Hubbry Logo
search
logo
888061

Polavaram Project

logo
Community Hub0 Subscribers
Read side by side
from Wikipedia

The Polavaram Project is an under-construction multi-purpose irrigation project on the Godavari River in the Eluru District and East Godavari District in Andhra Pradesh, India. The project has been accorded National Project status by the Central Government of India.[3][4][5] Its reservoir back water spreads up to the Dummugudem Anicut, i.e. approx 150 kilometres (93 mi) back from Polavaram dam on main river side and approx 115 kilometres (71 mi) on the Sabari River side. Thus, back water spreads into parts of Chhattisgarh and Odisha States.[6][7][8] Polavaram Hydroelectric Project (HEP) and National Waterway 4 are under construction[needs update][until when?] on left side of the river. It is located 40 kilometres (25 mi) upstream of Sir Arthur Cotton Barrage in Rajamahendravaram City and 25 kilometres (16 mi) from Rajahmundry Airport.

Key Information

History

[edit]

In July 1941, the first conceptual proposal for the project was mooted by the Madras Presidency. Diwan Bahadur L. Venkatakrishna Iyer, then Chief Engineer in the Presidency's irrigation department, made the first survey of the project site and made a definitive proposal for a reservoir at Polavaram. Sri Iyer not only envisaged cultivation of 350,000 acres (140,000 ha) over two crop seasons through this project, but also planned for a 40 MW hydroelectric plant within the project.[9] The project, when it was conceived in 1946–47, was estimated to cost Rs 129 crore.

In 1980, Chief Minister of Andhra Pradesh Tanguturi Anjaiah laid the foundation stone for the Polavaram irrigation project. In the year 2004, Y. S. Rajasekhara Reddy performed bhoomi pooja with the estimation cost of 8,261 cr, and the administrative sanction was accorded for construction of right and left canals at a cost of Rs 1,320 crore and Rs 1,353 crore.

Y. S. Rajasekhara Reddy Congress government completed 33% of project before 2014.[10] The Polavaram Project Authority was constituted by the Union Cabinet in May 2014 and the construction of project head works were taken up.[11] The Naidu government acquired the necessary lands for the right canal by solving court petition issues of farmers who lost their agricultural lands from both districts of West Godavari and Krishna; the Pattiseema Lift Irrigation Project has been launched in order to pump the Godavari river water and sent it to the Krishna river.[12][13] In June, the state was bifurcated under the Andhra Pradesh Reorganisation Act. In December 2017, it was reported that the project contractor, Transstroy, was seeking a deadline extension and a budget escalation.[14] Transstroy was reported to have its ₹4,300 crore loan turn NPA in July 2015.[15] In January 2018, the state government signed a new contract for the project spillway, spill channel, and stilling basin concrete work with Navayuga Engineering.[16] By June 2018, 110,355 acres (44,659 ha) of the required 168,213 acres (68,073 ha) had been acquired.[17] On June 11, 2018, the Polavaram diaphragm wall was completed, marking a significant milestone in the project construction.[18] On January 7, 2019, the Polavaram project entered the Guinness Book of World Records by pouring 32,100 cubic meters of concrete in 24 hours by Navayuga Engineering. The project beat the existing record of 21,580 cubic meters, which was achieved by Abdul Wahid Bin Shabib, RALS Contracting LLC and Alfa Eng. Consultant (all UAE), in Dubai between May 18 and 20 in 2017.[19] The Chief minister of Andhra Pradesh N. Chandrababu Naidu unveiled the first crest gate on 24 December 2018.[20]

Union Minister of Water Resources Nitin Gadkari, along with Andhra Pradesh Chief Minister N. Chandrababu Naidu, Irrigation Minister Devineni Uma Maheswara Rao, and other officials, addressing the media at the Polavaram project site in 2018.

Progress

[edit]
Milestone Start Date Completion Date
Spill way concreting work 30 December 2016[21] mostly completed as of May 2021
Diaphragm wall of earth and rock fill (ECRF) dam 1 February 2017[22] 11 June 2018[23]
Jet grouting January 8, 2018[24] October 29, 2018[25]
Upper coffer dam grouting June 8, 2017[26] Jan 8, 2018[27]
Lower coffer dam grouting June 8, 2017[26] Under construction
Spill channel concreting work Apr 23, 2018[28] Under construction
Right bank canal head works Under construction
Left bank canal head works Under construction
Navigation tunnel Under construction
Right bank canal works 2016 (90% completed)
Left bank canal works Under construction
Hydroelectric power plant Under construction
Blocking the natural course of the Godavari by raising the upper coffer dam level above the crest level (17.3 m MSL) of river sluice vertical gates (10 nos) provided in the spillway to divert the Godavari water through these gates.[29] 27 May 2021
Godavari water flows diverted fully through the river sluice gates of the spillway via the approach channel[30] 11 June 2021[31]
Upper coffer dam works completed. 31 January 2022
All the 48 barrage gates are fully erected and water can be stored in the reservoir to the extent permitted by the upper coffer dam design. 30 June 2022
Lower coffer dam works completed 17 February 2023[32]
Completion of inspection and field investigation of damaged diaphragm wall during the 2020 Godavari floods and the decision was given to rectify the damage that took place. 5 March 2023[33]
Repair works of damaged diaphragm wall 8 March 2023
ECRF dam yet to start

Purpose

[edit]

The National River-Linking Project, which works under the aegis of the Indian Ministry of Water Resources, was designed to overcome the deficit in water in the country.[34] As a part of this plan, surplus water from the Himalayan rivers is to be transferred to the peninsular rivers of India.[35] This exercise, with a combined network of 30 river-links and a total length of 14,900 kilometres (9,300 mi) at an estimated cost of US$120 billion (in 1999), would be the largest infrastructure project in the world.[36] In this project's case, the Godavari River basin[37] is considered as a surplus one, while the Krishna River basin is considered to be a deficit one.[38] As of 2008, 644 tmcft of underused water from Godavari River flowed into the Bay of Bengal.[39] But as of 2017, over 3000 tmcft are drained unused into the Bay of Bengal.[40] Based on the estimated water requirements in 2025, the Study recommended that sizable surplus water was to be transferred from the Godavari River basin to the Krishna River basin.[38]

Polavaram project Canal view near Talupulamma Lova
Polavaram project Canal view near Talupulamma Lova

The live storage available above 140 ft msl moderates substantially the flood wave of probable maximum flood (PMF) to reduce the effect of PMF downstream of Polavaram dam.[41] The capacity of the right and left canals are 17,500 cusecs each. During the monsoon months (July to October), nearly 360 tmcft of Godavari flood flows at the rate of 3 tmcft per day can be diverted into the canals.[42] At least another 190 tmcft water from the water stored in the Polavaram reservoir along with lean season inflows, excluding the downstream Godavari Delta water requirements, can be diverted into these canals. Thus the total annual water use capacity of the Polavaram project is 550 tmcft.[43] The water storage available in Sileru river basin is used as usual for the full water requirements of the Godavari Delta when natural inflows in the river falls short of its requirements and minimum environmental flows.

The hydropower plant (960 MW) will generate 2.29 billion kWh of renewable electricity annually.[2] Polavaram Reservoir will also create the potential to install nearly 158,000 MW of pumped-storage hydroelectric plants in the future.

Alternate site

[edit]

The dam could not be taken up for construction during the last century on techno-economical grounds. The proposed dam site at Polavaram is located where the river emerges from the last range of the Eastern Ghats into plains covered with deep alluvial sandy strata.[44] At Polavaram, the river width is about 1,500 metres (4,900 ft). Due to the depth (more than 30 m) of the bedrock at this dam site, the dam project was not found economical to take up. However, a lucrative alternate site is located upstream of the Polavaram site where the river passes through deep gorges of Papi hill range.[45] The width of river is about 300 metres (980 ft) in the rocky gorge stretch. Thirty years back,[when?] this alternative was found to be technologically challenging due to the need to connect the reservoir with the irrigation canals via tunnels across the ghat area. Also, it would need a costly underground hydroelectric station, compared to the riverbed-based hydroelectric station. When the project was actually taken up in the year 2004, the old finalised designs at Polavaram site were adopted without re-examining the latest cost of the upstream alternate site in view of state-of-the-art construction technology of tunnels and underground hydroelectric stations. The progress up to the year 2012 in construction of dam structures and the hydroelectric station is almost nil.[46] The alternate site located in the gorge stretch still merits re-examination to reduce the ever-increasing cost of Polavaram dam.[citation needed]

The spillway and non-overflow dam are founded on Khondalite bedrock in the Polavaram Project.[45] Khondalites, which are feldspar-rich, often contain soft graphite, hard garnet, etc. in addition to other minerals. Khondalites are highly weathered and hence unsuitable at dam sites.[47]

Technical details

[edit]
Aqueduct across Tammileru near Eluru

The project reservoir has a live storage of 75.2 tmcft above the canal's full supply level of 41.15 metres (135 ft) MSL and a gross storage of 194 tmcft, thereby enabling irrigation of 2,320,000 acres (940,000 ha) (including stabilisation of existing irrigated lands) in Krishna, West Godavari, Eluru district, East Godavari, Visakhapatnam, Vizianagaram, and Srikakulam districts of Andhra Pradesh.[48][49] The silt-free dead storage water of nearly 100 tmcft above the spillway crest level, 24.5 metres (80 ft) MSL, can also be used in downstream lift irrigation projects (Pattiseema lift, Tadipudi lift, Chintalapudi lift, Thorrigedda lift, Pushkara lift, Purushothapatnam lift, Venkatanagaram lift, Chagalnadu lift, etc.) and Dowleswaram Barrage during the summer months.[45][50][51][52] Chintalapudi lift / Jalleru project will supply water to irrigate most of the highlands in Eluru district and NTR districts, including the existing command area under Nagarjunasagar left canal in AP, facilitating 40 tmcft of saved Krishna river water for diversion to Rayalaseema from Srisailam reservoir.[50] GoAP announced the decision to construct the Purushothapatnam Lift Irrigation Scheme to transfer water at the rate of 3,500 cusecs to the Polavaram left bank canal and further pumping at the rate of 1,400 cusecs to Yeleru reservoir for feeding Yeleru canal, which is supplying water to Vizag city.[53][54] Uttarandhra Sujala Sravanthi lift irrigation scheme will also use the Godavari water and a sanction of ₹2,114 crores was made in 2017 for its first phase.[55][56] All the irrigated lands under these lift schemes can be supplied from Polavaram right and left canals by gravity flow when Polavaram reservoir level is above the canal's full supply level of 41.15 m MSL. However, these lift stations are to be operated every year during the dry season to draw water from the substantial dead storage available behind the floodgates of the Polavaram dam. So these lift schemes are not only for operation for a few years until the Polavaram dam is constructed but also operate every year for at least four months during the dry season after construction of Polavaram dam. Nearly 80 tmcft of live storage capacity available to Andhra Pradesh in Sileru river basin can also augment the water availability to the Polavaram project during the dry season.[57]

The dam construction involves the building of a 1.5-m-thick concrete diaphragm wall up to depths from 40 to 120 m below the river bed under the earth dam, which is the first of its kind in India.[58] The purpose of diaphragm wall is to stabilize the riverbed to withstanding the water pressure across the dam. The project would constitute an earth-and-rock-fill dam 2,310 metres (7,580 ft) long, a spillway 907 metres (2,976 ft) long with 48 vents to enable discharge of 5,000,000 cu ft/s (140,000 m3/s) of water.[59] The spillway is located on the right bank of the river, for which an approach and spill channels nearly 5.5 km long and 1.0 km wide is envisaged involving nearly 70 million cubic meters of excavation which, is nearly 2/3 of the project's total earthwork. The maximum flood level at Polavaram is 28 metres (92 ft) MSL and lowest water level is 10.9 metres (36 ft) MSL. Two cofferdams are planned, one up to 41 metres (135 ft) MSL, to facilitate a faster pace of work on the dam to complete the first phase of the project by June 2018.[60] With the cofferdams' inclusion and the bed level of the approach and discharge canals of the spillway increased to 17 metres (56 ft) MSL, the spillway-related rock excavation is reduced by 70%, leading to substantial cost reduction in the project's headworks cost. Ultimately, the material of cofferdams would be excavated and reused for the peripheral portions of the main earth-and-rock-fill dam. On the left side of the river, 12 water turbines, each having an 80 Megawatt capacity, were to be installed. Without removing the upper and lower coffer dams after the construction of the ECRF dam, the 960 MW hydropower plant cannot be commissioned, as they are blocking the water passages of the powerhouse. The right canal connecting to Krishna River upstream of Prakasam Barrage (173 kilometres (107 mi) long) discharges 17,500 cu ft/s (500 m3/s) at the headworks, and the left canal (182 kilometres (113 mi) long) discharges 17,500 cu ft/s (500 m3/s) of water.[48]

Indira Dummugudem lift irrigation scheme starting at 17°33′49″N 81°14′49″E / 17.56361°N 81.24694°E / 17.56361; 81.24694 (Rudrammakota) is under construction to supply irrigation water for 200,000 acres in Khammam, Krishna, Eluru, and West Godavari districts, drawing Godavari River water from the backwaters of Polavaram reservoir.[61] This is a joint project between Andhra Pradesh and Telangana states. This project was shelved and merged with another project by the Telangana state.

