Recent from talks
Nothing was collected or created yet.
Interstate Bridge
View on Wikipedia
Key Information
The Interstate Bridge (also Columbia River Interstate Bridge, I-5 Bridge, Portland-Vancouver Interstate Bridge, Vancouver-Portland Bridge) is a pair of nearly identical steel vertical-lift, Parker through-truss bridges that carry Interstate 5 traffic over the Columbia River between Vancouver, Washington and Portland, Oregon in the United States.
The present-day northbound bridge opened to traffic in 1917 as a single bridge carrying two-way traffic. A second twin bridge, which carries southbound traffic, opened in 1958.[2] The twin bridges are each over 3,500 feet (1,067 m) long and carry three lanes of traffic. The bridges handle a combined 130,000 vehicles daily.[2] It was added to the National Register of Historic Places in 1982, as the "Portland–Vancouver Highway Bridge".[4]
Since 2005, several proposals for replacing the bridge have been produced and debated. The bridge is considered responsible for traffic congestion of both road and river vehicles. Plans for a replacement bridge, known as the Columbia River Crossing (CRC) project, estimated to cost at least $3.4 billion, had come together by 2012 after many delays, but were very controversial, with both strong support and strong opposition.[8] In late June 2013, the CRC project was canceled, after the Washington state legislature declined to authorize funding for the project.[8] The Interstate Bridge Replacement Program, a joint effort between ODOT, WSDOT, Federal Highway Administration, Federal Transit Administration, Metro, Southwest Washington Regional Transportation Council, the cities of Portland and Vancouver, the Port of Portland, and the Port of Vancouver USA, was relaunched in 2017.
First bridge
[edit]

Before a permanent crossing existed between Portland and Vancouver, there was an overcrowded ferry system operated by Pacific Railway, Light & Power Co.
Plans for the original bridge began as early as 1912, with local efforts leading to an initial survey and bond measures totaling $2,000,000; $1.5 million contributed from Portland, and $500,000 from Vancouver. Waddell & Harrington were retained as the project's consulting engineers.[9] Construction on the bridge began in March 1915,[10] and the structure opened on February 14, 1917 at a final cost of $1.75 million (equivalent to $43 million in 2024[11]), which was shared between Clark and Multnomah counties.[12] Clark County paid $500,000 and Multnomah County paid $1.25 million—probably proportional to population.[13]
The first bridge has a total of 13 steel spans, with three measuring 275 feet (84 m) in length and the remaining ten spans 265 ft (81 m) each.[13] Piers sit atop pile caps on wooden pilings approximately 70 feet deep.[14] One of the 275-foot (84 m) spans is the lift span for allowing river traffic under the bridge.[13] The lift span is capable of moving 136 ft (41 m) vertically,[6] and provides 176 ft (53.6 m) of clearance below when fully raised.[2] The towers are 190 ft (57.9 m) tall, above the roadway.[6]
The original paved roadway was 38 ft (11.6 m) wide and had a 5 ft (1.52 m) wide sidewalk.[13] It was the first automobile bridge across the river between Washington and Oregon,[13] and the second to span the river at all, after the Wenatchee Bridge of 1908.[15] It was originally a toll bridge costing 5¢ per vehicle or per horse and rider,[6] equivalent to $1.23 in 2024. In 1928 the states of Washington and Oregon jointly purchased the bridge from the counties and discontinued tolling the following year.[2] The Oregon Department of Transportation became the lead agency responsible for the maintenance and operations of the structure.[16]
Electric streetcars operated across the bridge from opening day in 1917[3] until 1940. The bridge's deck carried dual gauge track,[6] to accommodate both Vancouver's standard gauge cars and Portland's 3 ft 6 in (1,067 mm) gauge cars. Before the bridge, Portland had had a Vancouver streetcar line since 1893, but it ran to Hayden Island, where passengers transferred to a ferry owned by the street railway company to continue across the river to Vancouver.[17] Streetcar service across the Interstate Bridge ended on September 3, 1940.[17]
The bridge became part of then-new Interstate 5 in 1957.[2] It was previously part of U.S. Route 99 when that route was established in 1926.[18]
Second bridge and renovations
[edit]
Plans to address congestion on the first Interstate Bridge, which carried over 30,000 vehicles per day by 1948, were drawn after World War II by highway officials in Oregon. The chief highway engineer, R. H. Baldock, proposed a second span over the Columbia River after it was determined that expanding the existing bridge was not feasible. Several sites were proposed and surveyed, but ultimately a twinned span west of the original bridge was chosen in September 1950 by Oregon and Washington. The proposed reinstatement of the toll led to a lawsuit that was heard by the Washington Supreme Court in September 1953 and decided in the states' favor.[19]
In 1958, a $14.5 million ($158 million in 2024 dollars) project created a second, almost identical span and doubled the capacity of the bridge. The new bridge was built with a "humpback" that provides 72 ft (21.9 m) of vertical clearance and minimizes bridge openings.[12] Construction began in summer 1956,[20][21] and the new, parallel bridge opened to traffic on July 1, 1958.[22]
