Hubbry Logo
logo
Narrows Bridge (Perth)
Community hub

Narrows Bridge (Perth)

logo
0 subscribers
Be the first to start a discussion here.
Be the first to start a discussion here.
Contribute something to knowledge base
Hub AI

Narrows Bridge (Perth) AI simulator

(@Narrows Bridge (Perth)_simulator)

Narrows Bridge (Perth)

The Narrows Bridge is a freeway and railway crossing of the Swan River in Perth, Western Australia.

Made up of two road bridges and a railway bridge constructed at a part of the river known as the Narrows, located between Mill Point and Point Lewis, it connects the Mitchell and Kwinana freeways, linking the city's northern and southern suburbs. The original road bridge was opened in 1959 and was the largest precast prestressed concrete bridge in the world. Construction of the northern interchange for this bridge necessitated the reclamation of a large amount of land from the river.

The bridge formed part of the Kwinana Freeway which originally ran for only 2.4 miles (3.9 km) to Canning Bridge. Over the following decades, the freeway system was expanded to the north and south, greatly increasing the volume of traffic using the bridge. As a result, in 2001, a second road bridge was opened to the west of the original bridge, and in 2005, the railway bridge was constructed in the gap between the two traffic bridges. Passenger trains first traversed the Narrows in 2007 with the opening of the Mandurah railway line.

The close distance between Mill Point and Point Lewis at the foot of Mount Eliza meant the site was suggested as a suitable location for a bridge as early as 1849. A bridge was proposed for the site in 1899, but its expected cost of £13,000 was deemed too high. Preliminary planning for a bridge at the site finally began in 1947, but was suspended so that a replacement for The Causeway could be built at Heirisson Island, at the city's eastern end. The new Causeway bridges were opened in 1952, and by 1954 traffic using them to enter the city had doubled, renewing calls for a bridge at the Narrows.

Site investigations for the bridge began in August 1954. The bridge was proposed for the Narrows site by the Town Planning Commission under the chairmanship of Harold Boas. The chosen site drew public protest on the basis that the bridge would spoil the view to and from the city. Also, residents of the wealthy Mill Point area were angry that they would have a major highway running beside their houses. The site also necessitated the reclamation of 60 acres (24 ha) of land from Mounts Bay for the bridge approach and interchange. This land reclamation, which started in October 1954, saw the addition of 3.4 million cubic metres (4.5 million cubic yards) of sand, much of which was dredged from Melville Water.

The state started saving for the new bridge in September 1954, and the construction of the bridge was approved by the Hawke state Labor government in November 1954, before the Hepburn-Stephenson metropolitan roads plan had been finalised, such was the urgency of a new traffic link. The construction of the bridge was subsequently endorsed in the 1955 Hepburn–Stephenson plan, which later developed into the Metropolitan Region Scheme.

The river bed at the site of the proposed bridge was not ideal for bridge building, with soft mud extending down as deep as 80 feet (24 m) and sand beds below that going a further 40 feet (12 m) down. Ernie Godfrey, a bridge engineer with the Main Roads Department, travelled overseas to inspect bridges in similar geological locations and to source a designer for the proposed bridge. The design contract for the bridge was won by British engineering firm Maunsell & Co.

Construction on the road system began in 1956, and the contract for construction of the bridge was signed by Commissioner of Main Roads J. Digby Leach on 16 March 1957. The bridge was built by Danish firm Christiani & Nielsen in conjunction with Western Australian engineering firm J. O. Clough & Son. Leif Ott Nilsen oversaw construction on behalf of Christiani & Nielsen. The first timber pile for the temporary staging for the construction was driven at noon on 8 June 1957. The first permanent pile for the bridge was driven home on 18 August 1957. Work on the bridge's precast concrete beams began in September 1957, and the first of these was lifted into place by the 60-foot (18 m) gantry crane in February 1958. The last river pile was driven home in November 1958, and the final concrete beam was lowered into position in June 1959. During construction on 10 February 1959, John Tonkin, then the Deputy Premier and Minister for Works, announced that the new bridge was to be named the Golden West Bridge. However, Golden West was also the name for a popular soft drink; the proposal encountered scorn from commentators and was quietly dropped.

See all
set of bridges in Perth, Western Australia
User Avatar
No comments yet.