Financing

[edit]
Financial progress status as on 30 September 2024[62]
Progress %
Main dam package
75.76
Connectivities
61.68
Right main canal
92.75
Left main canal
72.62
LA&RR
22.58
Total civil works
76.89
Overall progress
51.08

The revised cost of the total project including the 960 MW power station is 47,726 crores at 2017-18 prices.[63]

In December 2016, NABARD handed over ₹1,981 crores, as part of its loan from the Long Term Irrigation Fund (LTIF) under the Pradhan Mantri Krishi Sinchayee Yojana (PMKSY).[64] NABARD provided a loan of ₹2,981.54 crores during 2016-17 and ₹979.36 crores during 2017-18 under the LTIF to the National Water Development Authority (NWDA) for the project.[65]

Polavaram canal near Eluru (May 2019)
Polavaram canal near Eluru.

In its 2018 budget, Andhra Pradesh allocated ₹9000 crores to the project.[66] In June 2018, the Central Government approved ₹1,400 crores which had been sanctioned in January, but not released, through Extra Budgetary Resources raised by NABARD. These funds were from outside the LTIF.[67]

In January 2018, it was reported that the project cost had escalated to ₹58,319 crore.[68] In June 2018, the Water Ministry sanctioned ₹417.44 crore as grant-in-aid under the Accelerated Irrigation Benefit Programme under the Pradhan Mantri Krishi Sinchayi Yojana (PMKSY) towards the project.[69] By June 2018, ₹13,000 crore had been spent on the project.[17]

An expenditure of ₹16,035.88 crores has been incurred on the project from April 2014 to December 2022. A sum of ₹13,226.04 crores has been released by the centre for the execution of the project since April 2014. Bills amounting to ₹2,390.27 crores were rejected for reimbursement by the Polavaram Project Authority (PPA). Bills amounting to ₹548 crores have been received by the PPA for examination.[70]

Funding (Rs Crores) by Polavaram Project Authority (PPA) to AP state since 2014-15
Financial year 14–15 15–16 16–17 17–18 18–19 19–20 20–21 21–22 22-23[71]
Funds released by PPA to AP state 245 590 2,514.7 1,992.56 1,385 1,780 2,234.2 1,876.7 1,671.23

Interstate water sharing

[edit]

As per the inter state agreements dated 4 August 1978 (page 89) and 29 January 1979 (page 101) with Andhra Pradesh, the states of Karnataka and Maharashtra are entitled to use 21 tmcft and 14 tmcft respectively out of the unallocated waters of Krishna river when Godavari water transferred in a year by Polavaram right bank canal from Polavaram reservoir to Prakasam barrage across Krishna river does not exceed 80 tmcft at 75% dependability.[72][73] When additional Godavari water exceeding 80 tmcft is transferred from Polavaram reservoir, Karnataka and Maharashtra are entitled to additional water from the unallocated Krishna river waters in the same proportion (i.e. 21:14:45), provided all the following conditions are satisfied.[citation needed]

  • The additional Godavari water from Polavaram project should be transferred to the Krishna river upstream of Prakasam barrage. Such additional Godavari water to be shared is decided based on 75% dependability.
  • The transferred water shall also displace the water discharges from Nagarjuna Sagar Dam for the Krishna delta requirements. Krishna delta is the area located down stream of Prakasam barrage which is part of Krishna basin.[74] It does not include adjacent coastal river basins, which are being irrigated by the Krishna waters from the Prakasam barrage.[citation needed]

Thus Andhra Pradesh is entitled to transfer Godavari water in excess of 80 tmcft in three out of four years (below 75% dependability) reducing the water releases from Nagarjunasagar dam for Krishna delta requirements and need not share water with other states beyond 80 tmcft.[citation needed]

The above interstate water sharing agreement does not cover the Godavari water transferred to Krishna river which is not displacing the water releases from the Nagarjunasagar dam for the requirements of Krishna delta. Thus Andhra Pradesh need not share with other states the water transferred via Krishna river or any reservoir located on Krishna river for the water needs of any of its area (including Krishna basin) other than Krishna delta.[citation needed]

Future potential uses

[edit]

Godavari Penna River linking

[edit]

To stabilize the existing irrigated ayacut area under Nagarjuna sagar right canal, a new lift project construction with greenfield alignment was started in the first phase of Godavari Penna River linking project by having five step ladder pumping stages and a gravity canals to transfer 7,000 cusecs of Godavari water[75] from Prakasam Barrage back waters into the Nagarjuna sagar right canal near Nekarikallu by utilizing 73 tmcft of Godavari water. With FRL 25M newly created[76] Vykuntapuram Barrage pond will have back waters beyond Pokkunuru up to the toe of Pulichinthala Project. It is more economical to construct first stage pump house of this lift project to lift water from Prakasam Barrage back waters into newly created Vykuntapuram Barrage pond and the second lift stage from Vykuntapuram Barrage pond to existing K.L Rao sagar / Pulichintala Project and later lift stages from K.L Rao Sagar to Nagarjuna sagar right canal.It will shorten the length of this lift project canal, Pressure Main and fewer lift stages and also enables the lifting of water up to Srisailam Project via Existing Reversible Reverse turbine pump houses in Nagarjuna Sagar Dam and Srisailam project. It is even more economical, if we construct a new gravity canal from Ibrahimpatnam to Vykuntapuram Barrage pond to deliver the Polavaram right main canal/ Budameru diversion canal waters directly into the Vykuntapuram barrage pond since canal level is 33 m MSL at Ambapuram hill near Vijayawada. As water supply from Nagarjuna Sagar Left Bank Canal is highly erratic, Muktyala Lift Irrigation scheme is proposed by drawing water from the back waters of Vykuntapuram barrage on left bank of Krishna river.[77]

There is a proposal to link Nagarjuna Sagar Dam across the Krishna River and Somasila Dam across Penna River with 400 km canal as part of national river linking program. With help from the Indian Government, AP Govt can construct a new canal up to Somasila Dam as per DPR of Indian Rivers Inter-link program specifications.[78] Thus the Godavari River water will travel up to Somasila Dam and then Swarnamukhi in Chittoor district via existing Somasila Swarnamukhi link canal. GoAP can also provide water to Tamil Nadu with this Godavari water and retained water in Krishna River (15 TMC allocation of Krishna water to Telugu Ganga) will be used for other projects in Rayalaseema region.[citation needed]

In future a new massive dam named Palnadu Sagar[79] across hill range near Bollapalle[80] with 700 TMC capacity reservoir is possible using of flood water of Krishna River and Godavari River diverted with this lift project. It will submerge nearly 300Sq KM of land at FRL 260m MSL.Palnadu Sagar spillway with Francis Turbine will take and release water into Nagarjuna Sagar right canal along with Hydroelectricity power generation. Flood water of Krishna River will be pumped to Palnadu Sagar. The water stored in Palnadu Sagar will be used for irrigation and drinking in drought years.[citation needed]

Godavari Krishna River linking

[edit]

Vykuntapuram barrage would be constructed on Krishna river located near 16°34′41″N 80°24′43″E / 16.57806°N 80.41194°E / 16.57806; 80.41194 in the upstream of Prakasam barrage with FRL at 25m MSL to receive Godavari water diverted from Polavaram dam.[81][82]

A low level lift canal from the Krishna river located near 16°42′50″N 80°08′24″E / 16.71389°N 80.14000°E / 16.71389; 80.14000 at 20 m MSL in the downstream of Pulichintala dam will be executed to feed Godavari water diverted from Polavaram Dam to some of the existing command area (situated below 60 m MSL) under Nagarjuna Sagar right bank canal to facilitate extension of Nagarjuna Sagar right bank canal connecting to Kandaleru feeder canal / Somasila reservoir for serving irrigation needs in Prakasam, Potti Sriramulu Nellore and Chittur districts including Chennai drinking water supply. A branch from this lift canal is also extended up to Pulichinthala dam (FRL 53.34 m MSL) to store Godavari water in Pulichintala reservoir during drought years and to irrigate low lands along Krishna river up to Pulichintala dam.[83][84]

Another high level lift canal from above Krishna river location 16°42′50″N 80°08′24″E / 16.71389°N 80.14000°E / 16.71389; 80.14000 up to 90 m MSL would be constructed to join Nagarjuna Sagar tail pond (FRL 75 m MSL) irrigating lands en route along Krishna river in Guntur district. During drought years, the water transferred by this canal to Nagarjuna Sagar tail pond is further lifted to Nagarjuna Sagar and Srisailam reservoirs with the existing pumped storage hydro units for use in all the projects receiving water from these reservoirs. This high level lift canal is an alternative to Dummugudem to Sagar lift canal planned in Telangana region which would transfer Godavari river water from Dummugudem to Nagarjuna Sagar tail pond.[85] Ultimately the Polavaram right bank canal would be remodelled to enhance its capacity to 50,000 cusecs by raising its embankments for augmenting water transfer to meet shortages in the Krishna river basin and the needed environmental flows downstream of Prakasam barrage.[85]

25 MW power plant

[edit]

A 25 MW hydropower station can be established utilising Polavaram right bank canal water near Vijayawada city by transferring water via Budameru river and Eluru canal to Prakasam barrage pond.[86] The last portion of the Polavaram right bank canal is nothing but Budameru/ Velagaleru flood diversion canal which has flow limitation of 10,000 cusecs. Thus water flow from Polavaram right bank canal to Krishna River can be enhanced by constructing a 25 MW power plant.