At the time the new bridge was opened, the old one was temporarily closed for rebuilding to give it a matching humpback section. When both bridges were first open concurrently, on January 8, 1960,[23] each bridge became one-way (the new bridge for southbound traffic and the old one for northbound traffic) and tolls were reinstated at $0.20 for cars, $0.40 for light trucks, and $0.60 for heavy trucks and buses. The tolls were removed in 1966 after the construction expenses were paid off.[2][24]
A $3 million ($7.2 million in 2024 dollars) upgrade to the lift cables, expansion joints, and a deck repaving was completed in 1990. The diesel generator used to power the lift was replaced in 1995 at a cost of $150,000. In 1999, the bridge was repainted at a cost of $17 million. A $10.8 million electrical upgrade was completed in mid-May 2005.[25] The damaged trunnion on the northbound bridge was replaced in September 1997, requiring a full shutdown of I-5 for six days; the project was completed ahead of the original schedule, which anticipated a 21-day closure.[26] A temporary commuter train was operated by Amtrak from Union Station in Portland and Vancouver station during peak hours.[27] The free trains had ten round trips and drew an average of 1,335 passengers per day; the low ridership was attributed to the isolated location of Vancouver's station.[28][29] The northbound bridge's trunnion was replaced in 2020 with all traffic carried on the southbound bridge, arranged into two lanes in the peak direction controlled by a zipper machine.[30]
Vertical lift
[edit]The bridge is 3,538 feet (1,078 m) long with a main span of 531 feet (162 m).[31] The vertical lift provides 176 feet (53.6 m) of river clearance when fully opened. Openings last about ten minutes and occur between 20 and 30 times per month,[32] or around 300 per year.[33]


Outside peak commuting times (6:30 a.m. to 9 a.m. and from 2:30 p.m. to 6 p.m), marine traffic is granted right of way at the bridge by federal law (33 CFR 117.869).[34][35]
In 2006, the six total lanes of the bridges carried 130,000 vehicles daily.[2] Full traffic capacity occurs four hours every day.[32]
The Interstate Bridge's name is a simple descriptive one based on its location, as a bridge connecting two states.[2] In 1917, the new bridge gave its name to a Portland arterial street. Shortly before the bridge opened, a pair of streets through North Portland that were planned to be treated as the main route to and from the bridge, Maryland Avenue and Patton Avenue, were renamed Interstate Avenue.[36]
Replacement planning
[edit]Columbia River Crossing (2005–2013)
[edit]The bridge is frequently a bottleneck which impacts both traffic on the freeway, as well as on the river. The Oregon and Washington transportation departments are jointly studying how to replace the bridge. Both spans have been rated as "functionally obsolete," with sufficiency ratings of 18.3% and 49.4% for the original and second spans, respectively.[37][38] Initially, the estimated cost for a replacement bridge was around $2 billion,[39] but that number has climbed steadily to around $3.4 billion.[40] An independent study in 2010 estimated the full cost to be closer to $10 billion.[41]
Design of a replacement (especially a fixed-span bridge) is complicated by the existence of a railroad drawbridge crossing the Columbia a short distance downriver (on the Burlington Northern Railroad Bridge 9.6), which constrains the location of the shipping channel; and by approach paths to Portland International Airport in Portland and to Pearson Field in Vancouver, which limit the height of any new structure. Some have proposed replacing the bridge in a different location. There were originally 12 transportation plans that were being studied to improve and expand the Interstate 5 crossing of the Columbia River.[42] In late 2006, four of these plans were selected for a final proposal, along with a fifth no-build option.[43] The Columbia River Crossing project's six local partner agencies selected a replacement I-5 bridge and light rail extension to Clark College as the project's Locally Preferred Alternative (LPA) in 2008.[44]
There is also a longstanding debate as to whether or not a new bridge would include a MAX Light Rail line, express buses, or bus rapid transit. During his 2007 "State of the City" address, Vancouver mayor Royce Pollard stated
I've said it before, but it bears repeating – Vancouver and Clark County residents have the cheapest buy-in to one of the most successful light-rail systems in the world, the MAX system. There is over $5 billion invested in light rail across the river. We can tap into that system at a very minimal cost. We’d be foolish not to. The bi-state Columbia River Crossing initiative is making plans for the future of our community for 50 years and beyond. This project should not happen without integrating light rail that comes into downtown Vancouver. If the final alternative doesn’t have a light rail component, I will not support it.[45]
In December 2007, Oregon governor Ted Kulongoski advocated for a new bridge, publicly endorsing the Oregon Business Plan's proposal.[46]
In 2008, as fuel prices increased and project cost estimates soared, many in the area began questioning whether the project is worth the costs. In addition, many on the Portland side of the river fear that a 12-lane highway bridge to Vancouver, which many also believe has virtually no land use restrictions, will encourage suburban sprawl and development north of the river.[47]

Further concerns over the 12-lane "Columbia River Crossing" (CRC) proposal include its failure to examine critical environmental impacts, such as damage to Clark County's drinking water supply, endangered fish habitat in the Columbia, and air pollution in North Portland.
