Six Companies
Six Companies, Inc. was a joint venture of construction companies that was formed to build the Hoover Dam on the Colorado River in Nevada and Arizona.
They later built Parker Dam, a portion of the Grand Coulee Dam, the Colorado River Aqueduct across the Mojave and Colorado Deserts to urban Southern California, and many other large projects.
On January 10, 1932, the Bureau of Reclamation made bid documents for the Hoover Dam construction project available to interested parties at $5 a copy (equivalent to $103.00 in 2024). The government would provide the materials, and the contractor was to prepare the site and build the dam. The dam was described in minute detail, covering 100 pages of text and 76 drawings. A $2 million (equivalent to $33.1 million in 2024) bid bond was to accompany each bid. The winner would have to post a $5 million (equivalent to $82.8 million in 2024) performance bond. The contractor would have seven years to build the dam, or penalties would ensue.
Because of the project's immense size and the fact that it was the first dam on the Colorado River, no single contractor had the resources to make a qualified bid alone. So, general contractors Utah Construction Company of Ogden, Utah decided to form a consortium in order to submit a joint bid for the contract. Initially, Utah Construction Company's owners, brothers E.O. and W.H. Wattis, along with the company's vice president, Andrew H. Christensen, asked Harry W. Morrison of Morrison-Knudsen to join them. After they realized the bid would be much higher than expected, the Wattis Brothers and Morrison-Knudsen convinced four additional companies to join. In February 1930 The Six Companies, Inc. was incorporated as a joint venture and they began working out a bid enlisting the help of Morrison-Knudsen employee Frank T. Crowe to do so.
The project was so complex and large that only three bids were received and, on March 4, 1931, the US Secretary of the Interior accepted the Six Companies' bid of US$48,890,955 (equivalent to $809 million in 2024). This was $5,000,000 lower than the next bidder, meaning a bid-spread of almost 10%.
The Six Companies board selected Crowe, who had helped draft the bid, as the General Construction Superintendent of the Boulder Dam construction. He was heavily involved and hired each of the men who were employed during the course of the project, lived in Boulder City with his wife and two daughters, and was on the dam site every day of the week until the project was completed.
Work began around June 1931 and The Six Companies completed the dam's construction two years ahead of schedule in 1935. Crowe was awarded a bonus percentage of the profit for completing virtually every portion of the job well ahead of schedule. The dam was dedicated in September 1935 but it took an additional nine years (1938–1947) under relative secrecy, to fix serious leaks with a supplemental grout curtain.
The Six Companies also built the 19.1-mile (30.7 km) Six Companies Railroad. It ran along the Hemenway Wash, present day Las Vegas Bay, and connected to the US Government Hoover Dam Railroad at Lawler, Nevada, a location also known as "US Government Junction". From Lawler the railroad went north for seven miles (11 km) to Saddle Island and then east to the Three-Way Junction gravel plant, now submerged under Lake Mead. From the gravel plant the line split into two branches. One branch ran south for 4.8 miles (7.7 km) to the dam via Cape Horn, Lomix (the Low Level Concrete Mixing Plant) and Himix (the High Level Concrete Mixing Plant) and the dam face. The other branch, now also submerged under Lake Mead, ran north for 7.3 miles (11.7 km) across the Las Vegas Wash, crossed the Colorado River on a bridge into Arizona and the Arizona gravel pit (Arizona Gravel Deposits) at a location two miles (3.2 km) from Callville.
Hub AI
Six Companies AI simulator
(@Six Companies_simulator)
Six Companies
Six Companies, Inc. was a joint venture of construction companies that was formed to build the Hoover Dam on the Colorado River in Nevada and Arizona.
They later built Parker Dam, a portion of the Grand Coulee Dam, the Colorado River Aqueduct across the Mojave and Colorado Deserts to urban Southern California, and many other large projects.
On January 10, 1932, the Bureau of Reclamation made bid documents for the Hoover Dam construction project available to interested parties at $5 a copy (equivalent to $103.00 in 2024). The government would provide the materials, and the contractor was to prepare the site and build the dam. The dam was described in minute detail, covering 100 pages of text and 76 drawings. A $2 million (equivalent to $33.1 million in 2024) bid bond was to accompany each bid. The winner would have to post a $5 million (equivalent to $82.8 million in 2024) performance bond. The contractor would have seven years to build the dam, or penalties would ensue.
Because of the project's immense size and the fact that it was the first dam on the Colorado River, no single contractor had the resources to make a qualified bid alone. So, general contractors Utah Construction Company of Ogden, Utah decided to form a consortium in order to submit a joint bid for the contract. Initially, Utah Construction Company's owners, brothers E.O. and W.H. Wattis, along with the company's vice president, Andrew H. Christensen, asked Harry W. Morrison of Morrison-Knudsen to join them. After they realized the bid would be much higher than expected, the Wattis Brothers and Morrison-Knudsen convinced four additional companies to join. In February 1930 The Six Companies, Inc. was incorporated as a joint venture and they began working out a bid enlisting the help of Morrison-Knudsen employee Frank T. Crowe to do so.
The project was so complex and large that only three bids were received and, on March 4, 1931, the US Secretary of the Interior accepted the Six Companies' bid of US$48,890,955 (equivalent to $809 million in 2024). This was $5,000,000 lower than the next bidder, meaning a bid-spread of almost 10%.
The Six Companies board selected Crowe, who had helped draft the bid, as the General Construction Superintendent of the Boulder Dam construction. He was heavily involved and hired each of the men who were employed during the course of the project, lived in Boulder City with his wife and two daughters, and was on the dam site every day of the week until the project was completed.
Work began around June 1931 and The Six Companies completed the dam's construction two years ahead of schedule in 1935. Crowe was awarded a bonus percentage of the profit for completing virtually every portion of the job well ahead of schedule. The dam was dedicated in September 1935 but it took an additional nine years (1938–1947) under relative secrecy, to fix serious leaks with a supplemental grout curtain.
The Six Companies also built the 19.1-mile (30.7 km) Six Companies Railroad. It ran along the Hemenway Wash, present day Las Vegas Bay, and connected to the US Government Hoover Dam Railroad at Lawler, Nevada, a location also known as "US Government Junction". From Lawler the railroad went north for seven miles (11 km) to Saddle Island and then east to the Three-Way Junction gravel plant, now submerged under Lake Mead. From the gravel plant the line split into two branches. One branch ran south for 4.8 miles (7.7 km) to the dam via Cape Horn, Lomix (the Low Level Concrete Mixing Plant) and Himix (the High Level Concrete Mixing Plant) and the dam face. The other branch, now also submerged under Lake Mead, ran north for 7.3 miles (11.7 km) across the Las Vegas Wash, crossed the Colorado River on a bridge into Arizona and the Arizona gravel pit (Arizona Gravel Deposits) at a location two miles (3.2 km) from Callville.