Polavaram Banakacherla project

[edit]

This project is under active consideration by the AP state but the Ministry of Environment and Forest (MoEF) returned the proposal without according preliminary approval called Terms of Reference (ToR) in June 2025.[87] The project can get two tmcft/day for 100 days in a year by adding to water supply @ one tmcft/day on an average for 25 days from the 90 tmcft storage of AP state available in the reservoirs located in Sileru River basin. Nearly 40 tmcft live storage can also be maintained up to 145 ft MSL in the Polavaram reservoir during monsoon season per Annexure G of GWDT to moderate the inflows for feeding canals at their full capacity.The water available in the dead storage (nearly 120 tmcft) of Polavaram reservoir would be used for lean season water requirements of Dowleswaram Barrage in lieu of water supply from the stored water of Sileru River basin. With the assistance from the storages, the project can get full water more than 100 days even in a 75% dependable year at 1650 tmcft water going waste to sea. The scheme involves transferring water at 40 m MSL from Polavaram reservoir to existing Banakacherla canal regulator at 260 m MSL by many lifts. This project is economical only if all the lifted water to Banakacherla regulator is used above the 150 m MSL level without feeding to the Somasila reservoir at 100 m MSL.

Chinthalapudi lift irrigation project

[edit]

This is a project under construction to supply irrigation and municipal water requirements for the upland area located between the Krishna and Godavari Rivers in AP state. Water is drawn from the Godavari River by installing a pump house.[88] The project also supplys water to the existing command area served by the Nagarjunasagar Left Canal (NSLC) in AP state so that the saved water in the Nagarjunasagar reservoir is used for other water starved areas on the right bank side of Krishna River in the state.

Fresh water coastal reservoir

[edit]
Godavari delta (top river) and Krishna River delta (bottom river in the image) extending into the Bay of Bengal.

A fresh water coastal reservoir of storage capacity 1000 Tmcft (thousand million cubic feet) could be constructed along the sea coast to store the Krishna & Godavari river flood waters for creating additional irrigated area in Prakasam, Potti Sriramulu Nellore, Cudapah, Chittoor districts and further transfer of Godavari water to Kavery river in Tamil Nadu under interstate rivers linking project[89][90] This project is similar to Kalpasar Project to store Narmada River water in Gulf of Khambhat sea.[91][92]

Fresh water coastal reservoirs can be established in the shallow sea area by constructing sea dikes / bunds/ causeway up to the depth of 20 meters from the coast line. Water can be pumped from this artificial freshwater lagoon throughout the year for meeting agriculture, etc. needs. Also top surface of the dike can be used as coastal road & rail rout. The proposed dikes would be similar to the land reclamation of North Sea area called Delta Works in Netherlands or Saemangeum Seawall in South Korea. The earth bunds / dikes located on sea bed at 20 meters below the sea level, is lesser challenging technically when compared to Saemangeum Seawall project which is having 36 meters average water depth.[93][94]

The sea area up to 20 meters depth adjacent to coast line between the locations (near 16°19′19″N 81°42′22″E / 16.32194°N 81.70611°E / 16.32194; 81.70611 (Eastern tip of Coastal reservoir)) where Vashista Godavari, the right side branch of the Godavari river, is joining the sea and the mouth of the Gundlakamma River (near 15°34′09″N 80°13′49″E / 15.56917°N 80.23028°E / 15.56917; 80.23028 (Western tip of Coastal reservoir)), is highly suitable for creating the freshwater coastal reservoir. The average width of the sea up to 20 m depth is nearly 16 km wide and the length of the sea dikes is nearly 200 km. The area of the coastal reservoir would be nearly 2900 km2. A barrage would be constructed across the Vashista Godavari river (near 16°19′41″N 81°43′15″E / 16.32806°N 81.72083°E / 16.32806; 81.72083 (Vashista Godavari barrage)) near Antervedi Pallipalem town.[89] A flood canal (1.5 km long) from this barrage would feed Godavari river water to the coastal reservoir. With 70 tmcft live storage above the full supply level of its canals and another 100 tmcft above the spillway sill level, Polavaram reservoir will assist in moderating the Godavari flood water to make adequate water flow to the coastal reservoir.

The offshore earth dam extending up to 8 m msl high, is in the form of two parallel dikes separated by 1000 meters gap. The main purpose of the twin dikes is to prevent any sea water seepage into the coastal reservoir as its water level is below the sea water level. The water level between the dikes is always maintained at a minimum of 2 m above sea level by pumping fresh water from the coastal reservoir to the 1000 m gap between the dikes. The higher level water barrier between the two dikes eliminates any seawater seepage into the coastal reservoir by establishing freshwater seepage to the sea. The rainwater falling on the coastal reservoir area and runoff water from its catchment area is adequate to cater to the seepage and evaporation losses from the coastal reservoir. The 180 km long, 1000 m gap between the two dikes is also used as deep water mega harbor for shipping, ship breaking, ship building, etc.[95] For shipping purpose, the breakwater outer dike facing the sea is envisaged with few locks fitted with twin gates for access to the open sea. The top surface of the inner dike would serve as access to the mainland from the mega harbor with rail and road links. The coastal reservoir whose full reservoir water level (FRL) is at 0.0 m msl, would also reduce drastically the cyclone damage and flooding in coastal areas of West Godavari, Krishna, Guntur and Prakasam districts. It would also greatly improve the irrigated coastal land drainage in these districts. The coastal reservoir area can also be used for locating floating solar power plants to generate the needed water pumping power.[96] The dikes are built by dredging sand and clay from the nearby shallow sea bed to reduce the construction cost. Nearly 1850 tmcft of water of Godavari and Krishna flood waters can be utilized for irrigation, etc. requirements with this freshwater coastal reservoir.

Vast lands in the districts of Prakasam, Nellore, Cudapah, Ananthapur and Chittoor are drought prone and do not have adequate water sources for irrigating the dry lands to the extent of 10,000,000 acres.[97] Water from this coastal reservoir would be pumped uplands to Ramathirtham water tank (near 15°37′37″N 79°48′47″E / 15.62694°N 79.81306°E / 15.62694; 79.81306) which is at 85 m msl.[98] From this water tank, dry lands in Prakasam and Nellore districts up to Tamil Nadu border can be brought under irrigation by gravity canals. From this canal, water would be further pumped to the uplands up to 600 m msl across the Seshachalam mountains to irrigate vast area in Chittoor, Cudapah and Ananthapur districts. This gravity canal would also be extended further to transfer 350 tmcft water up to the Kavery river in Tamil Nadu state during South-west monsoon period. The total cost to Andhra Pradesh state would be less than ₹1,00,000 crores which is nearly ₹1,00,000 per acre of newly irrigated lands.[99]

Controversies

[edit]

The proposed project would displace 276 villages and 44,574 families spread across Andhra Pradesh state mainly. Tribals constitute 50% of such a displaced population.[100] Human rights activists came out against the project because of these reasons. In addition, one activist pointed out that this interlinking of the rivers will harm the interests of the region in the state.[101] Environmental activist Medha Patkar said that the project not only will displace several thousands of families, it will also submerge several archaeological sites, coal deposits, a wildlife sanctuary in Papikonda National Park, and several hectares of farm land.[102] 10,000 year old Megalithic period burial sites unearthered by AP state archeology officials in 2016 and 12th century temples would also be submerged.[103][104]

Sixty-four years after the initial conception of the project, the Government of Andhra Pradesh secured the environmental clearance from the central agency in 2005. This clearance was obtained after the state government prepared a 4,500 crore forest management plan and rehabilitation and resettlement proposal covering 59,756 hectares that were being lost under the project.[105] In addition, 40,000 was to be allotted for each dwelling to be constructed for the displaced as against 25,000 provided by other states.[106] Despite this clearance, the project faced political roadblocks. The Communist Party of India (M) and Bharat Rashtra Samithi were troubled with the issue of submerging agricultural lands by the project.[107][108]

Meanwhile, work on the project began in April 2006 and was expected to be completed by February 2007.[109] After 30% work of excavation work on the canals and 15% of the spillway works had been completed, the work was halted in May 2006 to seek clearance from the Ministry of Forests and Environment.[110]

The neighbouring state of Odisha also expressed its concern on the submerging of its land and decided to study this together with the officials from Andhra Pradesh.[111] In response, Chief Minister of Andhra Pradesh Late Y. S. Rajasekhara Reddy clarified that neither Odisha nor Chhattisgarh would be affected by the construction.[112] The problem continued until 2010, when Chief Minister of Odisha Naveen Patnaik remained steadfast in his demand for compensation and rehabilitation of tribals of his state who would be displaced due to the submerging of their land.[113]

Odisha and Chhattisgarh have filed a petition in the Supreme Court against the Project which has probability of temporarily submerging large areas of its state and allege that union government are going ahead with the project without the necessary permissions from Environment Ministry. Under section 90 of the Andhra Pradesh Reorganisation Act, 2014, union government has taken the responsibility of taking all clearances and approvals for the project execution and also declared the project as national project.[114] The states also allege that public hearing in the effected areas are not held. Under section 90 (3) of the Andhra Pradesh Reorganisation Act, 2014, Telangana state has already given the approval in all respects to the Polavaram project.[114][115]

In June 2018, it was reported that Naveen Patnaik, Chief Minister of Odisha had written to the Central Government to halt the Polavaram Project.[116]

Interstate river water disputes

[edit]

Odisha, Chhattisgarh and Andhra Pradesh entered into an agreement (clause vi of final order, page 80 of original GWDT) which was made part of Godavari Water Disputes Tribunal (GWDT) award.[73] The agreement allows Andhra Pradesh to construct the Polavaram reservoir with full reservoir level (FRL) at 150 feet above the mean sea level (MSL). Odisha approached Supreme Court against the design discharge capacity of the Polavaram dam spillway stating that it should be designed for five million cusecs (cubic feet per second) which is the estimated probable maximum flood (PMF) once in 1000 years duration. Odisha argues that otherwise there would be additional submergence above 150  ft MSL in its territory during peak floods. The recorded maximum flood is 3.0 million cusecs in the year 1986 during the last 115 years.[117][42]

The projected back water level build-up at Konta due to PMF in Godavari river after construction of the Polavaram project with the designed maximum water level (measured at dam point) shall be cross-checked with the level that can occur at Konta in Sabari basin from the PMF generated in the upstream of Konta when the downstream main Godavari is not under spate. Then only enhanced submergence during the PMF of the Godavari river in Odisha and Chhattisgarh states can be assessed due to the Polavaram dam construction.[1][118]

The location of Polavaram dam is in the plain area at approximately 10 km downstream from the 50 km long narrow gorge in the Papi Hills. It is also to be ascertained whether the higher backwater level during the PMF in Godavari river is solely due to the presence of long narrow gorge which is acting as a natural dam/barrier or further enhanced by the presence of the downstream Polavaram barrage.[119][1]

It is purely an academic interest showing concern for the few thousand hectares of farm/forest land submerged by the backwater level build-up once in five hundred or thousand years (against the permitted norm of once in 25 years) without showing concern for the thousands of square kilometers land submerged in the area downstream of the dam with a river flood of magnitude five million cusecs.[1]

Thirty-two years have passed after the GWDT award in 1980, Maharashtra, Odisha and Chhattisgarh have not made serious efforts to harness the major Godavari tributaries such as Sabari River, Indravati River and Pranahita River to utilize the allocated share of Godavari waters. This underutilization of water is the main reason for the very high flood flows at the Polavaram dam site. The vast area in excess of 10,000 square km up to sea are frequently flooded (at least once in a decade) by Godavari floods in Andhra Pradesh by the flood waters originating in Madhya Pradesh, Maharashtra, Odisha and Chhattisgarh states. The land submergence due to the Polavaram dam in Odisha and Chhattisgarh states is a fraction of the Andhra Pradesh area which is affected by the floods in the Godavari River. During the years from 1953 to 2011, Andhra Pradesh suffered nearly 55,800 crore which is 26% of total flood damage in India.[120] It is justified to raise the FRL of Polavaram dam further on this ground alone. One single criterion shall be applied by the tribunals/courts for all the submerged lands whether they are related to reservoir projects construction or due to river floods (i.e. non-utilization of river water). Upstream states shall not take granted that downstream state areas are permitted to be flooded /inundated by the river flood water without offering agreeable relief/comforts.[1]

