Basili's article "Iterative and Incremental Development: A Brief History", with one of the earliest being NASA's 1960s Project Mercury.