Recent from talks
Nothing was collected or created yet.
Gantt chart
View on Wikipedia

A Gantt chart is a bar chart that illustrates a project schedule.[1] It was designed and popularized by Henry Gantt c. 1910–1915.[2][3] Modern Gantt charts also show the dependency relationships between activities and the current schedule status.
Definition
[edit]A Gantt chart is a type of bar chart[4][5] that illustrates a project schedule.[6] This chart lists the tasks to be performed on the vertical axis, and time intervals on the horizontal axis.[4][7] The width of the horizontal bars in the graph shows the duration of each activity.[7][8] Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project.[1] Terminal elements and summary elements constitute the work breakdown structure of the project. Modern Gantt charts also show the dependency (i.e., precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent-complete shadings and a vertical "TODAY" line.
Gantt charts are sometimes equated with bar charts.[8][9]
Gantt charts are usually created initially using an early start time approach, where each task is scheduled to start immediately when its prerequisites are complete. This method maximizes the float time available for all tasks.[4]
History
[edit]Widely used in project planning in the present day, Gantt charts were considered revolutionary when introduced.[10] The first known tool of this type was developed in 1896 by Karol Adamiecki, who called it a harmonogram.[11] Adamiecki, however, published his chart only in Russian and Polish which limited both its adoption and recognition of his authorship.
In 1912, Hermann Schürch published what could be considered Gantt charts while discussing a construction project. Charts of the type published by Schürch appear to have been in common use in Germany at the time;[12][13][14] however, the prior development leading to Schürch's work is unclear.[15] Unlike later Gantt charts, Schürch's charts did not display interdependencies, leaving them to be inferred by the reader. These were also static representations of a planned schedule.[16]
The chart is named after Henry Gantt (1861–1919), who designed his chart around the years 1910–1915.[2][3] Gantt originally created his tool for systematic, routine operations. He designed this visualization tool to more easily measure productivity levels of employees and gauge which employees were under- or over-performing. Gantt also frequently included graphics and other visual indicators in his charts to track performance.[17]
One of the first major applications of Gantt charts was by the United States during World War I, at the instigation of General William Crozier.[18]
The earliest Gantt charts were drawn on paper and therefore had to be redrawn entirely in order to adjust to schedule changes. For many years, project managers used pieces of paper or blocks for Gantt chart bars so they could be adjusted as needed.[19] Gantt's collaborator Walter Polakov introduced Gantt charts to the Soviet Union in 1929 when he was working for the Supreme Soviet of the National Economy. They were used in developing the First Five Year Plan, supplying Russian translations to explain their use.[20][21]
In the 1980s, personal computers allowed widespread creation of complex and elaborate Gantt charts. The first desktop applications were intended mainly for project managers and project schedulers. With the advent of the Internet and increased collaboration over networks at the end of the 1990s, Gantt charts became a common feature of web-based applications, including collaborative groupware.[citation needed] By 2012, almost all Gantt charts were made by software which can easily adjust to schedule changes.[19]
In 1999, Gantt charts were identified as "one of the most widely used management tools for project scheduling and control".[4]
Example
[edit]In the following tables there are seven tasks, labeled a through g. Some tasks can be done concurrently (a and b) while others cannot be done until their predecessor task is complete (c and d cannot begin until a is complete). Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated using the beta probability distribution for the time estimates, using the formula (O + 4M + P) ÷ 6.
| Activity | Predecessor | Time estimates (in days) | Expected time (TE) | ||
|---|---|---|---|---|---|
| Opt. (O) | Normal (M) | Pess. (P) | |||
| a | — | 2 | 4 | 6 | 4.00 |
| b | — | 3 | 5 | 9 | 5.33 |
| c | a | 4 | 5 | 7 | 5.17 |
| d | a | 4 | 6 | 10 | 6.33 |
| e | b, c | 4 | 5 | 7 | 5.17 |
| f | d | 3 | 4 | 8 | 4.50 |
| g | e | 3 | 5 | 8 | 5.17 |
Once this step is complete, one can draw a Gantt chart or a network diagram.