Odisha and Chhattisgarh entered into an agreement (clause 3e, Annexure F, Page 159 of original GWDT) to construct a Hydro electricity project at Konta / Motu just upstream of the confluence point of Sileru tributary with Sabari River (tri-junction point of Andhra Pradesh, Odisha and Chhattisgarh borders).[121] When this project is constructed, the land submergence would be more than that of Polavaram backwaters. It would be better for Odisha and Chhattisgarh to enter into an agreement with Andhra Pradesh to shift the location of this Hydro electricity project further downstream in Andhra Pradesh territory to harness Sileru river water also for hydroelectricity generation. This joint project of the three states would eliminate the backwaters issue of the Polavaram dam.[citation needed]

The 200  km long stretch of the Sabari river forming boundary between Chhattisgarh and Odisha drops by 2.25 meters per km length on average. This stretch of the river has substantial hydroelectricity generation potential by building medium head (< 20 m) barrages in series to minimize land submergence.[122] The surplus water of Indravati River in Odisha can also be diverted to Sabari river via Jouranala through which Indravati River flood waters naturally overflow into Sabari basin for power generation.[123]

Dispute with Odisha and Telangana

[edit]

In July 2018, a two-member bench of the Supreme Court asked Andhra Pradesh, Telangana, Odisha and Chhattisgarh governments to frame the issues for arguments. Telangana said to the court it is in-principle agree for the project but the center should take up study by neutral central institute like CWPRS, Pune to study the impact of Backwater due to increase of 36 lakh cusecs to 50 lakh cusecs of spillway design discharge, it is to ascertain the safety of important temple town like Bhadrachalam, Mining areas and heavy water Plant. Odisha also insisted on backwater studies.[1] The matter is before Supreme court. Proceedings are going on. Supreme Court identified 13 issues to settle the dispute.[124]

See also

[edit]

References

[edit]
Revisions and contributorsEdit on WikipediaRead on Wikipedia
from Grokipedia
The Polavaram Project is a multi-purpose dam and irrigation initiative on the Godavari River near Ramayyapeta village in Polavaram Mandal, Andhra Pradesh, India, approximately 34 kilometers upstream from the Sir Arthur Cotton Barrage at Dowleswaram, intended to harness the river's flow for irrigation, hydroelectric power generation, and water supply.[1][2] The project features an earth-cum-rockfill dam with a spillway capable of discharging 3,600,000 cubic feet per second across 44 vents spanning 2,310 meters, creating a reservoir with gross storage of 194 thousand million cubic feet (tmcft) and live storage of 75.2 tmcft at full supply level.[3] It aims to develop a gross irrigation potential of 436,825 hectares through extensive canal networks, including a 182-kilometer left main canal irrigating 161,900 hectares in East Godavari and Visakhapatnam districts, while also generating 960 megawatts of hydropower via 12 Kaplan turbine units of 80 MW each.[1][2][4] Declared a national project under Section 90(1) of the Andhra Pradesh Reorganisation Act, 2014, the initiative supports water transfer to upland areas and integration with broader river-linking efforts, providing drinking water to urban centers and stabilizing delta agriculture against drought variability.[5][6] As of October 2025, construction advances toward completion by December 2027, with the diaphragm wall targeted for finish by year-end and the left main canal operational by January 2026 to enable initial water flows.[7][8] Notable achievements include the adoption of advanced engineering like automated tunneling for underground works and real-time structural monitoring to mitigate seepage risks in the permeable foundation strata, setting records in large-scale hydro construction efficiency.[9][10] However, the project has faced delays from geological challenges, funding constraints post-2014 state bifurcation, and interstate disputes over water allocation with Telangana and Odisha.[11] Controversies center on displacement affecting approximately 98,818 families, predominantly tribal communities in East and West Godavari districts, alongside submersion of archaeological sites and forests, raising empirical concerns about biodiversity loss and downstream ecological shifts from altered hydrology.[12][13] Rehabilitation efforts persist amid reports of inadequate resettlement, though official mechanisms prioritize land-for-land compensation under national guidelines.[12] Environmental assessments highlight potential for increased erosion and habitat fragmentation, underscoring trade-offs between regional development gains and localized impacts verifiable through pre- and post-impoundment monitoring data.[14][15]

Background and Overview

Geographical and Strategic Context

The Polavaram Project is located on the Godavari River near Ramayyapeta village in Polavaram mandal, West Godavari district, Andhra Pradesh, approximately 42 kilometers upstream from the Sir Arthur Cotton Barrage at Dowleswaram.[2] The Godavari, India's second-longest river at 1,465 kilometers, originates in the Western Ghats of Maharashtra and traverses Telangana before entering Andhra Pradesh, draining a basin spanning 312,812 square kilometers across Maharashtra (48.6%), Telangana (18.8%), Andhra Pradesh (4.5%), Chhattisgarh (10.9%), and Odisha.[16] The project's dam site lies in a geologically stable region within the Eastern Ghats, where the river flows through hilly terrain, facilitating reservoir formation with backwater effects extending into upstream areas of Telangana, Odisha, and Chhattisgarh.[17] Strategically, the project serves as a linchpin for inter-basin water transfer, enabling diversion of approximately 80 thousand million cubic feet (TMC) of surplus Godavari water to the Krishna River basin to irrigate drought-prone regions in Andhra Pradesh and support industrial needs.[18] Designated a national project by the Government of India in 2014, it addresses post-bifurcation water scarcity in Andhra Pradesh while generating up to 960 megawatts of hydroelectric power and providing flood control through reservoir storage.[19] Its upstream position relative to major tributaries like the Indravati and Sabari allows capture of monsoon flows, but submergence of over 300 villages across four states has sparked inter-state disputes over rehabilitation and water rights, highlighting tensions in riparian resource allocation.[17] The initiative aligns with broader national goals of river interlinking under the National River Linking Project, positioning Polavaram as a critical node for enhancing agricultural productivity—potentially irrigating 1.2 million hectares—and ensuring drinking water for urban centers like Visakhapatnam, amid competing claims from basin states.[19] This strategic centrality underscores its role in balancing ecological impacts, such as potential siltation in the Godavari delta, against developmental imperatives in a water-stressed peninsula.[20]

Primary Objectives and National Importance

The Polavaram Project serves as a multi-purpose initiative on the Godavari River, with core objectives centered on expanding irrigation coverage, generating hydroelectric power, and ensuring reliable water supply for domestic and industrial use. It aims to cultivate a gross irrigation potential of 436,825 hectares across drought-prone and rain-fed areas in Andhra Pradesh, primarily through left and right bank canals serving districts such as East Godavari, West Godavari, Visakhapatnam, and Krishna, thereby stabilizing existing farmland and enabling multi-season cropping to boost agricultural output.[1] The project also targets the production of 960 megawatts of hydropower via a surface power house equipped with 12 units of 80 MW each, contributing to regional energy needs while minimizing reliance on fossil fuels.[2] Beyond local benefits, the initiative includes provisioning 23.44 thousand million cubic feet (TMC) of water for drinking purposes to Visakhapatnam urban area and adjoining industries, such as the Visakhapatnam Steel Plant, addressing chronic urban water deficits. Additionally, it facilitates the diversion of approximately 80 TMC of surplus Godavari waters to the Krishna River basin, supporting downstream irrigation and mitigating seasonal shortages in interconnected river systems.[2] Its elevation to national project status under Section 90 of the Andhra Pradesh Reorganisation Act, 2014, highlights its broader strategic value to India's water security framework, with the central government assuming responsibility for execution, funding, and regulatory clearances to ensure timely completion in the public interest.[6] This designation stems from the project's capacity to harness underutilized river flows for inter-basin transfers, aligning with national goals of drought-proofing peninsular regions and integrating into larger river linking schemes, while addressing post-bifurcation resource equity among affected states like Telangana, Odisha, and Chhattisgarh.[21] By centralizing oversight through bodies like the Polavaram Project Authority, it underscores the federal commitment to infrastructure that enhances economic resilience and food production amid variable monsoons.[6]

Historical Development

Early Proposals and Feasibility Studies

The idea of constructing a storage reservoir at Polavaram on the Godavari River originated in the mid-19th century, when British engineer Sir Arthur Cotton, while overseeing the Dowleswaram Barrage (completed in 1852), identified the site's potential for impounding floodwaters to support irrigation in the delta regions.[22] This early conceptualization emphasized harnessing surplus monsoon flows that otherwise discharged unused into the Bay of Bengal, reflecting pragmatic hydraulic engineering principles amid colonial priorities for agricultural productivity.[22] The first formal proposal emerged on July 16, 1941, under the Madras Presidency, which advocated for a multipurpose dam to generate hydropower, irrigate arid upland tracts, and mitigate floods in the Godavari basin.[23] Diwan Bahadur L. Venkata Krishna Iyer, a senior engineer, spearheaded the initiative, drawing on hydrological data to project benefits for over 1 million acres of cultivable land across present-day Andhra Pradesh districts.[18] Preliminary feasibility investigations commenced shortly thereafter, involving topographic surveys and basic hydrological assessments to evaluate dam alignment, spillway requirements, and submersion impacts, though wartime constraints delayed comprehensive analysis.[23] Post-independence, during India's First Five-Year Plan (1951–1956), the Government of India reviewed Polavaram alongside alternative Godavari sites like Ramapadasagar but deferred prioritization, opting instead for upstream projects such as the Godavari Anicut system to address immediate irrigation deficits with lower capital outlay. Momentum revived in the 1970s amid growing recognition of inter-basin water transfers; in 1978, the Andhra Pradesh government commissioned a detailed project report (DPR) to quantify reservoir storage (estimated at 194 thousand million cubic feet), irrigation potential (up to 1.2 million acres), and power generation (960 MW). The DPR, incorporating geological borings, sediment yield models, and cost-benefit analyses, was finalized in 1985 and submitted to the Central Water Commission in 1987 for technical clearance, marking the transition from conceptual studies to actionable planning despite ongoing debates over environmental and displacement costs.[24]

Key Milestones in Planning and Approval

The first conceptual proposal for the Polavaram Project was put forward in July 1941 by the Madras Presidency, with preliminary investigations initiated thereafter to assess its feasibility for irrigation and flood control on the Godavari River.[23] Detailed feasibility studies and surveys continued intermittently through the post-independence period, focusing on hydrological data and site-specific engineering challenges, though progress stalled due to interstate water-sharing disputes.[25] A significant advancement occurred on April 2, 1980, when Andhra Pradesh, Madhya Pradesh, and Odisha signed an interstate agreement under the Godavari Water Disputes Tribunal award, authorizing clearance for the project and enabling Andhra Pradesh to proceed with submergence in upstream states.[25] [18] The detailed project report (DPR) was completed in 1985 and submitted to the Central Water Commission (CWC) in 1987 for technical appraisal, incorporating estimates for irrigation potential, hydropower generation, and reservoir capacity.[24] Initial environmental clearance was granted by the Ministry of Environment and Forests in October 2005, following submission of environmental impact assessments, though this was later quashed by the National Green Tribunal in 2008 amid concerns over inadequate tribal displacement studies and forest loss evaluations.[26] Investment clearance for the original estimated cost of Rs. 7,163 crore (at 2003-04 prices) was accorded by the Planning Commission on February 25, 2009, paving the way for funding under the Accelerated Irrigation Benefits Programme.[27] The project received designation as a national project under Section 90(1) of the Andhra Pradesh Reorganisation Act, 2014, effective from June 2, 2014, transferring responsibility for execution, clearances, and funding to the central government while deeming consent from Telangana.[28] A revised DPR, addressing scope changes and cost escalations to Rs. 55,548 crore (at 2017-18 prices), was approved by the Technical Advisory Committee of the Ministry of Water Resources in February 2019.[29] The Polavaram Project Authority was established in January 2015 to oversee inter-state coordination and implementation.[6]

