The IC4 is an inter-city rail train built by the Italian train manufacturer AnsaldoBreda for the trans-Great Belt routes of Danske Statsbaner (DSB), Denmark's national railway operator. Under DSB's 'Good trains for everyone' plan ('Gode tog til alle'), the intent of the IC4 project was to replace several types of outdated rolling stock. However, various delays and shortcomings have turned the project into a major political issue.
The IC4 units were originally scheduled to enter DSB's Intercity service in 2003. On 25 June 2007, one IC4 unit (trainset no. 4) entered regional service between Aarhus and Aalborg. On 27 August 2007, another test train entered regional passenger service between Aarhus and Fredericia in eastern Jutland. Two further units entered regional service during the autumn of 2007. By the end of 2007, DSB and AnsaldoBreda were to agree when the IC4 would be ready for Intercity and IntercityLyn (express inter-city) services. This, however, required the approval of the Danish National Rail Authority.
The IC4's first long-distance run, from Aalborg to Copenhagen, took place on 7 August 2008, while the train finally received approval for regular service with multiple connected trainsets on 9 November 2010. The 82nd and final unit (MG 5683) was delivered to DSB in September 2013, and as of 2015, IC4 trains are in regular operation on the Aarhus-Copenhagen, Aarhus-Aalborg, Aarhus-Esbjerg, Odense-Fredericia and Copenhagen-Holbæk-Kalundborg connections.
The train is powered by four low-emission diesel engines with a common rail direct-injection system, giving a total power output of 2,240 kW (3,004 bhp) (or 3045 metric hp). The engines are 20-litre (1,200-cubic-inch) V8s from Iveco. The maximum allowed speed of the train is 200 km/h (120 mph). Each train set consists of four articulated cars with a total length of 86 m (282 ft 2 in), and is capable of seating 204 people. Built of light aluminium alloys, each trainset weighs 140–160 tonnes (137.8–157.5 long tons; 154.3–176.4 short tons), and a fully operational (including diesel, water, etc.) weight of 170 tonnes (167.3 long tons; 187.4 short tons).
Up to four trainsets can be coupled together into a single train. However, there are problems associated with this configuration, so in the first instance it was decided to have the IC4 approved using one trainset only, with approval for multi-unit configurations to be sought later. Since a single trainset is too short for efficient long-distance operations, the first trains were used mainly for regional services. In December 2016, DSB gave up the efforts to connect four trainsets.
The design of the train is the outcome of cooperation between DSB's own designers, with an emphasis on Nordic minimalist design, and the Italian design company Pininfarina (famous for designing Ferrari cars) emphasizing Italian chic and curved lines. Externally, the bullet-shaped extremities at each end of the trainset—which are familiar from high-speed trains throughout Europe—represent a break with the design of the IC3 train, whose passengers are able to cross over between trainsets. The train interior features natural materials consistent with Scandinavia's design tradition, an audio/video information system with seat reservation displays, and a lounge area.
The IC4 train has become a contentious issue in Danish politics, mainly because of the long delays in AnsaldoBreda’s delivery of the trains. The Danish Minister of Traffic and Energy is routinely required to submit progress updates to parliament, and DSB's choice of a heavily customised train is often criticised as being the major reason for the delays. The expense involved in lengthening the platforms of several stations along the IC4 routes is the source of much additional criticism. In November 2006, it was revealed that the trains appeared to be working properly, but that the formal documentation requirements of the safety authorities were preventing the train from entering service fully. By the end of October 2007, four IC4 units had entered regional service in Jutland. However, service was suspended at the end of February 2008 because of problems with exhaust fumes. There have been many faults that did not really prevent the train from being used, but were still unacceptable, such as spurious warnings and various other computer-related problems.
In June 2008, DSB gave AnsaldoBreda an ultimatum whereby at least 14 trains had to be approved and ready for regular service before May 2009; otherwise, the contract would be cancelled and DSB would demand its money back and return its trains to the factory. DSB had ordered a total of 83 IC4 trainsets in 2000, with delivery originally scheduled for 2003.