Progress Gantt charts
[edit]In a progress Gantt chart, tasks are shaded in proportion to the degree of their completion: a task that is 60% complete would be 60% shaded, starting from the left. A vertical line is drawn at the time index when the progress Gantt chart is created, and this line can then be compared with shaded tasks. If everything is on schedule, all task portions left of the line will be shaded, and all task portions right of the line will not be shaded. This provides a visual representation of how the project and its tasks are ahead or behind schedule.[22]
Linked Gantt charts
[edit]Linked Gantt charts contain lines indicating the dependencies between tasks. However, linked Gantt charts quickly become cluttered in all but the simplest cases. Critical path network diagrams are superior to visually communicate the relationships between tasks.[23] Nevertheless, Gantt charts are often preferred over network diagrams because Gantt charts are easily interpreted without training, whereas critical path diagrams require training to interpret.[9] Gantt chart software typically provides mechanisms to link task dependencies, although this data may or may not be visually represented.[4] Gantt charts and network diagrams are often used for the same project, both being generated from the same data by a software application.[4]
Criticism
[edit]The Gantt chart's widespread adoption is perhaps less based on its universal application and suitability as perhaps the absence of any alternative. It flattens assumptions, which in turn can constrain the ability to respond to uncertainty and change.[24]
See also
[edit]- Critical path method
- Data and information visualization
- Event chain methodology
- Float (project management)
- List of project management software, which includes specific Gantt chart software.
- Program evaluation and review technique (PERT)
- Progress bar
- Event chain diagram
Citations
[edit]- ^ a b Project Management Institute 2021, Glossary §3 Definitions.
- ^ a b Gantt 1910.
- ^ a b Morris 1997, p. 7.
- ^ a b c d e f Klein 1999, p. 49.
- ^ Richman 2002, pp. 97, 117, 276.
- ^ Kumar, Pankaja Pradeep (2005). "Effective Use of Gantt Chart for Managing Large Scale Projects". Cost Engineering. 47 (7). Morgantown, WV: American Association of Cost Engineers: 13–21. ISSN 0274-9696. OCLC 209778284.
- ^ a b Richman 2002, pp. 117, 276.
- ^ a b Selig 2008, p. 235.
- ^ a b Flouris & Lock 2012, p. 236, Chapter 12.
- ^ Wilson 2003.
- ^ Marsh 1974, p. 32.
- ^ Weaver 2012a, pp. 5–6.
- ^ Weaver 2012b, pp. 4–6.
- ^ Weaver 2014, pp. 6–7.
- ^ Weaver 2014, p. 7.
- ^ Weaver 2014, p. 6.
- ^ Geraldi, Joana; Lechter, Thomas (2012). "Gantt charts revisited". International Journal of Managing Projects in Business. 5 (4): 578-594. doi:10.1108/17538371211268889.
- ^ Clark 1922.
- ^ a b Flouris & Lock 2012, p. 281, Chapter 14.
- ^ Kelly, D. J. (2004) "Marxist Manager Amidst the Progressives: Walter N. Polakov and the Taylor Society", Journal of Industrial History, 6(2), November 2004, 61-75
- ^ Olson, Richard G. (2015). Scientism and Technocracy in the Twentieth Century: The Legacy of Scientific Management. Lexington Books. ISBN 9781498525718. Retrieved 25 September 2018.
- ^ Klein 1999, pp. 56–57.
- ^ Flouris & Lock 2012, p. 239, Chapter 12.
- ^ "Gantt charts revisited: A critical analysis of its roots and implications to the management of projects today". ResearchGate. Archived from the original on 1 December 2024. Retrieved 4 October 2025.
References
[edit]- Clark, Wallace (1922). The Gantt Chart: A Working Tool of Management. New York, NY: Ronald Press.
- Flouris, Triant G.; Lock, Dennis (2012). Managing Aviation Projects from Concept to Completion. Ashgate Publishing Limited. ISBN 978-1-4094-8613-8.
- Gantt, H.L. (1910). "Work, Wages and Profit". Engineering Magazine. New York; republished as Work, Wages and Profits. Easton, Pennsylvania: Hive Publishing Company. 1974. ISBN 0-87960-048-9.
- Klein, R. (1999). Scheduling of Resource-Constrained Projects. Operations Research/Computer Science Interfaces Series. Springer US. ISBN 978-0-7923-8637-7.
- Marsh, Edward R. (1974). "The Harmonogram of Karol Adamiecki". Academy of Management Proceedings. 1974: 32. doi:10.5465/ambpp.1974.17530521. ISSN 0065-0668.
- Morris, Peter W. G. (1997) [1994]. The Management of Projects. Thomas Telford. ISBN 978-0-7277-2593-6.
- A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). Newtown Square, Pennsylvania: Project Management Institute. 2021. ISBN 978-1-62825-664-2.
- Richman, L. (2002). Project Management Step-by-step. Amacom. p. 117. ISBN 978-0-8144-2657-9.
