The Punggol LRT line (PGLRT) is a 10.3-kilometre (6.4 mi) elevated automated guideway transit line in Punggol, Singapore. The driverless system consists of 15 stations on two loops, with Punggol station serving as the interchange for both loops and linking the line to the North East Line on the Singapore MRT. It is the third Light Rail Transit (LRT) line in Singapore and the second LRT line to be operated by SBS Transit.

The PGLRT was conceived as part of the Punggol 21 development plan announced by prime minister Goh Chok Tong in 1996. Construction of the LRT line began in June 2000 and was completed in June 2004, and the Land Transport Authority transferred operations to SBS Transit in December that year. The East Loop began operations on 29 January 2005, with Oasis and Damai only opening in 2007 and 2011 respectively. The West Loop commenced operations on 29 June 2014, with Teck Lee station being the last to open on 15 August 2024.

The line utilises the Kyosan Automated People Mover (APM) fixed block signalling system and Mitsubishi Heavy Industries's Crystal Mover APM vehicles. Two-car operations were introduced in December 2016 to accommodate increased ridership. Between 2018 and 2022, the PGLRT underwent renewal works to improve reliability. A new fleet of 25 two-car APMs entered service in 2025, replacing 25 one-car trains and half of the 16 two-car trains in the existing fleet.

At the launch of the Punggol 21 housing concept in August 1996, prime minister Goh Chok Tong announced plans for a light rail (LRT) system in Punggol. According to Mohinder Singh, the planning director of the Land Transport Authority (LTA), the LRT system was not part of the original 1991 Urban Redevelopment Authority (URA) Concept Plan, but was later jointly developed by the Housing Development Board (HDB), URA, and LTA during the planning of Punggol 21. The Sengkang and Punggol LRT systems (SPLRT) were planned in tandem, with these agencies collaborating to integrate transport and housing for optimal service. In July 1998, communications minister Mah Bow Tan confirmed the government's decision to proceed with the Punggol LRT system, with 19 stations planned on the 13-kilometre (8.1 mi) route.

The contract for the design and construction of the SPLRT was awarded to a joint venture for S$656 million (US$392 million). The joint venture comprised Singapore Technologies Industrial Corporation, Mitsubishi Heavy Industries and Mitsubishi Corporation. On 20 May 1999, SBS Transit (then Singapore Bus Service) was appointed to operate the Punggol LRT along with the North East Line and the Sengkang LRT line.

Construction of the Punggol LRT line began in June 2000 and was completed in June 2004. Due to limited funding from the 1997 financial crisis and low projected ridership, the SPLRT was initially constructed for single-car operations, even though it had been designed for two. Nevertheless, provisions were made for future conversion to two-car operations during the expected equipment replacement cycle, which was expected to occur within 15 to 20 years. The LTA conducted tests on the line before handing it over to SBS Transit in December 2004 for additional trial operations. SBS Transit announced that the East Loop would open first as the West Loop served a less populated area of Punggol at that time.

On 10 January 2005, SBS Transit confirmed that the East Loop would open on 29 January, with the exception of the Oasis and Damai stations. The opening ceremony on the day itself was officiated by transport minister Yeo Cheow Tong. Early ridership remained low, especially due to the SARS outbreak. The East Loop initially operated unidirectional services in the peak flow direction. Morning services from 5:20 am to 3:00 pm ran anti-clockwise from Kadaloor to Punggol, while evening services from 3:00 pm to 12:35 am operated clockwise from Punggol to Kadaloor. After requests by residents to open Oasis station, the station opened on 15 June 2007. Damai station opened on 20 June 2011 and bidirectional services commenced on the East Loop.

The West Loop began operations from 29 June 2014 with the opening of Nibong, Sumang and Soo Teck stations. The West Loop initially operated unidirectional services at a frequency of 7 to 8 minutes, with morning services running from Nibong to Punggol, and evening services running from Punggol to Nibong via Soo Teck. Sam Kee station opened on 29 February 2016 to serve the Punggol Waterway Park and SAFRA Punggol Clubhouse.