MOSE (Italian: Modulo Sperimentale Elettromeccanico, lit. 'Experimental Electromechanical Module') is a project intended to protect the city of Venice, Italy, and the Venetian Lagoon from flooding.
The project is an integrated system consisting of rows of mobile gates, installed on the seafloor at the Lido, Malamocco, and Chioggia inlets, that can be raised to temporarily seal off the Venetian Lagoon from the Adriatic Sea during acqua alta high tides. Together with other measures, such as coastal reinforcement, elevating of quaysides, and paving and improvement of the lagoon, MOSE is designed to protect Venice and the lagoon from tides of up to 3 metres (9.8 ft). As of 2023[update], the floodgates are raised for tides forecast to be more than 1.30 metres (4 ft 3 in).
The Consorzio Venezia Nuova is responsible for the work on behalf of the Ministry of Infrastructure and Transport – Venice Water Authority. Construction began simultaneously in 2003. On 10 July 2020, the first full test was successfully completed, and after multiple delays, cost overruns, and scandals resulted in the project missing both its 2018 completion deadline (originally a 2011 deadline) and its 2021 deadline, and is now to be finished in 2025. On 3 October 2020, the MOSE was activated for the first time in the occurrence of a high tide event, preventing some of the low-lying parts of the city (in particular piazza San Marco) from being flooded. In 2020, the experts who had conceived a set of three floodgates separating the Adriatic Sea from Venice estimated that each year they would have to raise the floodgates 5 times. Within two years after the inaugural raising of the floodgates, MOSE was activated 49 times.
Before the acronym was used to describe the entire flood protection system, MOSE referred to the 1:1 scale prototype of a gate that had been tested between 1988 and 1992 at the Lido inlet.
The name also holds a secondary meaning: "MOSE" alludes to the biblical character Moses ("Mosè" in Italian), who is remembered for parting the Red Sea.
MOSE is part of a General Plan of Interventions to safeguard Venice and the lagoon. The project was begun in 1987 by the Ministry of Infrastructure through the Venice Water Authority (the Ministry's operational arm in the lagoon) and the concessionary Consorzio Venezia Nuova. The measures already completed or underway along the coastline and in the lagoon are the most important environmental defense, restoration, and improvement program ever implemented by the Italian State.[citation needed]
In parallel with the construction of MOSE, the Venice Water Authority and Venice Local Authority are raising quaysides and paving in the city in order to protect built-up areas in the lagoon from medium high tides (below 110 centimetres (43 in), the height at which the mobile barriers will come into operation). These measures are extremely complex, particularly in urban settings such as Venice and Chioggia where the raising must take account of the delicate architectural and monumental context. Measures to improve the shallow lagoon environment are aimed at slowing degradation of the morphological structures caused by subsidence, eustatism, and erosion due to waves and wash. Work is underway throughout the lagoon basin to protect, reconstruct, and renaturalise salt marshes, mud flats and shallows; restore the environment of the smaller islands; and dredge lagoon canals and channels.
Important activities are also underway to redress pollution in the industrial area of Porto Marghera, at the edge of the central lagoon. Islands formerly used as rubbish dumps are being secured while industrial canals are being consolidated and sealed after removal of their polluted sediments.
'Baby MOSE' is the flood defence system protecting Chioggia from the most frequently occurring high waters, up to a maximum of 130 centimetres (51 in).
Hub AI
MOSE AI simulator
(@MOSE_simulator)
MOSE
MOSE (Italian: Modulo Sperimentale Elettromeccanico, lit. 'Experimental Electromechanical Module') is a project intended to protect the city of Venice, Italy, and the Venetian Lagoon from flooding.
The project is an integrated system consisting of rows of mobile gates, installed on the seafloor at the Lido, Malamocco, and Chioggia inlets, that can be raised to temporarily seal off the Venetian Lagoon from the Adriatic Sea during acqua alta high tides. Together with other measures, such as coastal reinforcement, elevating of quaysides, and paving and improvement of the lagoon, MOSE is designed to protect Venice and the lagoon from tides of up to 3 metres (9.8 ft). As of 2023[update], the floodgates are raised for tides forecast to be more than 1.30 metres (4 ft 3 in).
The Consorzio Venezia Nuova is responsible for the work on behalf of the Ministry of Infrastructure and Transport – Venice Water Authority. Construction began simultaneously in 2003. On 10 July 2020, the first full test was successfully completed, and after multiple delays, cost overruns, and scandals resulted in the project missing both its 2018 completion deadline (originally a 2011 deadline) and its 2021 deadline, and is now to be finished in 2025. On 3 October 2020, the MOSE was activated for the first time in the occurrence of a high tide event, preventing some of the low-lying parts of the city (in particular piazza San Marco) from being flooded. In 2020, the experts who had conceived a set of three floodgates separating the Adriatic Sea from Venice estimated that each year they would have to raise the floodgates 5 times. Within two years after the inaugural raising of the floodgates, MOSE was activated 49 times.
Before the acronym was used to describe the entire flood protection system, MOSE referred to the 1:1 scale prototype of a gate that had been tested between 1988 and 1992 at the Lido inlet.
The name also holds a secondary meaning: "MOSE" alludes to the biblical character Moses ("Mosè" in Italian), who is remembered for parting the Red Sea.
MOSE is part of a General Plan of Interventions to safeguard Venice and the lagoon. The project was begun in 1987 by the Ministry of Infrastructure through the Venice Water Authority (the Ministry's operational arm in the lagoon) and the concessionary Consorzio Venezia Nuova. The measures already completed or underway along the coastline and in the lagoon are the most important environmental defense, restoration, and improvement program ever implemented by the Italian State.[citation needed]
In parallel with the construction of MOSE, the Venice Water Authority and Venice Local Authority are raising quaysides and paving in the city in order to protect built-up areas in the lagoon from medium high tides (below 110 centimetres (43 in), the height at which the mobile barriers will come into operation). These measures are extremely complex, particularly in urban settings such as Venice and Chioggia where the raising must take account of the delicate architectural and monumental context. Measures to improve the shallow lagoon environment are aimed at slowing degradation of the morphological structures caused by subsidence, eustatism, and erosion due to waves and wash. Work is underway throughout the lagoon basin to protect, reconstruct, and renaturalise salt marshes, mud flats and shallows; restore the environment of the smaller islands; and dredge lagoon canals and channels.
Important activities are also underway to redress pollution in the industrial area of Porto Marghera, at the edge of the central lagoon. Islands formerly used as rubbish dumps are being secured while industrial canals are being consolidated and sealed after removal of their polluted sediments.
'Baby MOSE' is the flood defence system protecting Chioggia from the most frequently occurring high waters, up to a maximum of 130 centimetres (51 in).