In 2008, the Environmental Protection Agency found that the Draft Environmental Impact Statement for the CRC had failed to adequately cover these issues, as well as the potential induced demand for suburban sprawl. In a letter to CRC planners, the EPA wrote that "There was no indication (in the CRC environmental impact statement) of how these vulnerable populations might be impacted by air pollution, noise, diesel construction vehicles and increased traffic", referring to minority communities in North Portland.[48]
In June 2013, the Washington Legislature voted against further funding of the CRC.[8] On June 29, Oregon Governor Kitzhaber directed the CRC to shut down operations.
Interstate Bridge Replacement Program (2019–present)
[edit]The relaunched Interstate Bridge Replacement Program is a joint effort between ODOT, WSDOT, Federal Highway Administration, Federal Transit Administration, Metro, Southwest Washington Regional Transportation Council, the cities of Portland and Vancouver, the Port of Portland, and the Port of Vancouver USA.[49]
The Joint Oregon-Washington Legislative Action Committee was formed by the Washington legislature in 2017 to study a bridge replacement, but initially had no Oregon representation for a year.[50][51] The new committee was formed to prevent $140 million in federal funding allocated for the CRC from being recalled after a deadline, which was extended to 2025.[52] In April 2019, the Washington legislature approved $17.5 million to establish a project office to conduct pre-design and planning work, which was followed by a matching contribution from the Oregon Transportation Commission in August.[53][54]
A new timeline for the project, with the start of environmental review in 2020 and construction by 2025, was approved by the joint committee in late 2019.[55] The replacement bridge's design is unspecified, with discussions about the inclusion of light rail, lane configurations, and investigating a third crossing all under consideration.[53] Former Michigan Department of Transportation deputy director Greg Johnson was appointed as the bridge program administrator in June 2020.[56][57] Several alternative ideas have been proposed, including an immersed tube tunnel, a third bridge, and a bascule bridge favored by the U.S. Coast Guard, but have been rejected for their drawbacks and cost.[58]
As of December 2022[update], the project is estimated to cost $5.5 billion to $7.5 billion.[59] The locally preferred alternative selected in 2022 is an eight-lane bridge with a light rail guideway on the west side and several modified interchanges.[60] The U.S. Coast Guard requested an alternative design with a drawbridge to preserve the clearance for river traffic, which would be lowered by 60 feet (18 m) if the locally preferred alternative was built.[61] Construction is scheduled to begin in late 2025 or early 2026. Tolls will be implemented on the Oregon side of the existing bridge to help fund the new bridge as it is being built.[62]
See also
[edit]References
[edit]- ^ "ASR Registration 1248957". Archived from the original on September 1, 2023. Retrieved September 1, 2023.
- ^ a b c d e f g h i j k Wood Wortman, Sharon; Wortman, Ed (2006). The Portland Bridge Book (3rd ed.). Urban Adventure Press. pp. 107–112. ISBN 0-9787365-1-6.
- ^ a b "Columbia Span Is Formally Opened: Dream of Half Century Is Realized (subheadlines: Traffic Starts With Brilliant Ceremony on Bridge; Thousands Attend Affair)" Archived June 8, 2023, at the Wayback Machine. (February 15, 1917). The Morning Oregonian, p. 1.
- ^ a b c "Oregon National Register List" (PDF). Oregon Parks and Recreation Department. June 6, 2011. p. 39. Archived from the original (PDF) on June 9, 2011. Retrieved July 13, 2011.
- ^ "National Register Information System". National Register of Historic Places. National Park Service. April 15, 2008.
- ^ a b c d e Bottenberg, Ray (2007). Bridges of Portland. Arcadia Publishing. pp. 78, 80. ISBN 978-0-7385-4876-0.
- ^ "Columbia River Bridges: Crossing Data, 1961 - 2014". Archived from the original on February 7, 2019. Retrieved June 25, 2015.
- ^ a b c Read, Richard (July 1, 2013) [online date June 30]. "Cheers, dismay over CRC's demise". The Oregonian. p. 1. Archived from the original on July 4, 2013. Retrieved July 7, 2013.
- ^ "The $1,750,000 Interstate Highway Bridge, Oregon and Washington". Engineering & Contracting. XLII (7). Chicago: Myron C. Clark Publishing Co.: 36 August 12, 1914. Retrieved June 6, 2021 – via Google Books.
- ^ Holstine, Craig E. (2005). Spanning Washington: Historic Highway Bridges of the Evergreen State. Washington State University Press. pp. 103–104. ISBN 0-87422-281-8.
