Lekki Port
Lekki Deep Sea Port, is a multi-purpose, deep sea port in the Lagos Free Zone and is the only currently operating deep sea port in the country, having started full commercial operations in April 2023.
It is the largest seaport of Nigeria and one of the biggest in West Africa. Lekki port is to be expanded to have a capacity of handling around 6 million TEUs of containers and a significant volume of liquid and dry bulk uncontainerized cargoes. The port is to be equipped with ships able to transport over 14,500 containers.
The port is being developed in phases. Its phase one, be operational in 2018, chiefly comprises it three container berths equipped to handle more than 1.8 million TEUs — one berth for dry bulk goods and two berths for liquid cargo.
The port is financed by private investors and a consortium of banks who have funded the project with $1.5 billion as of March 2021. The seaport is to occupy up to 90 hectares of land. The port started commercial operations in April 2023.
On October, 31st, 2022, the port has been handed over to the owners. Commissioning will start "in the next month". Lagos State governor Sanwo-Olu promised on this occasion to expand the roads to the port to 6 lane highways.
On 22 January 2023, a few hours before the official inauguration by President Buhari, the first commercial ship, the container freighter CMA CGM MOZART, docked at the port.
The layout of the port, including the layout of the approach channel, turning circle, and harbor basins have been derived from optimizations based on port operations, construction costs, and possible future extensions.
Two different breakwater concepts were applied for the main breakwater: A rubble mound with geo-bag core for the near-shore sections and a composite breakwater for the more exposed sections. The main breakwater is 1.5 km long.
Hub AI
Lekki Port AI simulator
(@Lekki Port_simulator)
Lekki Port
Lekki Deep Sea Port, is a multi-purpose, deep sea port in the Lagos Free Zone and is the only currently operating deep sea port in the country, having started full commercial operations in April 2023.
It is the largest seaport of Nigeria and one of the biggest in West Africa. Lekki port is to be expanded to have a capacity of handling around 6 million TEUs of containers and a significant volume of liquid and dry bulk uncontainerized cargoes. The port is to be equipped with ships able to transport over 14,500 containers.
The port is being developed in phases. Its phase one, be operational in 2018, chiefly comprises it three container berths equipped to handle more than 1.8 million TEUs — one berth for dry bulk goods and two berths for liquid cargo.
The port is financed by private investors and a consortium of banks who have funded the project with $1.5 billion as of March 2021. The seaport is to occupy up to 90 hectares of land. The port started commercial operations in April 2023.
On October, 31st, 2022, the port has been handed over to the owners. Commissioning will start "in the next month". Lagos State governor Sanwo-Olu promised on this occasion to expand the roads to the port to 6 lane highways.
On 22 January 2023, a few hours before the official inauguration by President Buhari, the first commercial ship, the container freighter CMA CGM MOZART, docked at the port.
The layout of the port, including the layout of the approach channel, turning circle, and harbor basins have been derived from optimizations based on port operations, construction costs, and possible future extensions.
Two different breakwater concepts were applied for the main breakwater: A rubble mound with geo-bag core for the near-shore sections and a composite breakwater for the more exposed sections. The main breakwater is 1.5 km long.