- Selig, Gad J. (2008). Implementing IT Governance: A Practical Guide to Global Best Practices in IT Management. Van Haren Publishing. ISBN 978-90-8753-774-6.
- Weaver, Patrick (2012a). "Henry L Gantt, 1861–1919: A retrospective view of his work" (PDF). PM World Journal. Retrieved 29 January 2018 – via Mosaic Projects. (It is unclear when this was last modified. The PDF metadata indicates 2015, and a note in the text says "Augmented with additional materials received since publication".)
- Weaver, Patrick (2012b). "Henry L Gantt, 1861–1919: Debunking the myths, a retrospective view of his work" (PDF). PM World Journal. 1 (5).
- Weaver, Patrick (2014). "A Brief History of Scheduling: Back to the Future (2nd ed.)" (PDF). PM World Journal. 3 (8). Adapted from a 2006 presentation at conference myPrimavera06, Canberra.
- Wilson, James M. (2003). "Gantt charts: A centenary appreciation" (PDF). European Journal of Operational Research. 149 (2): 430–437. doi:10.1016/S0377-2217(02)00769-5. Archived from the original (PDF) on 26 November 2013. Retrieved 28 July 2013.
Further reading
[edit]- Burkhard, Remo Aslak; Meier, Michael; Rodgers, Peter; Smis, Matthias Thomas Jelle; Stott, Jonathan (2005). Knowledge visualization: A comparative study between Project Tube Maps and Gantt Charts. 5th International Conference on Knowledge Management. Graz, Austria: University of Kent. Retrieved 17 September 2017.
- Geraldi, Joana; Lechter, Thomas (2012). "Gantt charts revisited: A critical analysis of its roots and implications to the management of projects today". International Journal of Managing Projects in Business. 5 (4): 578–594. doi:10.1108/17538371211268889.
- Kumar, Pankaja Pradeep (2005). "Effective use of Gantt chart for managing large scale projects". Cost Engineering. 47 (7): 14–21. ISSN 0274-9696. Archived from the original on 17 September 2017. Retrieved 17 September 2017.
- Marsh, Edward R. (1975). "The Harmonogram of Karol Adamiecki". Academy of Management Journal. 18 (2): 358–364. JSTOR 255537.
- Maylor, Harvey (2001). "Beyond the Gantt chart: Project management moving on". European Management Journal. 19 (1): 92–100. doi:10.1016/S0263-2373(00)00074-8. S2CID 153555271.
- Schürch, Hermann (1915), "Der Bau des Talüberganges bei Langwies an der elektrischen Bahn Chur-Arosa" [The construction of the valley crossing at Langwies of the Chur-Arosa electric railway line] (PDF), Armierter Beton: Monatsschrift für Theorie und Praxis des gesamten Betonbaues (Reinforced concrete: Monthly for theory and practice of the entire concrete construction) (in German), vol. 8, no. 10, Berlin: Springer, pp. 229–238, retrieved 29 January 2018
- Virine, Lev; Trumper, Michael (2013), ProjectThink. Why Good Managers Make Poor Project Choices, Gower Pub Co., ISBN 978-1409454984
- Virine, Lev; Trumper, Michael (2017), Project Risk Analysis Made Ridiculously Simple, World Scientific Publishing, ISBN 978-9814759373
- Weaver, Patrick. "Henry L. Gantt: A Retrospective view of his work". Retrieved 29 January 2018.
- Weaver, Patrick. "A Brief History of Scheduling".