- ^ 1634–1699: McCusker, J. J. (1997). How Much Is That in Real Money? A Historical Price Index for Use as a Deflator of Money Values in the Economy of the United States: Addenda et Corrigenda (PDF). American Antiquarian Society. 1700–1799: McCusker, J. J. (1992). How Much Is That in Real Money? A Historical Price Index for Use as a Deflator of Money Values in the Economy of the United States (PDF). American Antiquarian Society. 1800–present: Federal Reserve Bank of Minneapolis. "Consumer Price Index (estimate) 1800–". Retrieved February 29, 2024.
- ^ a b Wood, Sharon (2001). The Portland Bridge Book (2nd ed.). Oregon Historical Society. pp. 73–78. ISBN 0-87595-211-9.
- ^ a b c d e Horner, John B. (1919). "Oregon: Her History, Her Great Men, Her Literature". The J.K. Gill Co.: Portland.
- ^ "Seismic Vulnerability". Project Information. Columbia River Crossing. Archived from the original on January 29, 2013. Retrieved March 19, 2013.
- ^ Dorpat, Paul; Genevieve McCoy (1998). Building Washington: A History of Washington State Public Works. Tartu Publications. pp. 111–112. ISBN 0-9614357-9-8.
- ^ "Asset Management: Bridge Assessment Annual Report" (PDF). The Gray Notebook (34). Washington State Department of Transportation: 19. August 20, 2009. Archived (PDF) from the original on December 26, 2023. Retrieved December 26, 2023.
- ^ a b Thompson, Richard (2010). Portland's Streetcar Lines, pp. 72–73, 77. Arcadia Publishing. ISBN 978-0-7385-8126-2.
- ^ Pesanti, Dameon (February 12, 2017). "Interstate Bridge turns 100: 'With Iron Bands,' a century spanned". The Columbian. Archived from the original on May 7, 2021. Retrieved May 7, 2021.
- ^ Seekamp, William (February 19, 2023). "Interstate Bridge: Second span revives tolls". The Columbian. Archived from the original on June 12, 2024. Retrieved June 26, 2024.
- ^ "Construction of New Interstate Bridge Near Start". The Oregonian. July 17, 1956. p. 1.
- ^ "Piers Poured Under Water; Contractors to Try New Method in Construction of Interstate Bridge". The Sunday Oregonian. September 2, 1956. p. 16.
- ^ Hauser, Paul (July 2, 1958). "Rites Open 2d Bridge Over River". The Oregonian. p. 1.
- ^ "Twin Interstate Spans Open to Travel Friday". The Oregonian. January 8, 1960. p. 1.
- ^ Rivera, Dylan (August 9, 2008). "I-5 bridge tolls divide Portland, Vancouver". The Oregonian. Archived from the original on June 9, 2011. Retrieved July 13, 2011.
- ^ "Interstate Bridges Electrical Upgrade". Oregon Department of Transportation. Retrieved July 13, 2011.
- ^ "It's full speed ahead for I-5 bridge traffic". The Oregonian. September 22, 1997. pp. A1, A11.
- ^ Mize, Jeffery (November 30, 2019). "Clark Asks: Why can't Amtrak be used to commute to Portland from Vancouver?". The Columbian. Archived from the original on January 15, 2024. Retrieved January 14, 2024.
- ^ Hamilton, Don (September 17, 1997). "Amtrak commutes take on cruise aura". The Oregonian. p. A12. Retrieved January 24, 2025 – via Newspapers.com.
- ^ Oliver, Gordon (September 23, 1997). "Closure of I-5 bridge demonstrates transit's value". The Oregonian. p. A1.
- ^ Heffernan, Jack (September 19, 2020). "Day 1 of I-5 Bridge trunnion replacement project mostly on track". The Columbian. Archived from the original on January 15, 2024. Retrieved January 14, 2024.
- ^ Smith, Dwight A.; Norman, James B.; Dykman, Pieter T. (1989). Historic Highway Bridges of Oregon. Oregon Historical Society Press. p. 209. ISBN 0-87595-205-4.
- ^ a b I-5 Partnership. Regional Economic Effects of the I-5 Corridor: Columbia River Crossing Transportation Choke Points (PDF) (Report). Archived from the original (PDF) on March 17, 2009. Retrieved March 4, 2009.
{{cite report}}: CS1 maint: numeric names: authors list (link) - ^ Wong, Peter (August 25, 2023). "Interstate Bridge shows its age". Portland Tribune. Retrieved August 31, 2023.[dead link]
- ^ Albrecht, Bob (June 2, 2011). "High river levels prompt bridge lifts". The Columbian. Archived from the original on February 10, 2016. Retrieved January 24, 2013.
- ^ "Drawbridge Operation Regulation; Columbia River, Vancouver, WA". Federal Register. Archived from the original on September 30, 2015. Retrieved January 24, 2013.
- ^ "Street Name Changed: Maryland and Patton Avenue become Interstate Avenue". The Morning Oregonian. December 7, 1916. p. 13. Archived from the original on September 14, 2016. Retrieved July 17, 2016.