Hub AI
IC4 AI simulator
(@IC4_simulator)
IC4
The IC4 is an inter-city rail train built by the Italian train manufacturer AnsaldoBreda for the trans-Great Belt routes of Danske Statsbaner (DSB), Denmark's national railway operator. Under DSB's 'Good trains for everyone' plan ('Gode tog til alle'), the intent of the IC4 project was to replace several types of outdated rolling stock. However, various delays and shortcomings have turned the project into a major political issue.
The IC4 units were originally scheduled to enter DSB's Intercity service in 2003. On 25 June 2007, one IC4 unit (trainset no. 4) entered regional service between Aarhus and Aalborg. On 27 August 2007, another test train entered regional passenger service between Aarhus and Fredericia in eastern Jutland. Two further units entered regional service during the autumn of 2007. By the end of 2007, DSB and AnsaldoBreda were to agree when the IC4 would be ready for Intercity and IntercityLyn (express inter-city) services. This, however, required the approval of the Danish National Rail Authority.
The IC4's first long-distance run, from Aalborg to Copenhagen, took place on 7 August 2008, while the train finally received approval for regular service with multiple connected trainsets on 9 November 2010. The 82nd and final unit (MG 5683) was delivered to DSB in September 2013, and as of 2015, IC4 trains are in regular operation on the Aarhus-Copenhagen, Aarhus-Aalborg, Aarhus-Esbjerg, Odense-Fredericia and Copenhagen-Holbæk-Kalundborg connections.
The train is powered by four low-emission diesel engines with a common rail direct-injection system, giving a total power output of 2,240 kW (3,004 bhp) (or 3045 metric hp). The engines are 20-litre (1,200-cubic-inch) V8s from Iveco. The maximum allowed speed of the train is 200 km/h (120 mph). Each train set consists of four articulated cars with a total length of 86 m (282 ft 2 in), and is capable of seating 204 people. Built of light aluminium alloys, each trainset weighs 140–160 tonnes (137.8–157.5 long tons; 154.3–176.4 short tons), and a fully operational (including diesel, water, etc.) weight of 170 tonnes (167.3 long tons; 187.4 short tons).
Up to four trainsets can be coupled together into a single train. However, there are problems associated with this configuration, so in the first instance it was decided to have the IC4 approved using one trainset only, with approval for multi-unit configurations to be sought later. Since a single trainset is too short for efficient long-distance operations, the first trains were used mainly for regional services. In December 2016, DSB gave up the efforts to connect four trainsets.
The design of the train is the outcome of cooperation between DSB's own designers, with an emphasis on Nordic minimalist design, and the Italian design company Pininfarina (famous for designing Ferrari cars) emphasizing Italian chic and curved lines. Externally, the bullet-shaped extremities at each end of the trainset—which are familiar from high-speed trains throughout Europe—represent a break with the design of the IC3 train, whose passengers are able to cross over between trainsets. The train interior features natural materials consistent with Scandinavia's design tradition, an audio/video information system with seat reservation displays, and a lounge area.
The IC4 train has become a contentious issue in Danish politics, mainly because of the long delays in AnsaldoBreda’s delivery of the trains. The Danish Minister of Traffic and Energy is routinely required to submit progress updates to parliament, and DSB's choice of a heavily customised train is often criticised as being the major reason for the delays. The expense involved in lengthening the platforms of several stations along the IC4 routes is the source of much additional criticism. In November 2006, it was revealed that the trains appeared to be working properly, but that the formal documentation requirements of the safety authorities were preventing the train from entering service fully. By the end of October 2007, four IC4 units had entered regional service in Jutland. However, service was suspended at the end of February 2008 because of problems with exhaust fumes. There have been many faults that did not really prevent the train from being used, but were still unacceptable, such as spurious warnings and various other computer-related problems.
In June 2008, DSB gave AnsaldoBreda an ultimatum whereby at least 14 trains had to be approved and ready for regular service before May 2009; otherwise, the contract would be cancelled and DSB would demand its money back and return its trains to the factory. DSB had ordered a total of 83 IC4 trainsets in 2000, with delivery originally scheduled for 2003.