External links
[edit]- Long-running discussion regarding limitations of the Gantt chart format, and alternatives, on Edward Tufte's website
Gantt chart
View on GrokipediaFundamentals
Definition and Purpose
A Gantt chart is a type of bar chart that illustrates a project schedule, featuring horizontal bars that represent the start, duration, and finish of individual tasks plotted against a horizontal time scale.[6] This visualization tool arranges tasks vertically along the y-axis while the x-axis denotes time periods, such as days, weeks, or months, allowing for a clear depiction of how project elements unfold over time.[7] The primary purpose of a Gantt chart is to offer a visual overview of project progress, resource allocation, and task sequencing, thereby supporting effective planning, coordination, and communication among team members. By highlighting timelines and interdependencies, it enables project managers to monitor milestones, identify potential delays early, and adjust schedules as needed to ensure timely completion.[6] At its core, a Gantt chart operates on fundamental principles including time-based progression from left to right, where bars extend along the timeline to indicate task durations; task dependencies implied through bar positioning, such as one bar starting only after another ends; and integration with work breakdown structures (WBS) to organize tasks hierarchically before mapping them onto the schedule.[8] This approach revolutionized project visualization by emphasizing efficiency in production and management.[9]Key Components
A Gantt chart's structure relies on several core visual elements that collectively represent project schedules in a clear, timeline-based format. These components enable project managers to visualize task sequences, durations, and interdependencies without ambiguity, supporting effective planning and monitoring.[10] Task bars form the primary visual representation of activities within a Gantt chart, depicted as horizontal lines positioned along the timeline to indicate the start date, duration, and end date of each task. The length of each bar corresponds directly to the task's estimated duration, while its placement reflects the scheduled timing, allowing for quick assessment of overlaps or gaps in the schedule.[11][10] The vertical axis serves as the organizational backbone, listing tasks or work packages in a hierarchical order, typically derived from a work breakdown structure (WBS) to break down the project into manageable components. This axis ensures tasks are presented sequentially or by phase, providing a clear inventory of all project elements from high-level deliverables to detailed activities.[10] Along the horizontal axis, the time scale delineates calendar time in units such as days, weeks, or months, often augmented by gridlines to enhance precision in reading durations and alignments. This scale anchors the entire chart to real-world timelines, facilitating comparisons between planned schedules and actual progress.[11][10] Milestones appear as distinct markers, commonly diamond-shaped, to denote significant events or deliverables that lack duration but represent critical junctures in the project lifecycle. These points highlight key approvals, completions, or deadlines, serving as checkpoints without extending across the timeline like task bars.[11][10] Dependencies are illustrated through arrows or connecting lines that link task bars, denoting basic predecessor-successor relationships where one task must precede another to maintain logical workflow. This notation, often in a simple finish-to-start format, reveals sequence constraints without delving into complex calculations.[11][12][10] A legend accompanies the chart to explain symbols and color codes, such as those differentiating planned versus actual progress or various status indicators like in-progress or completed tasks. This key ensures consistent interpretation across team members, clarifying elements like shading for partial completion.[11][10]Historical Development
Origins and Early Concepts
The concept of visually representing production schedules predates the modern Gantt chart, with early precursors emerging in the late 19th century. In 1896, Polish engineer Karol Adamiecki developed the "harmonogram," a graphical tool designed to optimize workflows in steel mill operations by displaying interdependent processes on a timeline using detachable paper strips clamped in place. Adamiecki's invention aimed to harmonize work activities for greater efficiency in industrial settings, such as rolling mills and mechanical engineering factories, though it received limited international recognition due to its initial publication in Polish in 1931.[13][14] The modern Gantt chart evolved from these ideas through the work of American mechanical engineer Henry Laurence Gantt, who refined bar chart techniques between 1910 and 1915 to better track tasks and progress in manufacturing environments.[15] Gantt's charts improved upon earlier visualizations by incorporating time scales along the horizontal axis and task durations as horizontal bars, allowing managers to monitor production against planned schedules more effectively.[16] His approach was heavily influenced by Frederick Winslow Taylor's principles of scientific management, which Gantt had applied during his time as Taylor's associate starting in 1887; these principles stressed systematic efficiency, time studies, and incentive-based worker motivation to maximize output without increasing fatigue.[16] One of the earliest significant applications of Gantt's charts occurred during World War I, when in 1917 the U.S. Navy adopted them for scheduling shipbuilding and munitions production to accelerate wartime mobilization efforts.[17] Under the guidance of industrial consultants like Gantt himself, these charts facilitated coordinated planning across arsenals and emergency fleet operations, enabling rapid scaling of resources and timelines in high-stakes government projects.[18]Evolution and Adoption
