Recent from talks
Nothing was collected or created yet.
Rivne Nuclear Power Plant
View on WikipediaRivne Nuclear Power Plant (also called Rovno[1]) is a nuclear plant in Ukraine in Rivne Oblast, which operates the first VVER-440 reactors to be constructed in Ukraine.
Key Information
The Regulatory Committee of Ukraine, during a meeting in Varash, adopted a decision on extending the lifetime of Rivne power units 1 and 2 by 20 years.[2]
The power station has four reactors with a nameplate capacity of just over 2500 MWe. In 2018 unit 3, after modernization, received a life-extension license extending its operation by 20 years until 2037.[3]
History
[edit]The plant dates back to 1971, when the design of the West Ukrainian NPP, which was later renamed Rivne NPP, began.[citation needed]
Construction of the plant began in 1973. The first two power units with VVER-440 reactors were commissioned in 1980–1981, and the 3rd power unit, the millionth unit, was commissioned in 1986.[citation needed]
Since 1991, it has been guarded by the 5th NPP Protection Battalion.
Construction resumed in 1993 after the moratorium was lifted. A survey of Unit 4 was conducted, a program for its modernization was prepared, and a dossier for the construction completion project was prepared. Public hearings on this issue were also held. On October 10, 2004, Rivne NPP Unit 4 was put into operation. The reactor installation of the new Rivne NPP unit belongs to the modern series (VVER-1000).[citation needed]
In recent years, RNPP has been generating about 11–12 billion kWh of electricity, which is 16% of the production at nuclear power plants. On July 2, 2018, it was announced that preparations for the construction of power unit No. 5 were underway.[citation needed]
In early December 2018, a special train was demonstrated on the territory of the Rivne Nuclear Power Plant to transport waste to the repository. The HI-TRAC 190 transshipment container was tested. After loading, the container will be transported from the Rivne NPP to the storage facility in the Chornobyl zone. The container is 3 meters long and weighs 84 tons. The container will be transported from the station to the storage facility on a special railroad platform built specifically for this purpose. It will be protected from accidental collisions by a "softening" car, and the train itself will be under the control of paramilitary guards.[citation needed]
In early February 2019, it became known that the plant's engineers had increased the capacity of Unit 3 by 10 MW.[4]
On December 27, 2019, the radioactive waste treatment plant (RWTP) was launched at the Rivne Nuclear Power Plant.[5]
On the night of December 12, 2020, power unit No. 1 was automatically shut down. According to the announced data, the shutdown occurred as a result of the automatic protection system response due to the shutdown of one of the unit's turbines.[6]
In December 2020, the Technical Center for Automated Remote Metal Inspection was put into operation.[7]
The Russian-Ukrainian war
[edit]During the massive missile attack on Ukraine on November 15, 2022, the NPP lost connection with one of the 750 kV power lines. The plant's power had to be reduced, and one of the four units was automatically shut down.[8]
On July 1, 2023, President of Ukraine Volodymyr Zelenskyy visited the Rivne NPP and held a meeting of the Supreme Commander-in-Chief of the Armed Forces of Ukraine.[9]
On October 30, 2023, according to a report by the Ministry of Energy, the IAEA completed an unannounced inspection at the Rivne Nuclear Power Plant. The inspection was conducted by IAEA inspectors with the participation of an inspector from the State Nuclear Regulatory Inspectorate of Ukraine to verify the absence of undeclared nuclear materials.[10][11]
| Station | Type | Net capacity | Initial criticality | Grid date |
|---|---|---|---|---|
| Unit 1 | VVER-440/213 | 361 MWe | Dec 1980 | Sep 1981 |
| Unit 2 | VVER-440/213 | 384 MWe | Dec 1981 | Jul 1982 |
| Unit 3 | VVER-1000/320 | 950 MWe | Nov 1986 | May 1987 |
| Unit 4 | VVER-1000/320 | 950 MWe | Sep 2004 | Oct 2004 |
| Unit 5 (suspended plan) | VVER-1000/320 | 950 MWe | N/A | N/A |
-
Logo[12]
See also
[edit]References
[edit]- ^ "IAEA country statistics". IAEA. Archived from the original on 2022-04-15. Retrieved 2022-04-15.