Construction Timeline and Political Influences

Construction of the Polavaram Project commenced in 2005 following administrative approval in 2004, with initial works focusing on foundational elements like the diaphragm wall and cofferdams.[30] Early progress included land acquisition and preliminary earthworks, but the project faced immediate scaling challenges due to its massive scope, leading to revised timelines beyond the initial 2007 target.[31] By 2013, the diaphragm wall—a critical seepage barrier—was under construction, but it suffered significant damage during the 2020 Godavari floods, with approximately 35% affected at multiple points, necessitating reconstruction.[32] Further setbacks occurred in August 2025 when the upper cofferdam experienced a major slide, highlighting ongoing geotechnical vulnerabilities in the site's permeable soils.[33] As of October 2025, reconstruction efforts include a new diaphragm wall initiated in early 2025, targeted for completion by December 2025 using advanced trench cutters and grabbers.[34] Earth-cum-rockfill dam works are scheduled to begin in November 2025, with Phase 1 completion projected for June 2027, though earlier directives aimed for October 2026.[35] [36] Dewatering of the site began in June 2025 to facilitate these advances, marking a resumption of momentum after prior halts.[37] Despite these milestones, the project remains approximately 50% complete after two decades, with cost escalations exceeding ₹21,000 crore attributed to repeated rework and inflation.[38] Political dynamics have profoundly shaped the project's trajectory, with successive Andhra Pradesh governments prioritizing it as a prestige initiative while engaging in mutual recriminations over delays. The Telugu Desam Party (TDP) under N. Chandrababu Naidu accelerated works post-2004 approval but faced interruptions after the 2009 shift to Congress rule under Y. S. Rajasekhara Reddy, who integrated it into the Jala Yagnam program yet struggled with funding.[39] The 2014 state bifurcation, creating Telangana, elevated Polavaram to national project status with central funding commitments, but sparked disputes over submergence of Telangana territories and water allocation, complicating land mergers and rehabilitation.[40] Post-2014 TDP governance advanced headworks but saw contractor changes and quality lapses, while the 2019 YSR Congress Party (YSRCP) administration under Y. S. Jagan Mohan Reddy halted certain packages in 2019, reversed progress, and minimized advancements until 2024, prompting accusations of inefficiency and favoritism.[41] [30] The 2024 return of TDP-led NDA governance has refocused efforts with Union Minister Nitin Gadkari's oversight and enhanced central allocations, aiming to mitigate prior state-level funding shortfalls exacerbated by bifurcation revenue losses.[42] Inter-state tensions persist, with Odisha raising submergence concerns and Telangana contesting upstream impacts, though Andhra maintains the project's design minimizes externalities.[43] Allegations of corruption, labor exploitation by contractors, and political nexus have surfaced across regimes, underscoring how electoral cycles and patronage networks contribute to cost overruns and execution gaps beyond pure technical hurdles.[44] Central intervention, including expert panels post-damages, has been pivotal in enforcing standards, yet state political volatility remains a causal factor in protracted timelines.[34]

Technical Specifications

Dam and Spillway Design

The Polavaram Dam consists of a main earth-cum-rockfill embankment flanking a central concrete gravity spillway, engineered to manage high flood discharges while providing structural stability in a seismically active region. The embankment dam reaches a maximum height of 39.28 meters above the riverbed, utilizing locally sourced materials for the core and shell to ensure impermeability and resistance to seepage.[45] The design incorporates a diaphragm wall for enhanced foundation stability, particularly critical given the alluvial and rocky substrata along the Godavari River, to prevent underseepage and uplift pressures during reservoir filling.[46] The spillway, positioned on the right bank of the river, features an ogee-shaped crest profile optimized for efficient flow over the structure during extreme events. It spans 1,118.4 meters in length and is equipped with 48 radial gates, each measuring 16 meters wide by 20 meters high, enabling precise control of releases.[2] The crest elevation is set at +25.72 meters, with the structure designed to discharge the probable maximum flood (PMF) of 141,435 cubic meters per second (approximately 5 million cubic feet per second), corresponding to a 1-in-10,000-year event based on hydrological assessments of the Godavari basin.[2][47] This capacity exceeds initial tribunal specifications of 36 lakh cusecs at a 140-foot pond level, incorporating conservative margins for upstream tributary inflows and climate variability.[25] Seismic considerations in the design adopt horizontal and vertical coefficients of 0.08 and 0.04, respectively, reflecting the project's location in Seismic Zone III, with the spillway's maximum height reaching 57.90 meters to accommodate overtopping risks.[48] Radial gates were selected over vertical lift types for their hydraulic efficiency and reduced operational head losses, supported by finite element analyses validating stress distribution under full reservoir and flood loading conditions.[49] The overall configuration prioritizes flood attenuation to protect downstream deltas, with energy dissipation features in the stilling basin to minimize scour at the toe.[3]
ComponentSpecification
Dam TypeEarth-cum-rockfill embankment with concrete spillway
Maximum Dam Height39.28 m
Spillway Length1,118.4 m
Number of Gates48 radial gates
Gate Dimensions16 m (width) × 20 m (height)
Crest Elevation+25.72 m
Design Discharge (PMF)141,435 m³/s
Seismic CoefficientsHorizontal: 0.08; Vertical: 0.04

Reservoir Capacity and Hydrology

The reservoir of the Polavaram Project features a full reservoir level (FRL) of 45.72 meters (150 feet) above mean sea level and a minimum drawdown level of 41.15 meters (135 feet).[50] The gross storage capacity at FRL totals 5,511 million cubic meters (Mm³), equivalent to 194.6 thousand million cubic feet (TMCft), while live storage—usable for irrigation, power generation, and other purposes—amounts to 2,130 Mm³ (75.2 TMCft).[50] [1] Dead storage below the minimum drawdown level constitutes the remainder, primarily to accommodate sediment accumulation from upstream inflows, though its precise volume varies with siltation rates observed over time.[51] Hydrologically, the Polavaram site captures nearly the entire Godavari River basin, with a catchment area of approximately 306,643 square kilometers contributing to inflows.[52] The Godavari's long-term average annual surface flow at this downstream location reaches about 110 billion cubic meters (km³), predominantly from monsoon rainfall between June and October, enabling high utilization rates despite the reservoir's modest storage relative to total yield.[53] Design considerations account for peak flood events, with the spillway engineered for a maximum discharge capacity of 36 lakh cusecs (approximately 10,188 cubic meters per second, cumecs) to handle the probable maximum flood of 1.02 million cusecs (28,800 cumecs).[25] [52] This configuration prioritizes flood moderation and water diversion over extensive impoundment, as annual demands exceed live storage by factors of 3–4 times, relying on regulated releases from upstream projects like Srirama Sagar.[50]

Power and Irrigation Infrastructure

The power infrastructure of the Polavaram Project centers on a surface power house situated on the left bank of the dam, featuring an installed hydropower capacity of 960 MW through 12 turbine-generator units, each with a rating of 80 MW.[2] This facility harnesses the hydraulic head from the reservoir to produce electricity, with a gross head of approximately 27.95 meters supporting the generation process.[54] The design incorporates water conductor systems, including tunnels and penstocks, to channel flow efficiently to the turbines.[2] The irrigation infrastructure comprises an extensive network of canals originating from the dam's headworks. The left main canal extends 181.999 km, designed to deliver water by gravity to a culturable command area (CCA) of 161,855 hectares (400,000 acres) primarily in East Godavari and Visakhapatnam districts of Andhra Pradesh.[1] [2] This canal system includes branch canals and distributaries to stabilize existing ayacuts and extend coverage to new areas.[2] Complementing the left canal, the right main canal measures 178.81 km and serves dual purposes of irrigating local command areas and diverting surplus Godavari water (up to 80 TMC annually) toward the Krishna River basin for inter-basin transfer.[1] The right canal supports irrigation in West Godavari and Krishna districts, contributing to the project's total irrigation potential of 436,825 hectares across Andhra Pradesh.[1] Both main canals are lined in sections to minimize seepage losses and incorporate structures such as aqueducts, syphons, and cross-drainage works to navigate topography.[2] The integrated power and irrigation systems rely on the dam's reservoir, with a gross storage capacity of 194 TMC, enabling year-round water allocation for hydropower peaking and irrigation during dry seasons, while spillway arrangements manage flood discharges.[2]

Anticipated Benefits

Agricultural and Economic Impacts

The Polavaram Project is projected to generate an annual irrigation potential of 10.80 lakh acres (approximately 4.37 lakh hectares) through enhanced water distribution via main canals and branch networks, enabling higher cropping intensity of up to 150% in command areas across Andhra Pradesh districts including Eluru, West Godavari, Krishna, and East Godavari.[1] This expansion includes new irrigation for 5.25 lakh acres and stabilization of existing systems covering 2.2 lakh acres, facilitating year-round cultivation and crop diversification from rain-fed paddy to high-value crops such as sugarcane, cotton, and horticultural produce.[1] Reliable water supply is expected to mitigate drought risks, with hydrological models indicating sustained reservoir inflows supporting multiple cropping seasons.[55] Agriculturally, the project anticipates a significant uplift in productivity, with estimates suggesting doubled yields in irrigated zones due to controlled water application reducing dependency on erratic monsoons and groundwater overexploitation.[56] Farmer incomes in the command area could rise by 30-50% through expanded ayacut and improved soil moisture retention, as evidenced by analogous irrigation schemes in the Godavari basin where stabilized supplies led to similar gains in output per hectare.[57] The infrastructure, including the 178.81 km right main canal, will extend benefits to en route lands, promoting agro-based industries like rice milling and food processing.[1] Economically, the initiative is forecasted to contribute substantially to Andhra Pradesh's agrarian GDP by bolstering output from a sector employing over 60% of the rural workforce, with projected annual agricultural value addition exceeding ₹10,000 crore based on enhanced yields and market linkages.[58] Benefit-cost analyses from project appraisals indicate a ratio above 1:1, factoring in irrigation returns alongside ancillary gains like reduced migration and localized employment in canal maintenance and farming operations.[59] Industrial water allocation from surplus flows is poised to attract manufacturing investments, fostering job creation estimated at tens of thousands in downstream sectors, though realization hinges on timely completion amid cost escalations.[60] Overall, the project's causal chain links water security to economic multipliers, potentially elevating regional per capita incomes through integrated rural development.[56]

Hydropower and Energy Security

The Polavaram Project incorporates a surface hydropower plant on the left flank of the dam, featuring 12 Kaplan turbine units each rated at 80 MW, yielding a total installed capacity of 960 MW.[2] This configuration utilizes the reservoir's hydraulic head and flow from the Godavari River, with water conducted through tunnels and a tailrace system for efficient generation.[61] The plant is designed primarily as a run-of-river facility augmented by seasonal storage, enabling power production during monsoon inflows from June to December.[62] Upon full commissioning, the facility is projected to generate approximately 2.37 billion kilowatt-hours (kWh) of electricity annually, equivalent to about 2,369 million units, supporting peak and baseload demands in Andhra Pradesh.[63] This output derives from hydrological assessments of average annual inflows and operational efficiencies, with Kaplan turbines optimized for low-head, high-flow conditions typical of the Godavari basin.[4] In terms of energy security, the 960 MW addition will expand Andhra Pradesh's hydroelectric capacity, which stood at around 2,336 MW prior to the project, by over 40%, enhancing grid reliability and reducing reliance on coal-fired thermal plants that dominate the state's 20,000+ MW total installed base.[64] As a renewable source, it provides dispatchable power for peaking during high-demand periods, mitigating intermittency risks from solar and wind integrations, while contributing to lower carbon emissions in a region where thermal generation accounts for the majority of supply.[54] The project's integration via dedicated transmission lines to the state grid further bolsters regional energy independence, aligning with national goals for diversified hydropower under India's renewable energy targets.[65]