Following World War I, Gantt charts saw expanded adoption in the interwar period, particularly in large-scale construction projects such as the Hoover Dam, which began in 1931 and utilized the charts to coordinate tasks and timelines across thousands of workers.[19] During World War II, Gantt charts became integral to defense and logistics efforts, aiding in the scheduling of military production, shipbuilding, and resource management to meet wartime demands. These applications extended to coordinating complex supply chains and infrastructure builds, where the charts' visual clarity supported rapid adjustments amid resource constraints.[20] The tool's global spread was evident in non-Western contexts, notably in the Soviet Union during the 1920s, where engineer Walter Polakov introduced Gantt charts—locally termed "Ganttograms"—to support centralized planning under the New Economic Policy and early Five-Year Plans.[21] Polakov's adaptations emphasized worker involvement and production monitoring, influencing Soviet industrial organization despite political challenges.[22] In the 1950s, Gantt charts integrated with emerging network-based methods like the Critical Path Method (CPM), developed by DuPont and Remington Rand to handle time-cost trade-offs in maintenance and construction projects.[23] This combination proved vital for complex defense initiatives, such as the U.S. Navy's Polaris missile program, where CPM-derived schedules were often visualized using Gantt formats for executive oversight.[24] The 1980s marked a digitization milestone, with early computer software like Harvard Project Manager enabling automated Gantt chart creation and updates for desktop use in professional environments.[25] By the 1990s, web-based versions emerged, facilitating collaborative access over networks and integrating with broader project management systems.[26] By the late 1990s, Gantt charts were recognized as a standard tool, with a 1999 Ernst & Young survey identifying them among the top five project management techniques for scheduling and control across industries.[27]Construction and Usage
Building a Gantt Chart
Building a Gantt chart begins with a systematic process to translate project requirements into a visual schedule, emphasizing manual or conceptual methods for clarity and control. This approach ensures the chart accurately represents the project's timeline without relying on specialized software, allowing for adjustments based on real-time insights. The resulting diagram facilitates communication among team members by highlighting task sequences and overlaps in a straightforward format. The initial step involves identifying all necessary tasks through a work breakdown structure (WBS), which decomposes the overall project into sequential, manageable activities listed vertically on the left side of the chart.[6] This WBS, a standard tool in project management, helps ensure no critical elements are overlooked by breaking down high-level deliverables into specific actions, such as design, implementation, and testing phases. Next, estimate the duration of each task and assign start and end dates, considering available resources, constraints like team availability, and potential risks.[6] Durations are typically expressed in days or weeks, with start dates determined by project kickoff or predecessor completion, and end dates calculated accordingly to form the foundation for the horizontal timeline.[12] To visualize the schedule, plot horizontal bars on a timeline grid, where the vertical axis lists tasks and the horizontal axis represents time units, with each bar's length proportional to its estimated duration positioned between start and end dates.[6] This plotting step builds on core components like the task bars and time axis, creating an intuitive bar chart that illustrates overlaps and gaps at a glance.[6] Subsequently, incorporate task dependencies by drawing arrows connecting related bars to indicate relationships, such as finish-to-start links where one task must complete before another begins, and mark milestones as diamond-shaped points for critical achievements like project approvals.[6] These elements enhance the chart's utility by revealing workflow logic and key checkpoints without cluttering the visual. Finally, establish a baseline by duplicating the initial schedule bars in a lighter shade or separate layer to enable comparisons between planned and actual progress as the project unfolds.[6] This baseline serves as a reference for variance analysis, helping managers track deviations early. For manual creation, graph paper provides a simple medium: draw a grid with rows for tasks and columns for time increments, then shade bars proportionally using a ruler for precision.[28] Alternatively, spreadsheets such as Microsoft Excel and Google Sheets support conceptual building of Gantt charts. Users can start with free templates for these tools to simplify setup and building. For instance, end dates can be computed with formulas such as = Start Date + Duration - 1, where Duration is input as a number of days, facilitating dynamic adjustments.[29][30]Interpreting Gantt Charts