- ^ "NBI Structure Number: 000000PR0000000". National Bridge Inventory Database. 2012. Archived from the original on February 10, 2016. Retrieved May 23, 2013.
- ^ "NBI Structure Number: 0005216A0000000". National Bridge Inventory Database. 2012. Archived from the original on February 10, 2016. Retrieved May 23, 2013.
- ^ Mayer, James (November 22, 2006). "Columbia bridge advice: Scrap the old, build new". The Oregonian.
- ^ Rivera, Dylan (May 28, 2008). "Charge tolls first, then maybe build a bridge, Metro councilors say". The Oregonian. Archived from the original on June 9, 2011. Retrieved May 29, 2008.
- ^ Rose, Joseph (October 15, 2010). "New study warns Columbia River Crossing could cost $10 billion". The Oregonian. Archived from the original on January 12, 2013. Retrieved January 24, 2013.
- ^ "Preliminary Alternative Packages". Columbia River Crossing. Archived from the original on November 14, 2006. Retrieved November 5, 2006.
- ^ "State of Oregon: Oregon Department of Transportation". Archived from the original on August 21, 2008. Retrieved July 24, 2008.
- ^ "State of Oregon: Oregon Department of Transportation". Archived from the original on August 21, 2008. Retrieved July 24, 2008.
- ^ "State of the City". City of Vancouver. January 23, 2007. Archived from the original on October 15, 2006. Retrieved January 25, 2007.
- ^ McCall, William (December 4, 2007). "Ore.: Governor urges new bridge". Houston Chronicle. Associated Press.
- ^ "Bridge to Disaster". The Portland Mercury. March 19, 2008. Archived from the original on May 17, 2008. Retrieved May 29, 2008.
- ^ Reed, Len (July 10, 2008). "I-5 bridge impacts on pollution, growth unexamined". The Oregonian. Archived from the original on May 19, 2012. Retrieved July 13, 2011.
- ^ "I-5 - Interstate Bridge Replacement Program". Washington State Department of Transportation. Retrieved October 14, 2022.
- ^ Thomas, Jake (December 15, 2017). "Panel aims to span I-5 dilemma". The Columbian. p. A1. Archived from the original on July 21, 2020. Retrieved July 20, 2020.
- ^ Thomas, Jake (December 7, 2018). "Oregon to join in Interstate 5 Bridge replacement talks". The Columbian. Archived from the original on July 21, 2020. Retrieved July 20, 2020.
- ^ Mize, Jeffery (September 24, 2019). "Washington, Oregon get another 5 years on I-5 Bridge funds". The Columbian. Archived from the original on July 21, 2020. Retrieved July 20, 2020.
- ^ a b Mize, Jeffrey (October 13, 2019). "New I-5 Bridge project: Here we go, again...again". The Columbian. p. A1. Retrieved July 20, 2020.
- ^ Theen, Andrew (August 16, 2019). "Oregon will spend $9 million on new Interstate Bridge project". The Oregonian. Archived from the original on July 12, 2020. Retrieved July 20, 2020.
- ^ Theen, Andrew (September 24, 2019). "Oregon and Washington: We'll start building a new Interstate Bridge by 2025". The Oregonian. Archived from the original on July 9, 2020. Retrieved July 20, 2020.
- ^ "ODOT and WSDOT name key leader to head the Interstate Bridge Replacement Program" (Press release). Washington State Department of Transportation. June 11, 2020. Retrieved July 20, 2020.
- ^ Monahan, Rachel; Mesh, Aaron (June 29, 2022). "U.S. Coast Guard Says Planned Bridge Across Columbia River Is 60 Feet Too Low". Willamette Week. Archived from the original on June 30, 2022. Retrieved June 30, 2022.
- ^ Seekamp, William (September 18, 2022). "Why alternative Interstate 5 Bridge replacement ideas won't work". The Columbian. Archived from the original on September 25, 2022. Retrieved September 25, 2022.
- ^ Seekamp, William (December 9, 2022). "New I-5 Bridge cost: Likely $6 Billion". The Columbian. Archived from the original on December 10, 2022. Retrieved December 10, 2022.
- ^ Garcia, Isabella (May 5, 2022). "Interstate Bridge Engineers Propose Eight Lane Design with Light Rail". Portland Mercury. Archived from the original on December 10, 2022. Retrieved December 10, 2022.
- ^ Macuk, Anthony (April 26, 2023). "Interstate Bridge replacement costs and project scale come into focus as Oregon considers how to fund it". KGW. Archived from the original on June 29, 2023. Retrieved January 29, 2024.
- ^ Macuk, Anthony (October 20, 2023). "Interstate Bridge tolling timeline takes shape with planned 2026 start". KGW. Archived from the original on January 8, 2025. Retrieved January 29, 2024.
External links
[edit]- Historic American Engineering Record (HAER) No. WA-86, "Vancouver–Portland Interstate Bridge, Interstate Route 5 Spanning Columbia River, Vancouver, Clark County, WA", 7 photos, 30 data pages, 1 photo caption page
- WSDOT:Interstate Bridge Archived March 13, 2018, at the Wayback Machine
- Interstate Bridge Replacement program: Home page of ODOT/WSDOT project to replace the Interstate Bridge
Interstate Bridge
View on GrokipediaHistory
Original Construction and Opening (1917–1918)
The Interstate Bridge, spanning the Columbia River between Portland, Oregon, and Vancouver, Washington, was conceived to replace ferry crossings that had long constrained regional connectivity. Jointly funded by Multnomah County ($1,250,000 in bonds) and Clark County ($500,000 in bonds), construction addressed the growing demand for reliable vehicular and streetcar access amid early 20th-century economic expansion. Preliminary surveys began on April 28, 1912, under engineer Ralph Modjeski, with the final design contracted to the firm Waddell & Harrington on January 6, 1914.[10][5] Groundbreaking occurred on March 6, 1915, with the substructure built by Pacific Bridge Company using reinforced concrete and timber piles, while United States Steel Products Company fabricated the steel superstructure of riveted truss spans, erected by Porter Brothers. The bridge comprises 14 main truss spans across the river—ten at 265 feet and three at 275 feet—plus approach structures, totaling approximately 3,538 feet in length, with a vertical-lift span providing 150 feet of vertical clearance when raised. The 38-foot-wide roadway accommodated two vehicle lanes, dual streetcar tracks, and a five-foot sidewalk, reflecting its dual role in highway and rail transport. Construction concluded under the $1.75 million budget, finishing with a $56,000 surplus after less than two years of work.[3][5][3] Pedestrians first crossed on December 30, 1916, followed by the official vehicular and ceremonial opening on February 14, 1917, drawing crowds estimated at up to 50,000—the largest in Vancouver's history at the time—and featuring addresses by Oregon Governor James Withycombe, Washington Governor Ernest Lister, and other dignitaries. Electric streetcars began service immediately, operating until 1940, underscoring the bridge's integration into regional transit networks. This engineering feat, leveraging steel trusses with curved top chords for aesthetic and structural efficiency, marked a pivotal infrastructure milestone, enabling seamless interstate commerce and mobility without the delays of prior ferry reliance.[3][11][3]Second Span Addition (1958)
By the mid-1940s, the original 1917 Interstate Bridge was overwhelmed by surging automotive traffic exceeding 30,000 vehicles daily and frequent vertical lift operations to accommodate river vessels, leading to significant delays and capacity constraints.[12][13] In 1950, Oregon highway engineer R. H. Baldock formally proposed a parallel second span west of the original, with surveying commencing that May and design finalized by 1952 at an estimated cost of $11.2 million.[13] Oregon and Washington legislatures authorized the project in 1953 through bond sales for funding, following resolution of legal challenges.[12][13] Construction contract was awarded in 1956 to the Guy F. Atkinson Company, with work beginning that summer and completing on June 30, 1958, at a final cost of $14.5 million (equivalent to approximately $140 million in 2020 dollars), including expenses for the new spans and an Oregon Slough bridge.[12] The second span featured a design nearly identical to the 1917 structure—a metal vertical lift bridge with an 11-panel rivet-connected Parker through truss and a 278.7-foot lift span—but included refinements such as a 40-foot-wide roadway (2 feet wider than the original), a total length of 3,538 feet across 16 sections (versus 14), riveted Warren truss floorbeams, and a raised "hump" section south of the lift span providing 72 feet of vertical clearance to minimize future liftings for smaller vessels.[12][14] Two workers died during construction amid these efforts to double the crossing's vehicular capacity to 75,000–80,000 vehicles per day.[13] The second span opened to southbound traffic on July 1, 1958, marked by a ribbon-cutting ceremony attended by dignitaries including descendants of early bridge supporters, though drawing a smaller crowd than the 1917 opening.[12] Immediately following, the original span closed for an 18-month renovation costing about $3 million to install a matching hump for improved clearance, reopening on January 8, 1960, as the dedicated northbound structure and establishing a one-way pair configuration.[12] Tolls, absent since 1929, were reinstated on January 10, 1960 (20 cents for cars, up to 60 cents for heavy vehicles), to service bonds and offset costs but discontinued on November 1, 1966, after payoff.[12][13]Post-1958 Renovations and Modifications