Urban Water Supply and Navigation Enhancements

The Polavaram Project allocates 23.44 thousand million cubic feet (TMC) of water for drinking and industrial supply, directed primarily through the left main canal to Visakhapatnam city and the Visakhapatnam Steel Plant.[2] This provision addresses urban water demands in Andhra Pradesh's northern coastal region, supporting residential and industrial consumption in Visakhapatnam and surrounding areas.[1] In addition to urban allocations, the project delivers drinking water to 2.85 million individuals across 611 villages along the canal routes, mitigating scarcity in rural and semi-urban locales.[25] The 182-kilometer left main canal extends irrigation to East Godavari and Visakhapatnam districts while enabling water conveyance up to Anakapalli, with completion targeted for January 2026 to expedite urban distribution.[66] [2] Navigation enhancements stem from the project's reservoir and canal infrastructure, which stabilize water levels in the Godavari River and affiliated waterways. A proposed navigation channel connecting Rajamahendravaram (Rajahmundry) to Badrachalam is envisioned to facilitate inland transport and stimulate tourism.[67] Reservoir impoundment to depths of 41.15 to 45.72 meters will improve boating viability, prompting demands for permanent jetties to accommodate tourist vessels.[68] These features align with broader efforts to develop navigable stretches under National Waterway 4, potentially integrating cargo and recreational traffic along the Godavari.[69]

Current Progress and Challenges

Construction Achievements to Date

As of October 2025, the construction of the diaphragm wall—a vital underground barrier for the project's earth-cum-rockfill dam foundation—has advanced to 37,302 cubic meters out of a total required 63,656 cubic meters, representing approximately 59% completion.[66] This progress includes ongoing excavation and concreting using multiple trench cutters and grabbers, with works continuing uninterrupted despite seasonal floods in the Godavari River basin, enabling the completion of an additional 6,600 square meters of parallel diaphragm wall segments in September 2025.[70] International experts have monitored the quality and pace, confirming adherence to design specifications for the 1,398-meter-long, 5-meter-wide structure.[71] Preparatory works for the main earth-cum-rockfill dam have reached a stage where principal construction is set to commence on November 1, 2025, pending final design approval from the Central Water Commission.[72] Upstream cofferdams and buttress berms, essential for diverting river flow during dam building, have seen incremental advancements, including rock filling at key gaps to stabilize the site.[73] These efforts build on earlier foundational achievements, such as partial spillway gate installations and initial canal alignments, contributing to an overall project completion rate exceeding 55% as reported in early 2025, with accelerated gains under current oversight.[74] Left and right main canals, integral to irrigation distribution, have progressed with sections operational for testing, including aqueducts and linings near Eluru, though full commissioning awaits reservoir filling.[75] Hydropower components, including power house foundations, remain in preparatory phases but benefit from site stabilization achieved through the diaphragm works.[76] These milestones reflect intensified resource allocation since mid-2024, prioritizing flood-resilient techniques and expert validation to mitigate prior delays.[77]

2025 Developments and Acceleration Efforts

In early 2025, the Andhra Pradesh government under Chief Minister N. Chandrababu Naidu intensified efforts to accelerate the Polavaram Project, achieving a progress milestone of 55.90% overall completion by February, a 6.1 percentage point increase from the prior eight months under the NDA administration, compared to 38.21% as of May 2019. This uptick was driven by renewed focus on critical infrastructure, including the initiation of a new diaphragm wall on January 18, which reached 11.33% completion (158.20 meters out of 1,396.60 meters) by April, with a targeted finish by December 31.[74] The government also announced enhanced rehabilitation measures for project-affected families in March, aiming to address displacement concerns amid accelerated construction.[12] By mid-2025, construction faced scrutiny for uneven pacing, with reports in July highlighting delays in meeting the diaphragm wall deadline despite overall momentum, though the project demonstrated resilience by managing flood discharges exceeding 10.17 lakh cusecs via the spillway in August. Acceleration efforts included the start of a new parallel diaphragm wall at Gap II on May 5, as noted by the Polavaram Project Authority, and international engineering experts commended the site's progress and quality standards in September.[6][78][79][71] In October 2025, Naidu issued directives to expedite works for completion ahead of the 2027 Godavari Pushkarams, mandating the earth-cum-rockfill dam construction to begin in November and conclude by December 2027, alongside finishing the left main canal by January 2026 to enable water supply to Anakapalli district. Complementary acceleration targeted the Polavaram-Banakacherla linkage for Godavari water diversion to Rayalaseema by 2027, bypassing stalled interstate negotiations. These measures built on the buttress dam's full completion and 74% vibro-compaction progress reported contemporaneously, underscoring a strategic push to operationalize key components despite persistent hydrological risks like cofferdam erosion during floods.[80][66][81][82][83] In a recent on-site inspection, Chief Minister N. Chandrababu Naidu reviewed the project's progress, noting 87% completion of civil works. He directed officials to finish remaining works within the stipulated timeline, expedite Polavaram Left Canal works, ensure water supply to the Kolleru region via the Right Canal, and prepare an action plan for rehabilitation and resettlement of project-affected families.[84][85]

Ongoing Technical and Logistical Hurdles

The Polavaram Project continues to encounter structural vulnerabilities in its cofferdam system, particularly the upper cofferdam, which has experienced multiple slides and cave-ins exacerbated by heavy monsoon rains. In August 2025, a 10x10 meter mud slip occurred on the left bank between stretches 80-90 due to continuous rainfall, prompting emergency repairs that were completed within days, with officials asserting no downstream impacts or structural damage.[86][87] However, independent reports highlighted ongoing seepage issues necessitating persistent dewatering operations, even as diaphragm wall construction proceeded, raising concerns over the cofferdam's stability for diverting river flow during dam foundation work.[83][88] Project authorities have downplayed these incidents as minor and vehicle-induced, denying broader damage claims amid conflicting assessments from site observers.[89][90] Quality control remains a persistent technical challenge, with lapses in construction standards persisting despite recommendations from foreign experts. As of July 2025, the project selected a third-party agency to oversee transparency and adherence to specifications, addressing recurrent defects in materials and workmanship that have delayed progress.[34] These issues compound foundational geological risks in the Godavari basin, where weak soil strata have historically complicated seepage mitigation and required reinforced designs like the diaphragm wall, targeted for completion by late 2025.[7] Logistically, land acquisition and rehabilitation efforts face significant delays, hindering site clearance and displacing communities without timely alternatives. In September 2025, officials in Alluri Sitarama Raju district were directed to identify 4,000 acres for resettling project-affected families, particularly tribals, amid prolonged compensation disputes and possession holdups.[91][92] August 2025 directives from Eluru district authorities urged expedited acquisitions for relief and rehabilitation, yet bureaucratic and resistance-related bottlenecks persist, contributing to overall project stagnation.[93][12] These hurdles, intertwined with funding intermittency, have extended timelines, with technical interventions like cofferdam reinforcements and logistical streamlining essential to meet accelerated targets for 2026 canal completion and 2027 full operations.[94]

Financing and Governance

Funding Mechanisms and Central Support

The Polavaram Project's funding has historically relied on a combination of state budgetary allocations from Andhra Pradesh and central government assistance, with the latter intensifying after the project's designation as a national project of importance in 2014 under the Andhra Pradesh Reorganisation Act.[95] This status shifted the financial burden toward the centre, which committed to covering a significant share of costs, including through reimbursements via the Long Term Irrigation Fund managed by the National Bank for Agriculture and Rural Development (NABARD).[96] Mechanisms include direct budgetary grants, extra-budgetary resources raised by NABARD with government guarantees, and phased releases tied to project milestones, such as the Rs 1,400 crore sanctioned in 2018 for headworks completion.[97] In July 2024, Finance Minister Nirmala Sitharaman announced that the central government would fully finance the project to accelerate completion, addressing prior delays attributed to funding shortfalls under the previous state administration.[98] This commitment materialized through substantial allocations: Rs 12,157 crore released as a balance grant, split as Rs 6,000 crore for fiscal year 2024-25 and Rs 6,157 crore for 2025-26, alongside the revised project cost approval of Rs 30,436.95 crore in the 2025 Union Budget.[99] [100] The 2025-26 Union Budget further earmarked Rs 5,936 crore specifically for Polavaram, reflecting prioritized central support amid Andhra Pradesh's fiscal constraints.[101] Central funding releases have been responsive to state-submitted estimates, such as the Andhra Pradesh government's June 2023 proposal for Rs 17,144.06 crore in balance works, processed via the Ministry of Jal Shakti.[102] However, implementation has faced scrutiny over reimbursement delays and alignment with actual expenditures, with the centre historically approving costs below state claims—e.g., capping at Rs 47,725.74 crore in earlier revisions despite higher demands—to enforce fiscal discipline.[103] These mechanisms underscore a hybrid model where central grants mitigate state liabilities, but execution hinges on coordinated approvals and verifiable progress reporting.

Cost Escalations and Economic Analysis

The Polavaram Project's initial detailed project report, prepared in 1986, estimated costs at ₹2,665 crore based on 1985-86 price levels.[104] By 2004, when the project received central approval, the estimated cost had risen to approximately ₹14,000 crore, reflecting preliminary adjustments for scope including irrigation, hydropower, and flood control components.[105] The second revised cost estimate (RCE-II), approved by the Ministry of Jal Shakti at 2017-18 prices, stood at ₹55,548.87 crore, incorporating escalated expenses for construction, land acquisition, and rehabilitation.[106] Cost overruns have been driven primarily by prolonged delays exceeding two decades since construction began in earnest around 2004, compounded by inflation, iterative design modifications to address geological and hydrological challenges, and expanded rehabilitation requirements under updated land acquisition laws.[30] [107] Political transitions in Andhra Pradesh, contractor terminations due to performance issues, and disputes over funding reimbursements between state and central governments have further inflated expenditures, with one assessment attributing over ₹10,000 crore in losses directly to delays as of late 2024.[108] [109]
Cost Estimate MilestoneAmount (₹ crore)Price Level/Base YearKey Factors Noted
1986 Initial Report2,6651985-86Basic irrigation and power scope[104]
2004 Approval14,000ContemporaryExpanded multipurpose elements[105]
2017-18 RCE-II55,5492017-18Delays, R&R, design revisions[106]
Economic assessments of the project hinge on projected returns from irrigating over 300,000 hectares, generating 960 MW of hydropower, and supplying drinking water to urban centers, though final benefit-cost ratios remain contingent on state-provided data clarifications and have not been independently verified in recent public analyses.[59] Government approval of revised estimates presupposes viability, with anticipated agricultural productivity gains and flood mitigation benefits outweighing costs in official evaluations, yet critics highlight that unchecked overruns—exacerbated by funding gaps and scope expansions—diminish net returns and strain public finances without proportional output realization.[106] [108] Delays have imposed opportunity costs, including forgone irrigation revenues estimated in thousands of crores annually, underscoring the need for rigorous ex-post audits to validate long-term internal rates of return amid persistent fiscal pressures.[110]