- ^ "Rivne NPP". Energoatom. 3 March 2022. Archived from the original on 4 March 2022. Retrieved 3 March 2022.
- ^ "Life extension for Ukraine's Rovno 3". Nuclear Engineering International. Progressive Media International. 23 July 2018. Archived from the original on 25 July 2018. Retrieved 25 July 2018.
- ^ Леонова, Вікторія (6 February 2019). "На Рівненській АЕС вдалося підвищити потужність енергоблока № 3". golos.com.ua (in Ukrainian).
- ^ "На Рівненській атомній станції запустили комплекс з перероблювання радіоактивних відходів". uprom.info/. Національний промисловий портал. 2020-01-07. Archived from the original on 2021-02-24. Retrieved 8 January 2020.
- ^ "Відключено від мережі енергоблок №1 РАЕС". energoatom.com.ua. Energoatom. 2020-12-12. Archived from the original on 2020-12-12. Retrieved 12 December 2020.
- ^ "RNPP - На РАЕС запрацював перший в атомній галузі країни технічний центр контролю металу". www.rnpp.rv.ua. Retrieved 2021-03-22.[dead link]
- ^ "МАГАТЕ: Через ракетну атаку росіян постраждали дві українські АЕС". Українська Правда. 2022-11-17.
- ^ Президент відвідав Рівненську АЕС і провів засідання Ставки Верховного Головнокомандувача. 01.07.2023, 21:06
- ^ "МАГАТЕ проінспектувала Рівненську АЕС: шукала незаявлені ядерні матеріали" [IAEA inspected Rivne Nuclear Power Plant: searched for undeclared nuclear materials.]. www.pravda.com.ua. 10 January 2023. Retrieved 2024-07-17.
- ^ Pylypiv, Igor (30 October 2023). "МАГАТЕ провело неоголошену перевірку на Рівненській АЕС" [IAEA conducted an unannounced inspection at Rivne Nuclear Power Plant]. Економічна правда (in Ukrainian). Retrieved 2024-07-17.
- ^ "Рівненська Атомна Електростанція" [Rivne Nuclear Power Plant]. Rivne Nuclear Power Plant (in Ukrainian). Energoatom. Archived from the original on 4 March 2022. Retrieved 15 April 2022.
External links
[edit]Rivne Nuclear Power Plant
View on GrokipediaSite and Design
Location and Infrastructure
The Rivne Nuclear Power Plant is located in the Polissia region of Rivne Oblast, northern Ukraine, approximately 3 km east of the city of Varash on the banks of the Styr River.[3] [1] The site lies near the border between Rivne and Volyn oblasts, with low seismic activity and proximity to European Union borders facilitating potential export considerations.[1] Varash serves as the satellite town for the plant's workforce.[1] The infrastructure includes four reactor units with a combined electrical capacity of 2,835 MW, supported by cooling systems drawing makeup water from the Styr River and featuring six natural draft cooling towers, each handling 100,000 m³/h of circulation.[3] [1] Power transmission infrastructure connects the plant to the national grid via two 750 kV lines, four 330 kV lines, and five 110 kV lines, including a 353 km 750 kV line to the Kyiv substation completed in 2015.[3] Additional facilities encompass makeup water purification systems operational since 2007 and an automated radiation monitoring network installed in 2004.[1] The site also includes a Radioactive Waste Treatment Facility commissioned in 2018.[1]Reactor Types and Technical Features
The Rivne Nuclear Power Plant features four pressurized water reactors (PWRs) of the VVER design, developed in the Soviet Union. Units 1 and 2 are VVER-440 Model V-213 reactors, each with a gross electrical capacity of 440 MWe, while Units 3 and 4 are VVER-1000 Model V-320 reactors, each rated at approximately 1,000 MWe gross.[1][3] The total installed capacity exceeds 2,800 MWe, contributing significantly to Ukraine's electricity grid.[1] VVER reactors utilize light water as both coolant and moderator, with fuel assemblies arranged in a hexagonal lattice within the core. Unlike Western PWRs, VVER designs incorporate horizontal steam generators and, for the VVER-440 models, six primary coolant loops per unit, each equipped with GTsN-317 main circulation pumps and reactor coolant piping.[3][4] The VVER-1000 units employ four primary loops, high-capacity pressurizers to maintain system pressure around 15.7 MPa, and steam generators capable of handling secondary side pressures up to 6.3 MPa.[3] These configurations enhance thermal efficiency and support refueling outages every 12-18 months, with core designs optimized for enriched uranium oxide fuel.[4]| Unit | Reactor Model | Gross Capacity (MWe) | Primary Loops | Key Features |