Following the opening of the second span in 1958, the original 1917 northbound span underwent remodeling to align with the new structure, including raising the lift span to match the adjacent bridge's height, with work commencing on July 1, 1958, and contract awarded for $2,993,995.[5] This modification enabled the spans to operate in tandem while accommodating increased interstate traffic volumes under the newly designated I-5 corridor.[5] In 1979, deck and expansion joint reconstruction addressed wear from decades of heavy use, replacing standard asphalt concrete surfacing with rubberized asphalt concrete to improve durability and ride quality, completed in November at a cost of $946,600.[5] This upgrade targeted deterioration in the roadway surfaces but did not alter the structural truss or lift mechanisms.[5] The 1990 replacement of lift-span cables and a sheave in the engine room, costing $385,708 and completed that year, ensured continued reliable operation of the vertical lift system on the original span, preventing potential failures in the hoisting apparatus amid rising maintenance demands.[5] Subsequently, in 1991, comprehensive deck restoration and expansion joint repairs were performed across both spans, completed by March at $2,432,385, focusing on resurfacing and sealing to mitigate corrosion and fatigue without substantive seismic or load-capacity enhancements.[5] These interventions represent routine preservation efforts rather than transformative overhauls, with no documented major seismic retrofitting or capacity expansions undertaken, leaving the bridges vulnerable to Cascadia Subduction Zone events as noted in subsequent engineering assessments.[15] Ongoing maintenance has prioritized operational continuity over fundamental redesign, amid escalating traffic exceeding original design loads by factors of 5-10 times.[16]Design and Technical Specifications
Structural Composition and Materials
The Interstate Bridge comprises two parallel vertical-lift bridges, each characterized by a central Pratt through-truss lift span and flanking Parker through-truss approach spans, all fabricated from riveted steel. The original span, completed in 1917, utilized steel superstructure elements produced by the United States Steel Products Company, while the 1958 addition's steelwork was fabricated and erected by the Guy F. Atkinson Company.[5][14] Substructure components incorporate reinforced concrete, including a 5¼-inch-thick concrete slab for the roadway deck on the 1917 bridge and T-beam spans for approaches. Piers on the original span are dumbbell-type reinforced concrete, founded on timber piles driven into open timber caissons and sealed with concrete. The 1958 span features piers assembled from hollow precast concrete segments, filled with tremie concrete and supported on timber pilings, eliminating the need for cofferdams used in the initial construction.[5][1] These materials reflect early 20th-century engineering practices for long-span movable bridges, prioritizing steel's tensile strength for the truss framework and concrete's compressive durability for foundations amid the Columbia River's challenging geotechnical conditions.[5]
Vertical Lift System and Operational Mechanics
The Interstate Bridge features two parallel vertical-lift truss bridges spanning the Columbia River, each with a 279-foot Pratt truss lift span designed to rise vertically while remaining parallel to the roadway.[5] The system employs a Waddell & Harrington-type mechanism, utilizing counterweights, steel wire ropes, cast steel sheaves, and operating drums to facilitate the lift.[5] Reinforced concrete counterweights, positioned at each end of the lift span, balance the approximately 1,800-ton span, connected via cables that run over sheaves mounted on trunnions within the lift towers.[5] [17] Operation begins with bridge tenders in the main control room on Pier 2 signaling vessel passage requests, coordinated with the U.S. Coast Guard.[5] Electric motors drive the operating ropes wound around drums, raising the span along guide rails at a controlled speed, achieving up to 176 feet of vertical clearance above mean high water to accommodate marine traffic.[18] [19] The counterweights offset most of the span's dead load, minimizing motor power requirements, while separate uphaul and downhaul rope systems ensure precise control and friction-based force transmission via sheaves.[20] Modern monitoring systems enhance operational safety, with dataloggers, tiltmeters, and laser sensors tracking span tilt, displacement, torque, and counterweight position in real-time during lifts.[19] Data is collected at 5-second intervals during operations and transmitted wirelessly to Oregon Department of Transportation servers for analysis, allowing adjustments to maintain balance and detect misalignments early.[19] The spans open an average of 250 times annually, varying with river traffic and levels, up to 480 in peak years.[21] Maintenance includes periodic replacement of worn ropes, drums, and bearings to preserve alignment and functionality.[5]Clearance, Navigation, and Load Capacities
The Interstate Bridge features a vertical lift span that provides 178 feet (54.3 m) of clearance above Columbia River Datum (CRD) when raised, enabling passage of large vessels and barges on the Columbia River navigation channel.[22] When lowered, the clearance under the lift span measures 39 feet (11.9 m) above 0.0 CRD in the primary channel.[23] The horizontal clearance under the 542-foot (165 m) lift span is 263 feet (80 m), accommodating standard river traffic widths.[23] Navigation through the bridge is regulated by the U.S. Coast Guard under 33 CFR 117.1041, requiring the lift span to open on signal except during weekday rush hours from 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m., when openings are limited to vessels needing 140 feet (42.7 m) or greater clearance.[24] Outside these periods, at least four hours' advance notice is required for openings. The system uses counterweights and electric motors to raise the span approximately 140 feet in about 4 minutes, minimizing disruptions to highway traffic while prioritizing commercial navigation needs on this federal waterway.[25] Load capacities adhere to federal Interstate Highway standards, permitting a maximum gross vehicle weight of 80,000 pounds (36,287 kg), with single-axle limits of 20,000 pounds (9,072 kg) and tandem-axle limits of 34,000 pounds (15,422 kg), calculated via the Federal Bridge Formula to distribute loads and prevent structural overload.[26] No unique postings or reductions specific to the bridge's age or design were identified beyond these norms, reflecting periodic inspections and reinforcements maintaining sufficiency for HS-20 loading ratings typical of interstate spans.[27]Operational Performance