Management Structure and Accountability

The Polavaram Project is owned and primarily executed by the Government of Andhra Pradesh through its Water Resources Department, with the Chief Engineer for the Polavaram Irrigation Project responsible for on-site construction oversight, including civil works for the dam, spillway, and canals.[6] Central government involvement stems from the project's designation as a national project under the Andhra Pradesh Reorganisation Act, 2014, leading to the establishment of the Polavaram Project Authority (PPA) via notification dated May 28, 2014, to ensure coordinated execution across interstate aspects.[96] The PPA operates under the Ministry of Jal Shakti, functioning as a nodal agency for monitoring, funding release, and technical guidance, with the Government of Andhra Pradesh's executing agency handling day-to-day implementation under PPA directives.[6] The PPA's Governing Body, chaired by the Secretary of the Ministry of Jal Shakti, includes representatives from relevant central ministries and Andhra Pradesh officials, tasked with policy formulation, progress review, and dispute resolution related to designs, land acquisition, and rehabilitation.[111] The Chief Executive Officer (CEO) of the PPA, appointed by the central government—such as Atul Jain, who assumed additional charge on December 19, 2024—holds administrative, financial, and operational powers equivalent to a head of department, including approval of expenditures and coordination with state agencies.[112] Supporting bodies include the Project Monitoring and Coordination Committee (PMCC), which tracks civil works, land acquisition, and rehabilitation activities for timely completion.[96] Accountability mechanisms emphasize technical scrutiny and external validation to address execution risks. The Central Water Commission (CWC) reviews dam designs and operational protocols, while the Central Soil and Materials Research Station (CSMRS) enforces quality control and assurance standards across construction phases.[96] Model studies for hydraulic performance are conducted by the Central Water and Power Research Station (CWPRS), and WAPCOS Limited serves as the Project Monitoring and Coordination Consultant, providing independent progress audits.[96] A third-party quality control framework, proposed by the PPA for headworks, left main canal, and right main canal, was implemented with agency selection in 2025 to enhance transparency amid persistent quality lapses, such as spillway foundation issues flagged by foreign experts.[113][34] Additional oversight includes periodic inspections by central parliamentary committees, as in January 2025, and interventions by the Andhra Pradesh Lokayukta for rehabilitation compliance, ensuring displaced families receive mandated compensation.[114][115]

Interstate Relations

Water Allocation Under Godavari Agreements

The Godavari Water Disputes Tribunal (GWDT), constituted in April 1969 under the Inter-State Water Disputes Act, 1956, to adjudicate claims among riparian states including Andhra Pradesh, Maharashtra, Karnataka, Madhya Pradesh, and Orissa, issued its final award on July 7, 1980. Rather than imposing fixed volumetric shares, the tribunal validated a series of pre-existing inter-state agreements negotiated between 1975 and 1979, which delineated utilizable quantities based on project-specific assessments and principles of equitable apportionment at 75% dependability flow. These agreements implicitly assigned utilizations totaling approximately 2,102 TMC from the basin's assessed 2,360 TMC dependable yield, prioritizing in-basin uses while permitting limited diversions subject to non-prejudicial impacts on co-riparians. For the Polavaram Project, the GWDT explicitly approved Andhra Pradesh's construction of the dam on the main Godavari stem and its utilization for irrigation, hydropower, and inter-basin transfer, confirming that upstream tributary projects by other states would not diminish flows available at the Polavaram site. The tribunal authorized the diversion of up to 80 TMC of surplus Godavari water at 75% dependability through Polavaram's canals to augment irrigation in the Krishna basin, particularly the Krishna delta, without altering upper riparian entitlements.[116][25] This diversion quantum was calibrated to harness monsoon excesses post in-basin allocations, with the project reservoir designed to store 75.2 TMC live capacity for regulated releases.[6] In-basin allocations under the endorsed agreements permitted Andhra Pradesh to draw from Godavari flows for Polavaram's irrigation command of about 320,000 hectares across upland areas, stabilizing delta ayacut below Dowleswaram barrage, and 960 MW hydropower generation, with annual consumptive use estimated at 23-30 TMC net after return flows. The framework required Andhra Pradesh to maintain minimum flows for downstream ecology and navigation, while upper states like Maharashtra and Madhya Pradesh secured protections for their tributary abstractions totaling around 753 TMC combined. Post-2014 bifurcation, these pre-bifurcation entitlements under GWDT continue to underpin Andhra Pradesh's Polavaram operations, though implementation amid Telangana's claims has invoked supplementary bilateral talks without altering core tribunal approvals.[25].pdf)

Disputes with Telangana

The disputes between Andhra Pradesh and Telangana over the Polavaram Project intensified after the 2014 bifurcation of Andhra Pradesh, with Telangana expressing concerns over land submergence in its Khammam district, particularly around Bhadrachalam, due to the project's full reservoir level (FRL) operations. Telangana officials have highlighted that construction activities have accelerated floodwater flow towards upstream areas, reducing the time for flood peaks to reach Bhadrachalam from several days to hours, thereby increasing inundation risks during monsoons.[117][118] In April 2025, Telangana objected to ongoing works without adequate mitigation for submergence-related impacts, prompting calls for joint surveys to assess affected areas and ensure proper rehabilitation.[118] A major flashpoint emerged in 2025 over Andhra Pradesh's proposed Polavaram-Banakacherla Link Project (PBLP), which seeks to divert approximately 200 thousand million cubic feet (TMC) of surplus Godavari water from the Polavaram reservoir to the Krishna basin via a new canal and lift irrigation system in water-scarce Rayalaseema regions. Telangana contends that the PBLP violates the 1980 Godavari Water Disputes Tribunal (GWDT) award, which mandates prior consent from co-basin states for any inter-basin transfers or modifications to Polavaram's design that could alter water levels or flows affecting upstream allocations.[119][120][121] The project, estimated at ₹82,000 crore, has faced opposition on grounds that it encroaches on Telangana's allocated Godavari share—fixed at 1,060.78 TMC under post-bifurcation arrangements—potentially exacerbating water scarcity in Telangana's drought-prone districts without mutual agreement.[82][122] In response, Telangana urged the Union Jal Shakti Ministry in June 2025 to withhold environmental and technical clearances for the PBLP, citing non-compliance with GWDT stipulations and risks to its irrigation commands dependent on Godavari inflows.[123] The Expert Appraisal Committee (EAC) under the Ministry of Environment, Forest and Climate Change temporarily rejected Andhra Pradesh's proposal in July 2025, pointing to unresolved submergence issues in upstream states and the absence of interstate consensus.[124] Andhra Pradesh proceeded with preliminary works despite the setback, leading Telangana to announce plans in April 2025 to approach the Supreme Court, arguing the initiative undermines the Andhra Pradesh Reorganisation Act's provisions for equitable resource sharing.[125] The Union government responded by constituting a high-level expert committee on July 17, 2025, to mediate the broader Krishna-Godavari water disputes, including Polavaram-related contentions.[126] Legal proceedings have included multiple petitions in the National Green Tribunal and Supreme Court, with Telangana seeking directives to enforce GWDT consent requirements for any Polavaram height adjustments or diversions that could backwater into its territory.[127] As of October 2025, Andhra Pradesh accelerated PBLP site activities amid Telangana's silence on direct intervention, though Maharashtra's support for Telangana's GWDT claims added interstate dimensions to the impasse.[128][82] These conflicts underscore ongoing tensions over Polavaram's upstream externalities, with Telangana prioritizing protection of its riparian rights against Andhra Pradesh's developmental imperatives.

Disputes with Odisha and Chhattisgarh

Odisha and Chhattisgarh have raised objections to the Polavaram Project primarily due to anticipated submergence of lands and villages from reservoir backwater effects, disproportionately affecting tribal populations without adequate prior consultation or mitigation. According to surveys conducted by Andhra Pradesh, the project could lead to submergence in these states upon completion, prompting demands for comprehensive backwater studies and design revisions.[129] The disputes stem from the project's location on the Godavari River, where upstream storage and altered flood discharge capacities are expected to cause perennial inundation in downstream riparian areas.[130] In Odisha, particularly Malkangiri district, opposition intensified over risks to eight villages and approximately 1,005 families, with earlier estimates indicating 7,656 hectares of land submergence, including forest areas, potentially displacing over 6,800 residents, of whom 5,916 are tribals.[131][130] The Biju Janata Dal (BJD) has protested design modifications that increased the flood discharge capacity beyond the original 36 lakh cusecs—citing studies projecting peaks of 50 to 58 lakh cusecs, raising reservoir levels to 216-232 feet, exceeding the interstate-agreed maximum of 174.22 feet and exacerbating backwater flooding.[130] BJD delegations submitted memoranda to the Central Water Commission (CWC) on December 16, 2024, and the Ministry of Tribal Affairs on August 21, 2025, urging suspension of works until Odisha's concerns, including unaddressed tribal impacts, are resolved through independent studies.[130][132] Odisha's government, including Chief Minister Mohan Charan Majhi, has opposed the project in principle, rejecting proposed 30 km embankments as insufficient against flood risks, with public hearings still pending.[133][130] Chhattisgarh's concerns mirror Odisha's, focusing on submergence of up to 10 villages and associated tribal displacements, with the state filing a suit against the project as early as August 2011 under its then-BJP government.[134][135] The central government has suggested 29.12 km of embankments for mitigation, but Chhattisgarh joined Odisha and Telangana in Supreme Court petitions challenging regulatory compliance, environmental clearances, and lack of riparian state involvement in design alterations.[130][136] These legal challenges, ongoing as of May 2025, demand consultations and redressal before further construction, amid broader calls from joint action committees in March 2025 for halting works until all submergence issues across affected states are settled.[137][138] The disputes trace back to the 1980 Godavari Water Disputes Tribunal award, which did not fully anticipate post-construction modifications, leading to assertions that Andhra Pradesh proceeded unilaterally.[130]

Controversies and Critiques

Environmental and Ecological Concerns

The Polavaram Project's reservoir is projected to submerge approximately 3,731 hectares of forest land, resulting in direct deforestation and habitat fragmentation across Andhra Pradesh and neighboring states. This submergence threatens carbon sequestration capacity and disrupts ecological connectivity in the Eastern Ghats region. Construction activities have contributed to accelerated forest degradation, with studies documenting loss of biological resources including medicinal plants, timber species, and understory vegetation essential for soil stability.[139] Biodiversity impacts are pronounced, with habitat loss affecting endangered mammals such as sloth bears (Melursus ursinus) and tigers (Panthera tigris), whose populations face degradation from reduced foraging areas and increased human-wildlife conflict post-impoundment.[140] The submergence area encompasses habitats for vulnerable, threatened, and rare species, including otters, pangolins, and various avifauna, leading to estimated declines in local faunal diversity without adequate translocation or corridor provisions. Aquatic ecosystems face risks from altered hydrology, including sedimentation buildup that could smother benthic habitats and reduce fish spawning grounds in the Godavari River.[139][140] Proximity to protected areas like Papikonda National Park amplifies concerns, as backwater effects and construction-induced land use changes have correlated with 12% forest loss within the park boundaries between 1991 and 2014, potentially fragmenting tiger corridors and migratory bird routes.[141] Submergence of graphite mines poses additional risks of heavy metal leaching into the reservoir, contaminating water quality and endangering downstream aquatic life and fisheries dependent on the Godavari delta.[142] Environmental impact assessments have identified these issues but note gaps in long-term monitoring data, with mitigation measures like compensatory afforestation often criticized for inadequate species matching and survival rates in comparable projects.[140]