Interpreting a Gantt chart begins with examining the timeline, where horizontal bars represent task durations plotted against a time scale on the x-axis, allowing assessment of task overlaps to identify opportunities for parallelism and gaps that may signal potential delays. Overlapping bars indicate concurrent activities that can accelerate project completion, while gaps between sequential tasks suggest idle periods or sequencing issues that could extend the overall schedule.[31] Dependency analysis involves tracing arrows or lines connecting task bars to understand relationships, such as finish-to-start links where one task must end before another begins, helping to identify the critical path—the longest sequence of dependent tasks that determines the project's minimum duration—and bottlenecks where delays in key tasks propagate risks to subsequent ones. Tasks on the critical path have no allowable delay without impacting the project end date, whereas non-critical paths offer flexibility.[32] Progress evaluation requires comparing actual progress bars or shaded portions against baseline planned bars, often overlaid on the same chart, to quantify schedule performance using a simple duration-based metric: ((Planned duration - Actual duration) / Planned duration) × 100, where a negative value indicates the task is behind schedule and a positive value shows it is ahead. For instance, if a task planned for 10 days takes 12 days, the metric is ((10 - 12) / 10) × 100 = -20%, signaling a need for corrective action to realign the timeline. This comparison highlights deviations early, enabling adjustments to maintain project momentum.[6] Resource insights are gained by reviewing the vertical alignment of task bars in the same time period, where multiple bars stacked or overlapping for the same resource reveal overallocation, indicating that one team member or asset is assigned beyond capacity, potentially leading to burnout or delays. Tools often use color coding or workload views adjacent to the Gantt to quantify this, showing hours or percentages per day to spot imbalances and reallocate efficiently.[33] Risk identification focuses on highlighting float time, or slack, which is the buffer between the end of a dependent task and the start of its successor, calculated as the difference between the latest possible start and earliest start times for non-critical tasks. Greater slack provides a cushion against uncertainties like resource shortages, allowing delays without affecting the critical path, while minimal or zero slack on critical tasks heightens vulnerability to disruptions and requires proactive monitoring to mitigate potential project overruns.[34]Practical Examples
Simple Task Schedule
A straightforward application of a Gantt chart can be seen in planning a small product launch event, where the focus is on sequencing basic tasks over a short timeline to ensure timely completion. In this scenario, a team outlines four key tasks: conducting market research, developing promotional designs, reviewing materials for approval, and executing the launch event itself. These tasks are arranged sequentially, with the review phase dependent on the completion of design to allow for necessary feedback and revisions. The entire project spans 12 days, providing a clear overview of the schedule without delving into resource assignments or multiple parallel activities.[6] The following table summarizes the tasks, their start and end dates (assuming the project begins on Day 1), and durations:| Task | Start Date | End Date | Duration |
|---|---|---|---|
| Market Research | Day 1 | Day 3 | 3 days |
| Promotional Design | Day 4 | Day 7 | 4 days |
| Review and Approval | Day 8 | Day 9 | 2 days |
| Event Execution | Day 10 | Day 12 | 3 days |
Complex Project Illustration
To illustrate the scalability of Gantt charts, consider a software development project for a web-based customer management application, structured across multiple phases with dependencies and resource allocations to manage a team of 15 members over 9 weeks. This scenario encompasses 9 key tasks, starting with requirements gathering in weeks 1–2 and culminating in deployment in week 9, allowing for parallel execution of development activities to accelerate progress while respecting sequential constraints like testing following integration. Such phased approaches are standard in software projects to align timelines with iterative delivery.[36] In the Gantt chart visualization, horizontal bars denote task durations along a 9-week timeline, with colors differentiating phases (e.g., blue for design, green for development). Overlapping bars highlight parallel tasks, such as UI development and backend development both spanning weeks 5–7, enabling concurrent resource use by separate teams. Arrows indicate dependencies, including multiple incoming links to integration from UI, backend, and database setup tasks. Resource labels appear alongside bars (e.g., "UI Team" for UI development), and diamond-shaped markers denote milestones like the beta release at the end of week 8. This layout reveals bottlenecks, such as the wait for design completion before parallel coding begins, facilitating proactive adjustments.[37] Analysis of the chart identifies the critical path as the longest sequence of dependent tasks—requirements gathering, design, backend development, integration, and testing—which totals 9 weeks and dictates the project's minimum completion time. Any delays on this path would extend the overall timeline, underscoring the need for vigilant monitoring of these activities. The total project span remains 9 weeks, with parallels reducing idle time, and the beta release milestone serving as a checkpoint for stakeholder review before final deployment. Costs are estimated based on typical hourly rates for roles in small-scale software projects, totaling approximately $130,000.[38] The following table provides the underlying data for constructing the Gantt chart, including assignees, estimated costs, and dependencies:| Task | Start Week | End Week | Duration (Weeks) | Assignee | Cost | Dependencies | Milestones |
|---|---|---|---|---|---|---|---|
| Requirements Gathering | 1 | 2 | 2 | Business Analyst | $10,000 | None | |
| Design | 3 | 4 | 2 | Architect | $15,000 | Requirements Gathering | |
| UI Development | 5 | 7 | 3 | UI Team | $25,000 | Design | |
| Backend Development | 5 | 7 | 3 | Backend Team | $30,000 | Design | |
| Database Setup | 5 | 6 | 2 | DB Admin | $10,000 | Design | |
| Integration | 8 | 8 | 1 | Dev Team | $10,000 | UI Development, Backend Development, Database Setup | |
| Testing | 8 | 9 | 2 | QA Team | $20,000 | Integration | Beta Release (end of week 8) |
| Bug Fixes | 9 | 9 | 1 | Dev Team | $5,000 | Testing | |
| Deployment | 9 | 9 | 1 | Ops Team | $5,000 | Bug Fixes | Project Complete |