Daily Traffic Volumes and Patterns
The Interstate Bridge accommodates an average weekday traffic volume of approximately 130,000 vehicles, with 2023 data recording 133,737 vehicles per weekday.[28] This represents a recovery from the 2020 pandemic low of 120,361 vehicles per weekday, though volumes remain about 5% below the 2019 peak of 138,700 vehicles per day.[28][29] Historical growth has been substantial, rising from 33,537 vehicles per day in 1961 to over 130,000 by the 2020s, driven by regional population and economic expansion.[30] Traffic patterns exhibit a strong commuter orientation, with directional imbalances during peak periods: southbound flows dominate mornings from 6 to 9 a.m., corresponding to travel from Vancouver, Washington, suburbs to Portland, Oregon, employment centers, while northbound volumes peak in the afternoon and evening.[31] Weekday volumes exceed weekends by roughly 20-30%, with hourly data showing maximum throughput during rush hours but constrained by the bridge's capacity, leading to recurring bottlenecks.[32] Trucks constitute about 8% of weekday traffic, primarily during off-peak times to avoid congestion.[33] Overall, volumes reflect induced demand from limited crossings, with minimal long-term growth post-2019 despite regional development.[34]Congestion Metrics and Bottlenecks
The Interstate Bridge experiences recurrent congestion primarily during peak travel periods, with southbound queues forming in the morning and northbound in the afternoon and evening. In the 2019 baseline year, southbound congestion on the bridge spans approximately 3 hours from 6 to 9 a.m., extending about 3 miles, while northbound congestion persists for 8.75 hours from 11:15 a.m. to 8 p.m., backing up over 10 miles.[35] These patterns reflect the bridge's limited capacity of roughly 5,000 vehicles per hour in the peak direction, which is frequently exceeded during high-demand hours.[36] Level of service (LOS) on the bridge deteriorates to E or F—indicating unstable flow and forced operation at reduced speeds—during peaks. Southbound AM peak segments achieve LOS E with volume-to-capacity (V/C) ratios of 0.90–1.0 from 6–7 a.m., dropping to LOS F with V/C exceeding 1.1 by 8 a.m. Northbound PM peak conditions reach LOS F with V/C ratios of 1.0–1.1 from 3–5 p.m., following earlier LOS B–C in the morning off-peak.[35] Average travel delays during these periods range from 24–38 minutes southbound in the AM peak (6–9 a.m.) and 31–40 minutes northbound in the PM peak (3–7 p.m.).[35]| Direction and Peak Period | Congestion Duration | Approximate Queue Length | Typical Delay |
|---|---|---|---|
| Southbound AM (6–9 a.m.) | 3 hours | 3 miles | 24–38 minutes[35] |
| Northbound PM/Evening (11:15 a.m.–8 p.m.) | 8.75 hours | 10+ miles | 31–40 minutes[35] |
Accident Statistics and Safety Data
The Interstate Bridge and its immediate approaches register crash rates significantly above averages for comparable urban interstate facilities, primarily attributable to chronic congestion inducing abrupt braking and rear-end collisions. Between 2002 and 2006, the bridge structure itself (spanning approximately 0.67 miles) experienced an average of 108 crashes annually, based on data from the Oregon Department of Transportation (ODOT) and Washington State Department of Transportation (WSDOT).[40] In the broader 5-mile project corridor encompassing the bridge and key approach segments, annual crashes averaged around 409 during the same period, with rear-end impacts comprising 66% of incidents and sideswipe collisions 14%, patterns exacerbated by bottlenecks and merging traffic.[40][41] Crash density in the vicinity remains elevated, with approaches to the bridge exhibiting rates over three times higher than statewide norms for similar roadways, particularly during peak hours when volume-to-capacity ratios exceed 1.0.[42] A 2011 analysis of the Columbia River Crossing area reported a collision rate of 1.58 per million vehicle miles traveled (MVMT), compared to an urban interstate benchmark of 0.55 per MVMT, underscoring the safety premium from substandard geometry, narrow lanes, and lift-span operations that periodically halt traffic.[43] From 2015 to 2019, the program study area recorded 7 fatal crashes and 33 serious injury crashes, reflecting persistent vulnerabilities tied to high daily volumes exceeding 140,000 vehicles.[42]| Metric | Value | Period/Source |
|---|---|---|
| Crashes on bridge structure | ~108/year | 2002–2006 (ODOT/WSDOT)[40] |
| Crashes in 5-mile corridor | ~409/year | 2002–2006 (ODOT/WSDOT)[40] |
| Collision rate (corridor) | 1.58/MVMT | Pre-2011 (WSDOT)[43] |
| Fatal crashes (study area) | 7 | 2015–2019[42] |
| Serious injury crashes (study area) | 33 | 2015–2019[42] |