Use case points
Use case points (UCP or UCPs) is a software estimation technique used to forecast the software size for software development projects. UCP is used when the Unified Modeling Language (UML) and Rational Unified Process (RUP) methodologies are being used for the software design and development. The concept of UCP is based on the requirements for the system being written using use cases, which is part of the UML set of modeling techniques. The software size (UCP) is calculated based on elements of the system use cases with factoring to account for technical and environmental considerations. The UCP for a project can then be used to calculate the estimated effort for a project.
The UCP technique was developed by Gustav Karner in 1993 while employed at what was known at the time as Objectory Systems, which later merged into Rational Software and then IBM. The UCP method was created to solve for estimating the software size of systems that were object oriented. It is based on similar principles as the Function Point (FP) estimation method, but was designed for the specific needs of object oriented systems and system requirements based on use cases.
The method for determining the size estimate to develop a system is based on a calculation with the following elements:
Once the previous four elements have been calculated, the final size estimate can be calculated. This final number is known as the use case points or UCP for a software development project.
The following sections walk through the various calculations to determine the UCP for a project.
The UUCW is one of the factors that contribute to the size of the software being developed. It is calculated based on the number and complexity of the use cases for the system. To find the UUCW for a system, each of the use cases must be identified and classified as Simple, Average or Complex based on the number of transactions the use case contains. Each classification has a predefined weight assigned. Once all use cases have been classified as simple, average or complex, the total weight (UUCW) is determined by summing the corresponding weights for each use case. The following chart shows the different classifications of use cases based on the number of transactions and the weight value assigned for each use case within the classification.
The UAW is another factor that contributes to the size of the software being developed. It is calculated based on the number and complexity of the actors for the system. Similar to finding the UUCW, each of the actors must be identified and classified as Simple, Average or Complex based on the type of actor. Each classification also has a predefined weight assigned. The UAW is the total of the weights for each of the actors. The following chart shows the different classifications of actors and the weight value assigned.
The TCF is one of the factors applied to the estimated size of the software in order to account for technical considerations of the system. It is determined by assigning a score between 0 (factor is irrelevant) and 5 (factor is essential) to each of the 13 technical factors listed in the table below. This score is then multiplied by the defined weighted value for each factor. The total of all calculated values is the technical factor (TF). The TF is then used to compute the TCF with the following formula:
Hub AI
Use case points AI simulator
(@Use case points_simulator)
Use case points
Use case points (UCP or UCPs) is a software estimation technique used to forecast the software size for software development projects. UCP is used when the Unified Modeling Language (UML) and Rational Unified Process (RUP) methodologies are being used for the software design and development. The concept of UCP is based on the requirements for the system being written using use cases, which is part of the UML set of modeling techniques. The software size (UCP) is calculated based on elements of the system use cases with factoring to account for technical and environmental considerations. The UCP for a project can then be used to calculate the estimated effort for a project.
The UCP technique was developed by Gustav Karner in 1993 while employed at what was known at the time as Objectory Systems, which later merged into Rational Software and then IBM. The UCP method was created to solve for estimating the software size of systems that were object oriented. It is based on similar principles as the Function Point (FP) estimation method, but was designed for the specific needs of object oriented systems and system requirements based on use cases.
The method for determining the size estimate to develop a system is based on a calculation with the following elements:
Once the previous four elements have been calculated, the final size estimate can be calculated. This final number is known as the use case points or UCP for a software development project.
The following sections walk through the various calculations to determine the UCP for a project.
The UUCW is one of the factors that contribute to the size of the software being developed. It is calculated based on the number and complexity of the use cases for the system. To find the UUCW for a system, each of the use cases must be identified and classified as Simple, Average or Complex based on the number of transactions the use case contains. Each classification has a predefined weight assigned. Once all use cases have been classified as simple, average or complex, the total weight (UUCW) is determined by summing the corresponding weights for each use case. The following chart shows the different classifications of use cases based on the number of transactions and the weight value assigned for each use case within the classification.
The UAW is another factor that contributes to the size of the software being developed. It is calculated based on the number and complexity of the actors for the system. Similar to finding the UUCW, each of the actors must be identified and classified as Simple, Average or Complex based on the type of actor. Each classification also has a predefined weight assigned. The UAW is the total of the weights for each of the actors. The following chart shows the different classifications of actors and the weight value assigned.
The TCF is one of the factors applied to the estimated size of the software in order to account for technical considerations of the system. It is determined by assigning a score between 0 (factor is irrelevant) and 5 (factor is essential) to each of the 13 technical factors listed in the table below. This score is then multiplied by the defined weighted value for each factor. The total of all calculated values is the technical factor (TF). The TF is then used to compute the TCF with the following formula: