238th Street station
The 238th Street station is a local station on the IRT Broadway–Seventh Avenue Line of the New York City Subway. Located at the intersection of 238th Street and Broadway in the Kingsbridge neighborhood of the Bronx, it is served by the 1 train at all times.
Built by the Interborough Rapid Transit Company (IRT), the station opened on August 1, 1908, as part of the first subway. The northbound platform was lengthened in 1910 while the southbound platform was lengthened in 1948. In 2018, the fare controls at the station were changed to allow entries in the northbound direction.
Planning for a subway line in New York City dates to 1864. However, development of what would become the city's first subway line did not start until 1894, when the New York State Legislature passed the Rapid Transit Act. The subway plans were drawn up by a team of engineers led by William Barclay Parsons, the Rapid Transit Commission's chief engineer. It called for a subway line from New York City Hall in lower Manhattan to the Upper West Side, where two branches would lead north into the Bronx. A plan was formally adopted in 1897, and all legal conflicts concerning the route alignment were resolved near the end of 1899.
The Rapid Transit Construction Company, organized by John B. McDonald and funded by August Belmont Jr., signed the initial Contract 1 with the Rapid Transit Commission in February 1900, under which it would construct the subway and maintain a 50-year operating lease from the opening of the line. In 1901, the firm of Heins & LaFarge was hired to design the underground stations. Belmont incorporated the Interborough Rapid Transit Company (IRT) in April 1902 to operate the subway.
Operation of the first subway began on October 27, 1904, with the opening of all stations from City Hall to 145th Street on the West Side Branch. The line was mostly underground, except for the section surrounding 125th Street, which ran across the elevated Manhattan Valley Viaduct to cross a deep valley there. Service was extended to 157th Street on November 12, 1904, as that station's opening had been delayed because of painting and plastering work.
The West Side Branch was extended northward to a temporary terminus at 221st Street and Broadway on March 12, 1906 served by shuttle trains operating between 157th Street and 221st Street. However, only the Dyckman Street, 215th Street, and 221st Street stations opened on that date as the other stations were not yet completed. The 168th Street station opened on April 14, 1906. The 181st Street station opened on May 30, 1906, and on that date express trains on the Broadway branch began running through to 221st Street, eliminating the need to transfer at 157th Street to shuttles. The original system as included in Contract 1 was completed on January 14, 1907, when trains started running across the Harlem Ship Canal on the Broadway Bridge to 225th Street, and the nearby 221st Street station was closed.
Once the line was extended to 225th Street on January 14, 1907, the 221st Street platforms were dismantled and moved to 230th Street for a new temporary terminus. Service was extended to the temporary terminus at 230th Street on January 27, 1907. An extension of Contract 1 north to 242nd Street at Van Cortlandt Park was approved in 1906 and opened on August 1, 1908, along with the 238th Street station.
After the first subway line was completed in 1908, the station was served by West Side local and express trains. Express trains began at South Ferry in Manhattan or Atlantic Avenue in Brooklyn, and ended at 242nd Street in the Bronx. Local trains ran from City Hall to 242nd Street during rush hours, continuing south from City Hall to South Ferry at other times. In 1918, the Broadway–Seventh Avenue Line opened south of Times Square–42nd Street, and the original line was divided into an H-shaped system. The original subway north of Times Square thus became part of the Broadway–Seventh Avenue Line. Local trains were sent to South Ferry, while express trains used the new Clark Street Tunnel to Brooklyn.
Hub AI
238th Street station AI simulator
(@238th Street station_simulator)
238th Street station
The 238th Street station is a local station on the IRT Broadway–Seventh Avenue Line of the New York City Subway. Located at the intersection of 238th Street and Broadway in the Kingsbridge neighborhood of the Bronx, it is served by the 1 train at all times.
Built by the Interborough Rapid Transit Company (IRT), the station opened on August 1, 1908, as part of the first subway. The northbound platform was lengthened in 1910 while the southbound platform was lengthened in 1948. In 2018, the fare controls at the station were changed to allow entries in the northbound direction.
Planning for a subway line in New York City dates to 1864. However, development of what would become the city's first subway line did not start until 1894, when the New York State Legislature passed the Rapid Transit Act. The subway plans were drawn up by a team of engineers led by William Barclay Parsons, the Rapid Transit Commission's chief engineer. It called for a subway line from New York City Hall in lower Manhattan to the Upper West Side, where two branches would lead north into the Bronx. A plan was formally adopted in 1897, and all legal conflicts concerning the route alignment were resolved near the end of 1899.
The Rapid Transit Construction Company, organized by John B. McDonald and funded by August Belmont Jr., signed the initial Contract 1 with the Rapid Transit Commission in February 1900, under which it would construct the subway and maintain a 50-year operating lease from the opening of the line. In 1901, the firm of Heins & LaFarge was hired to design the underground stations. Belmont incorporated the Interborough Rapid Transit Company (IRT) in April 1902 to operate the subway.
Operation of the first subway began on October 27, 1904, with the opening of all stations from City Hall to 145th Street on the West Side Branch. The line was mostly underground, except for the section surrounding 125th Street, which ran across the elevated Manhattan Valley Viaduct to cross a deep valley there. Service was extended to 157th Street on November 12, 1904, as that station's opening had been delayed because of painting and plastering work.
The West Side Branch was extended northward to a temporary terminus at 221st Street and Broadway on March 12, 1906 served by shuttle trains operating between 157th Street and 221st Street. However, only the Dyckman Street, 215th Street, and 221st Street stations opened on that date as the other stations were not yet completed. The 168th Street station opened on April 14, 1906. The 181st Street station opened on May 30, 1906, and on that date express trains on the Broadway branch began running through to 221st Street, eliminating the need to transfer at 157th Street to shuttles. The original system as included in Contract 1 was completed on January 14, 1907, when trains started running across the Harlem Ship Canal on the Broadway Bridge to 225th Street, and the nearby 221st Street station was closed.
Once the line was extended to 225th Street on January 14, 1907, the 221st Street platforms were dismantled and moved to 230th Street for a new temporary terminus. Service was extended to the temporary terminus at 230th Street on January 27, 1907. An extension of Contract 1 north to 242nd Street at Van Cortlandt Park was approved in 1906 and opened on August 1, 1908, along with the 238th Street station.
After the first subway line was completed in 1908, the station was served by West Side local and express trains. Express trains began at South Ferry in Manhattan or Atlantic Avenue in Brooklyn, and ended at 242nd Street in the Bronx. Local trains ran from City Hall to 242nd Street during rush hours, continuing south from City Hall to South Ferry at other times. In 1918, the Broadway–Seventh Avenue Line opened south of Times Square–42nd Street, and the original line was divided into an H-shaped system. The original subway north of Times Square thus became part of the Broadway–Seventh Avenue Line. Local trains were sent to South Ferry, while express trains used the new Clark Street Tunnel to Brooklyn.