|---|---|---|---|---|
| 1 | VVER-440/V-213 | 440 | 6 | Horizontal SGs, hexagonal fuel |
| 2 | VVER-440/V-213 | 440 | 6 | Horizontal SGs, hexagonal fuel |
| 3 | VVER-1000/V-320 | 1,000 | 4 | Vertical SGs in later models, soluble boron control |
| 4 | VVER-1000/V-320 | 1,000 | 4 | Enhanced safety systems post-Chernobyl |
History
Construction and Commissioning (1970s-1980s)
The Rivne Nuclear Power Plant's design phase commenced in 1971 under the Soviet Ministry of Energy and Electrification, initially designated as the West Ukraine Nuclear Power Plant to bolster electricity supply in the western Ukrainian SSR. Construction of the site infrastructure and first reactor unit began on August 1, 1973, amid the USSR's broader nuclear expansion program, which prioritized pressurized water reactors for regional grid integration. The project involved standardized VVER-440/213 designs, with civil works focusing on the reactor buildings, turbine halls, and cooling systems adapted to the local geology near the Styr River.[3][6] Unit 1, featuring a VVER-440/213 reactor with a gross capacity of 420 MWe, achieved first criticality on December 17, 1980, following seven years of on-site assembly and testing. It synchronized to the grid shortly thereafter and entered full commercial operation on September 22, 1981, marking the plant's initial contribution to the Soviet Unified Energy System. Unit 2, a near-identical VVER-440/213 unit with 415 MWe gross capacity, followed a parallel construction timeline, reaching first criticality on December 19, 1981, and commercial operation on July 29, 1982. These early units incorporated Soviet-era safety features such as containment structures and emergency core cooling systems, though later assessments highlighted limitations in seismic design given the region's moderate earthquake risk.[7][8][9] The commissioning of Units 1 and 2 proceeded without major publicized delays or incidents during the late Soviet period, reflecting centralized planning efficiencies but also opaque reporting practices typical of state-controlled projects. By the mid-1980s, groundwork for Unit 3 (a larger VVER-1000) had initiated, extending the plant's development into the decade, though its full commissioning fell in 1986. These phases established Rivne as a key node in Ukraine's nuclear fleet, generating baseline load power for industrial and residential demands in the northwest.[2][10]Expansion and Post-Soviet Operations (1990s-2000s)
Following Ukraine's declaration of independence in 1991, the Rivne Nuclear Power Plant encountered significant operational and expansion hurdles amid the Soviet Union's dissolution and the lingering effects of the 1986 Chernobyl disaster. A moratorium on new nuclear construction, enacted by the Verkhovna Rada in August 1990, halted work on Unit 4 (VVER-1000, 1,000 MWe), which was approximately 80% complete at the time.[2][11] Existing Units 1 through 3 (two VVER-440s and one VVER-1000) continued operations but faced economic strains, including reduced electricity demand, funding shortages for fuel and maintenance, and a sharp decline in national power generation from 296 TWh in 1990 to much lower levels by the mid-1990s.[11] Construction on Unit 4 resumed in 1993 after the moratorium was lifted, supported by modernization programs and international assessments. The International Atomic Energy Agency (IAEA) conducted Operational Safety Review Team (OSART) missions in 1996, evaluating safety practices and commending personnel qualifications.[2] In 2000, the European Bank for Reconstruction and Development (EBRD) approved a $215 million loan toward completion, though funding was later adjusted to $42 million amid delays.