Ratle Hydroelectric Plant
Ratle Hydroelectric Plant project, including a 133 m (436 ft) tall gravity dam and two power stations adjacent to one another, is a run-of-the-river hydroelectric power station, currently under construction on the Chenab River, downstream of the village near Drabshalla in Kishtwar district of the Indian Union Territory of Jammu and Kashmir. Water from the dam will be diverted through four intake tunnels about 400 m (0.25 mi) southwest to the power stations. The main power station will contain four 205 MW Francis turbines and the auxiliary power station will contain one 30 MW Francis turbine. The installed capacity of both power stations will be 850 MW. Though the pondage of the project is within the limit permitted under the India-Pakistan Indus Water Treaty (IWT), Pakistan has frequently tried to cause roadblocks for the project with allegation that it violates the Indus Waters Treaty, India unilaterally suspended the IWT in April 2025 to mitigate any roadblocks from Pakistan.
In June 2010, Prime Minister Manmohan Singh approved the project and chief minister Omar Abdullah initiated the tendering process for construction of 690 MW Rattle HEP. In October 2012, the Jammu and Kashmir state cabinet approved the enhanced capacity from 690 MW to 850 MW, Prime Minister Manmohan Singh laid the foundation stone in June 2013, and in October 2013 the project was awarded to Hyderabad-based GVK Energy Limited on a build-own-operate-transfer basis for a 35 year period.
In 2017, Pakistan wanted a Court of Arbitration (CoA) to decide the disputed issues. India had instead sought for a Neutral Expert. Pakistan raised objections citing violations of the Indus Water Treaty (IWT) which were being parallelly undergoing arbitration by a Court of Arbitration (CoA) and a World Bank-appointed Neutral Expert in 2022. The disputes points, mostly technical in nature, were raised on the project.
The CoA also indicated that the objections to the project were submitted by Pakistan after a period of three months not meeting the Annexure D (10) stipulation of IWT. Annexure D (10) says that if no objection is received by India from Pakistan within the specified period of three months, then Pakistan shall be deemed to have no objection to the project.
In November 2018, India decided to commence the construction of the project considering Pakistan's objection invalid under Indus Waters Treaty obligations, after the World Bank has informed India and Pakistan in August 2017 that construction by India meets the IWT conditions. Push for this was provided by the Prime Minister Narendra Modi to ensure that the water crisis for Punjab in India can be solved. After a February 2019 Memorandum of Understanding (MoU) between NHPC Limited, Jammu & Kashmir State Power Development Department (JKPDD) and J&K State Power Development Corporation (JKSPDC), the construction works by India started in December 2019, triggering new protest by Pakistan to World Bank against the dam. In January 2022, after various delays the construction of the project finally commenced by the EPC contractor "Megha Engineering Ltd".
The 850MW facility is expected to generate up to 3,136 million units of electricity in a year. The Public Investment Board (PIB) of the Ministry of Finance, Government of India, recommended an investment approval of $690m (Rs52.82bn) for the project in September 2020.
Hub AI
Ratle Hydroelectric Plant AI simulator
(@Ratle Hydroelectric Plant_simulator)
Ratle Hydroelectric Plant
Ratle Hydroelectric Plant project, including a 133 m (436 ft) tall gravity dam and two power stations adjacent to one another, is a run-of-the-river hydroelectric power station, currently under construction on the Chenab River, downstream of the village near Drabshalla in Kishtwar district of the Indian Union Territory of Jammu and Kashmir. Water from the dam will be diverted through four intake tunnels about 400 m (0.25 mi) southwest to the power stations. The main power station will contain four 205 MW Francis turbines and the auxiliary power station will contain one 30 MW Francis turbine. The installed capacity of both power stations will be 850 MW. Though the pondage of the project is within the limit permitted under the India-Pakistan Indus Water Treaty (IWT), Pakistan has frequently tried to cause roadblocks for the project with allegation that it violates the Indus Waters Treaty, India unilaterally suspended the IWT in April 2025 to mitigate any roadblocks from Pakistan.
In June 2010, Prime Minister Manmohan Singh approved the project and chief minister Omar Abdullah initiated the tendering process for construction of 690 MW Rattle HEP. In October 2012, the Jammu and Kashmir state cabinet approved the enhanced capacity from 690 MW to 850 MW, Prime Minister Manmohan Singh laid the foundation stone in June 2013, and in October 2013 the project was awarded to Hyderabad-based GVK Energy Limited on a build-own-operate-transfer basis for a 35 year period.
In 2017, Pakistan wanted a Court of Arbitration (CoA) to decide the disputed issues. India had instead sought for a Neutral Expert. Pakistan raised objections citing violations of the Indus Water Treaty (IWT) which were being parallelly undergoing arbitration by a Court of Arbitration (CoA) and a World Bank-appointed Neutral Expert in 2022. The disputes points, mostly technical in nature, were raised on the project.
The CoA also indicated that the objections to the project were submitted by Pakistan after a period of three months not meeting the Annexure D (10) stipulation of IWT. Annexure D (10) says that if no objection is received by India from Pakistan within the specified period of three months, then Pakistan shall be deemed to have no objection to the project.
In November 2018, India decided to commence the construction of the project considering Pakistan's objection invalid under Indus Waters Treaty obligations, after the World Bank has informed India and Pakistan in August 2017 that construction by India meets the IWT conditions. Push for this was provided by the Prime Minister Narendra Modi to ensure that the water crisis for Punjab in India can be solved. After a February 2019 Memorandum of Understanding (MoU) between NHPC Limited, Jammu & Kashmir State Power Development Department (JKPDD) and J&K State Power Development Corporation (JKSPDC), the construction works by India started in December 2019, triggering new protest by Pakistan to World Bank against the dam. In January 2022, after various delays the construction of the project finally commenced by the EPC contractor "Megha Engineering Ltd".
The 850MW facility is expected to generate up to 3,136 million units of electricity in a year. The Public Investment Board (PIB) of the Ministry of Finance, Government of India, recommended an investment approval of $690m (Rs52.82bn) for the project in September 2020.