Hubbry Logo
search
logo
1912250

THTR-300

logo
Community Hub0 Subscribers
Write something...
Be the first to start a discussion here.
Be the first to start a discussion here.
See all
THTR-300

The THTR-300 was a thorium cycle high-temperature nuclear reactor rated at 300 MW electric (THTR-300) in Hamm-Uentrop, West Germany. It started operating in 1983, synchronized with the grid in 1985, operated at full power in February 1987 and was shut down on 1 September 1989. The THTR-300 served as a prototype high-temperature reactor (HTR) to use the TRISO pebble fuel produced by the AVR, an experimental pebble bed operated by VEW (Vereinigte Elektrizitätswerke Westfalen). The THTR-300 cost 2.05 billion and was predicted to cost an additional €425 million through December 2009 in decommissioning and other associated costs. The German state of North Rhine Westphalia, Federal Republic of Germany, and Hochtemperatur-Kernkraftwerk GmbH (HKG) financed the THTR-300’s construction.

On 4 June 1974, the Council of the European Communities established the Joint Undertaking "Hochtemperatur-Kernkraftwerk GmbH" (HKG).

The electrical generation part of the THTR-300 was finished late due to ever-newer requirements and licensing procedures. It was constructed in Hamm-Uentrop from 1970 to 1983 by Hochtemperatur-Kernkraftwerk GmbH (HKG). Heinz Riesenhuber, Federal Secretary of Research at that time, inaugurated it, and it first went critical on 13 September 1983. It started generating electricity on 9 April 1985, but did not receive permission from the atomic legal authorizing agency to feed electricity to the grid until 16 November 1985. It operated at full power in February 1987 and was shut down on 1 September 1989, after operating for less than 16,000 hours.

Because the operator did not expect the decision to decommission the facility, the plant was put into "safe enclosure" status, given that this was the only technical solution for fast decommissioning, especially in consideration of the lack of a final storage facility.

The THTR-300 was a helium-cooled high-temperature reactor with a pebble bed core consisting of approximately 670,000 spherical fuel compacts each 6 centimetres (2.4 in) in diameter with particles of uranium-235 and thorium-232 fuel embedded in a graphite matrix. The pressure vessel that contained the pebbles was prestressed concrete. The THTR-300's power conversion system was similar to the Fort St. Vrain reactor in the USA, in that the reactor coolant transferred the reactor core's heat to water.

The thermal output of the core was 750 megawatts; heat was transferred to the helium coolant, which then transported its heat to water, which then was used to generate electricity via a Rankine cycle. Because this system used a Rankine cycle, water could occasionally ingress into the helium circuit. [citation needed] The electric conversion system produced 308 megawatts of electricity. The waste heat from the THTR-300 was exhausted using a dry cooling tower.

On 4 May 1986 fuel pebbles became lodged in the fuel feeding system due to handling errors by the control room operator, specifically the manual override of the automated fuel loading mechanism, a deviation from standard operating procedures. Consequently, radioactive helium containing aerosols was released to the environment via the feed system's exhaust air chimney. The incident initially went unnoticed due to the overlap with radioactive fallout from the Chernobyl disaster, complicating attribution. An anonymous informant from the THTR-300 workforce was the first to blow the whistle on the incident, and alleged that there was a deliberate attempt to conceal the radioactive emissions from authorities and environmental groups. The reactor operators had up to this point concealed the incident from regulatory authorities, then denied any irregularities, claiming that any emissions were within permissible limits and were part of normal operations. They attributed the detected radioactivity to routine discharges or to the existing contamination from Chernobyl. Official investigations were delayed, and environmental monitoring stations eventually identified unusual levels of radioactive Protactinium-233 (²³³Pa) isotopes, inconsistent with fallout from Chernobyl.

The plant had to be ordered to shut down while the effects of the incident were assessed. Later analysis showed that the plant had released radioactive aerosols, estimated at up to 2 · 108 Bq, likely slightly below 180-day operation limits of 1,85 · 108 Bq, yet possibly above daily limits of 0,74 · 108 Bq. The exact amount of released material could never be determined. Control room operators, when confronted with radiation alarms, disabled aerosol measuring equipment and failed to change filters that would have allowed for exact measurements of the release, again deviating from procedures.

See all
User Avatar
No comments yet.