[11] Unit 4, modernized with involvement from Framatome ANP and Russia's Atomstroyexport, was connected to the grid in October 2004, marking a key post-Soviet expansion milestone.[11] Commercial operations for Unit 4 commenced in April 2006 following state acceptance, boosting the plant's total capacity to 2,835 MWe and enabling annual electricity production to exceed 17 billion kWh.[2] Further IAEA OSART reviews in 2003 and 2008 affirmed ongoing safety enhancements.[2] Between 2004 and 2010, additional modernizations were funded by EBRD and Euratom loans totaling $125 million, addressing post-Soviet infrastructure gaps and improving reliability.[11] These efforts solidified Rivne's role in Ukraine's energy supply despite persistent economic and supply chain challenges from reliance on Russian nuclear fuel and equipment.[11]Modernization and Life Extensions (2010s)
In December 2010, Ukraine's State Nuclear Regulatory Inspectorate approved a 20-year extension of the operational licenses for Rivne Nuclear Power Plant units 1 and 2, VVER-440 reactors originally designed for a 30-year lifespan ending in 2010 and 2011, respectively.[3][2] This decision followed comprehensive safety reviews, including probabilistic safety assessments and environmental impact evaluations under the Espoo Convention, with investments exceeding hundreds of millions of dollars in upgrades such as enhanced reactor vessel integrity monitoring and control systems.[11][12] The extensions aimed to maintain reliable baseload power amid Ukraine's energy security needs, though environmental groups like the National Ecological Centre of Ukraine raised concerns over procedural compliance and long-term risk assessments.[13] Preparations for unit 3's life extension began in the mid-2010s, with Energoatom conducting upgrades to meet extended operation criteria.[14] In 2010, the second stage of the unit's computer information system modernization was completed, improving operational monitoring and data processing.[15] Additional efforts included retrofitting physical protection systems for reactor unit 3 to bolster nuclear security against potential threats.[16] Extensive modernization of unit 3, a 1,000 MWe VVER-1000 reactor commissioned in 1986, commenced in December 2017, focusing on safety-critical components like steam generators and instrumentation to extend service beyond its projected 2016-2017 endpoint.[17] The State Nuclear Regulatory Inspectorate granted a 20-year license extension in July 2018, allowing operation until December 2037, conditional on intermediate reviews after 10 years; the unit was reconnected to the grid on July 24, 2018, following these works.[17][18] These measures aligned with broader Ukrainian nuclear policy to prolong asset life amid economic constraints and fossil fuel import dependencies, supported by international standards from IAEA and WANO peer reviews.[1]Operations and Capacity
Power Generation and Reliability
The Rivne Nuclear Power Plant operates four pressurized water reactors with a total net installed capacity of 2,835 MW, enabling it to supply a substantial portion of Ukraine's electricity needs from the western region. Three units employ VVER-440/213 designs, each rated at approximately 365–381 MW net, while the fourth unit features a VVER-1000/320 design with 950 MW net capacity. Electricity output is transmitted via connections to the national grid at 750 kV, 330 kV, and 110 kV levels, supporting baseload power generation critical for grid stability. In 2020, the plant delivered 15,796 GWh to the grid, reflecting its role in producing around 16% of Ukraine's nuclear-generated electricity under normal conditions.[3][1]| Unit | Reactor Type | Net Capacity (MW) | Commercial Operation Date |
|---|---|---|---|
| 1 | VVER-440/213 | 381 | October 1, 1980 |
| 2 | VVER-440/213 | 376 | December 29, 1981 |
| 3 | VVER-440/213 | ~380 | March 4, 1986 |
| 4 | VVER-1000/320 | 950 | October 10, 2004 |