Displacement, Rehabilitation, and Social Costs

The Polavaram Project is projected to displace approximately 96,660 families across 373 habitations in Andhra Pradesh, with significant impacts on scheduled tribe communities, including the Koya and Konda Reddi groups. Official estimates indicate submergence of up to 276 villages, primarily tribal-dominated areas, though recent assessments have expanded the affected zones to include additional habitations due to backwater effects and revised contour levels. This displacement affects over 177,000 individuals, with tribal families comprising a substantial portion, such as 3,093 out of 5,618 families in Devipatnam Mandal alone. Interstate ramifications extend to potential submergence of eight villages in Odisha and additional areas in Chhattisgarh, exacerbating cross-border social disruptions.[143][144] Rehabilitation efforts, mandated under the Land Acquisition, Rehabilitation and Resettlement Act, 2013, include a "land-for-land" policy promising equivalent agricultural land, housing, and livelihood restoration, but implementation has lagged. As of September 2025, Andhra Pradesh officials pledged phased rehabilitation adhering to norms, with Phase I targeting up to +41.15 meters contour affecting 20,946 families, of which only 6,351 had been relocated by late 2021. Public interest litigation in the Andhra Pradesh High Court has highlighted deficiencies, including incomplete compensation and flooded resettlement colonies during 2022 monsoons. In March 2025, Chief Minister N. Chandrababu Naidu announced accelerated resettlement, yet reports indicate persistent gaps, with many displaced families facing interim insecurity and unfulfilled promises of infrastructure in new sites.[143][145][12] Social costs manifest in profound impoverishment risks, particularly for tribal populations reliant on forest-based livelihoods and subsistence agriculture, leading to economic marginalization and cultural erosion. Displaced communities experience severed kinship networks, loss of traditional practices like Gussadi dance among affected tribes, and heightened vulnerability to poverty, as rehabilitation often fails to replicate pre-displacement self-sufficiency. Studies document increased uselessness and social fragmentation, with incomplete relocation compounding health, education, and employment deficits in transit camps. These outcomes underscore causal links between large-scale hydraulic infrastructure and involuntary displacement's long-term societal toll, disproportionately borne by indigenous groups despite project benefits accruing elsewhere.[146][147]

Allegations of Corruption and Inefficiency

The Polavaram Project has been subject to multiple allegations of corruption, particularly in land acquisition and contract execution. In October 2022, Devipatnam police registered cases against two Polavaram Irrigation Project officials and 27 others for allegedly diverting Rs 195 crore in land acquisition funds, with investigations revealing irregularities in compensation disbursals.[148] An RTI response in the same year exposed payments of Rs 6 crore to 21 fake farmers claiming 82 acres, highlighting fraudulent claims in the rehabilitation process.[149] A 2013 CAG audit further indicted the project for massive irregularities in irrigation schemes, including Polavaram, pointing to cost inflations and procedural lapses that enabled undue benefits to contractors.[150] Contractor-related scandals have also surfaced, such as the CBI probe into Transstroy India Ltd., a Hyderabad-based firm, for alleged bank fraud exceeding Rs 7,900 crore linked to overstated work claims on Polavaram packages; site verification showed only Rs 576 crore in actual progress against billed Rs 751 crore as of 2020.[151] Political figures have amplified these claims, with BJP Andhra Pradesh president D. Purandeswari stating in December 2023 that the project served as a "rich source of money for corrupt politicians," while Congress leader Chinta Mohan accused both TDP and YSRCP governments of graft driving cost escalations in January 2025.[152][153] Activists in 2018 described systemic corruption, noting that evidence of graft was often dismissed as isolated incidents despite patterns in tendering and oversight.[154] The Union Ministry of Jal Shakti denied widespread graft in June 2020, asserting no illegalities in execution based on its review.[155] Inefficiency allegations center on chronic delays and cost overruns, with the project, initiated in 2005, originally budgeted at Rs 10,151 crore but revised to over Rs 50,000 crore by 2023 due to inflation, contractor changes, and administrative hurdles.[156][157] Progress on critical components like the diaphragm wall has lagged, with international experts in August 2025 criticizing the slow pace as risking further timeline slippages, despite recommendations for quality controls.[158] CAG reports from 2018 attributed overruns in national water projects, including Polavaram, to poor contract management and delays escalating costs from Rs 3,530 crore baseline to multiples thereof.[159] Andhra Pradesh Chief Minister Y.S. Jagan Mohan Reddy extended the completion deadline to 2025 in August 2023, blaming TDP mismanagement, while YSRCP leaders in September 2025 cited "wrong priorities" under previous regimes for halting works.[160][161] These issues reflect broader governance challenges in large-scale infrastructure, where frequent political transitions and inadequate oversight have compounded inefficiencies.[162]

Future Prospects and Extensions

Integration with River Linking Initiatives

The Polavaram Project functions as a critical upstream reservoir in the Godavari (Polavaram)–Krishna (Vijayawada) link canal, a component of India's National River Linking Project (NRLP) under the Peninsular Links division, enabling the diversion of surplus Godavari waters to the water-stressed Krishna basin.[163] This integration aims to transfer approximately 5,325 million cubic meters (Mm³) of water annually through a proposed link canal originating from the Polavaram right main canal near Vijjeswaram and terminating near Vijayawada on the Krishna River, supporting irrigation expansion in Andhra Pradesh's drought-prone Rayalaseema and Krishna delta regions.[69] The project's design incorporates headworks including a barrage, navigation lock, and powerhouses to facilitate this inter-basin transfer, with Polavaram's reservoir providing regulatory storage to mitigate seasonal floods in the Godavari while optimizing downstream allocations.[1] Andhra Pradesh has actively pursued this linkage as part of its state-led initiatives, including the Polavaram-Banakacherla Head Regulator project, which seeks to channel Godavari floodwaters into the Krishna basin via an 80 TMC (thousand million cubic feet) diversion, estimated at ₹80,112 crore, explicitly tying it to national river interlinking goals for enhanced water security and hydropower generation.[11] The state government initiated construction elements of the link canal in 2024, leveraging Polavaram's infrastructure to preemptively enable transfers, though federal oversight requires interstate consensus under the NRLP framework, which has stalled broader implementation due to riparian disputes.[164] Proponents argue this setup could irrigate an additional 1.2 million hectares in the Krishna basin by balancing monsoonal surpluses against deficits, drawing on hydrological data showing Godavari's average annual yield exceeding allocated shares.[165] Further integration envisions Polavaram as a hub for cascading links, such as potential extensions to the Pennar and Cauvery basins via Krishna intermediaries, aligning with the NRLP's objective to interconnect 30 major rivers through 16,000 kilometers of canals for nationwide flood moderation and drought alleviation.[166] However, progress remains contingent on Detailed Project Reports (DPRs) validated by the National Water Development Agency (NWDA), with the Godavari-Krishna segment's feasibility affirmed in 2000 but delayed by environmental clearances and state-level allocations under the 2015 Godavari Water Disputes Tribunal award.[167] Andhra Pradesh's autonomous advancements, including the operational Pattiseema lift scheme diverting 70 TMC since 2014 as a precursor, underscore Polavaram's role in unilateral water optimization amid federal hesitancy.[168]

Additional Irrigation and Power Projects

The Pattiseema Lift Irrigation Project, operational since 2015, functions as a supplementary scheme to the Polavaram Project by diverting Godavari River water to Krishna delta canals, irrigating around 2 lakh hectares in water-scarce regions of Andhra Pradesh.[169] This lift irrigation system pumps up to 240 cubic meters per second from the Godavari near Pattiseema village, leveraging existing Polavaram right bank canal alignments to transfer approximately 70-80 thousand million cubic feet (TMC) of water annually during surplus periods.[170] Constructed at a cost of about Rs 1,300 crore, it mitigates drought impacts in Krishna and West Godavari districts pending full Polavaram reservoir utilization.[169] Proposed extensions include the Banakacherla Lift Irrigation Project, which seeks to channel surplus Polavaram waters into the Krishna basin for Rayalaseema's arid zones, targeting irrigation for additional lakhs of hectares through a 416 km infrastructure of canals, tunnels, pipelines, and multiple lift points.[171] Estimated at Rs 82,000 crore, the initiative plans to divert 200 TMC of floodwater yearly by upgrading the Polavaram Right Main Canal from 17,500 to 38,000 cusecs capacity and constructing reservoirs like Banakacherla on the Krishna River.[172] As of 2025, the project faces interstate disputes with Telangana over water shares and environmental clearances, with Andhra Pradesh advocating its role in balancing inter-basin water deficits.[173] On the power front, while the core Polavaram hydropower station targets 960 MW output via 12 units of 80 MW each, the reservoir's creation supports downstream enhancements and potential pumped storage developments to augment renewable energy capacity.[174] Seven units were slated for commissioning by 2024-25 to contribute to Andhra Pradesh's grid, generating an estimated 4 billion kWh annually from the project's hydro resources.[54] Further proposals, such as integrating with regional pumped hydro projects like the 1,350 MW Upper Sileru facility, aim to leverage Polavaram's stabilized flows for improved energy storage and peak demand management.[175]

Long-Term Risks and Policy Recommendations

One primary long-term risk associated with the Polavaram Project is reservoir sedimentation, which could diminish storage capacity by trapping silt from the Godavari River's upper catchment, potentially reducing effective water volume for irrigation and power generation within decades. Studies indicate that dams in the Godavari basin, including upstream structures, already contribute to sediment retention, exacerbating downstream delta erosion and shoreline recession by limiting nutrient-rich silt delivery to coastal ecosystems. This process has been observed in analogous Indian river systems, where reduced sediment flux leads to subsidence and loss of agricultural productivity in deltas over 20-50 years.[176][20] Hydrological alterations pose additional risks, including modified flood regimes and water quality degradation from stagnant reservoirs, which may foster algal blooms and impair downstream fisheries and biodiversity. Expert analyses highlight inadequacies in initial environmental impact assessments for appraising these prolonged effects, such as shifts in aquatic habitats and terrestrial ecosystems spanning affected tribal forests. Climate change amplifies vulnerabilities, with projected erratic monsoons potentially causing inflow deficits during dry periods or overflow risks during extremes, as large dams have shown limited adaptive capacity in Indian contexts.[177][15] Persistent construction quality deficiencies, including seepage and material failures reported as recently as 2024, raise concerns over structural longevity and dam safety in a region classified under seismic zones II-III, where cumulative stresses from reservoir loading could precipitate cracks or breaches over operational lifespans exceeding 100 years. Financial unsustainability looms from cost overruns—now estimated over ₹1 lakh crore—and dependency on federal funding amid inter-state disputes, potentially straining Andhra Pradesh's fiscal health if benefits underperform due to these factors.[34][178] Policy recommendations emphasize establishing an independent, multi-disciplinary oversight body for continuous monitoring of sedimentation rates, ecological indicators, and structural integrity, with mandatory annual audits incorporating satellite and ground data to enable proactive interventions like selective reservoir flushing. To mitigate delta erosion, protocols for controlled sediment release during monsoons should be integrated into operations, informed by basin-wide hydrological modeling that accounts for upstream dams and land-use changes.[176] Enhancing project viability requires enforcing water-use efficiency standards in irrigated command areas, targeting reductions in evapotranspiration losses through drip systems and crop diversification, which could extend benefits amid variable inflows. Rehabilitation frameworks must evolve beyond one-time compensation to include long-term livelihood programs, such as skill training for displaced communities, verified through third-party evaluations to address documented shortfalls in forest rights and social equity. Finally, mandating transparent procurement and real-time digital tracking of expenditures, as suggested by expert panels, would curb inefficiency risks while fostering inter-state collaboration via updated Godavari Water Disputes Tribunal mechanisms for equitable allocation adjustments.[179][34]

References

User Avatar
No comments yet.